Project Monitoring & Control
Project Monitoring & Control
Content
Introduction Controlling concept Planning Schedule Project Lift Cycle Project controlling system
Thus, Project Monitoring & Control process becomes one of the key processes of Project Management.
Initiation
Executing
Controlling Finish
Planning
Controlling
Executing
Finish
Project Monitoring
Project Monitoring is Tracking of :
the scope
time schedule project cost and resources
Project Monitoring
It is the process used by the project team to ensure the team is making satisfactory progress
Project Control
It is taking corrective action to reduce difference between plan & reality, to achieve a balance between Cost, Time & Performance parameters of the project.
Project Schedules
Master Programme
Schedule Of Revenue Schedule Of Milestone Events Schedule Of Plant And Machinery Schedule Of Staff Schedule Of Labor Schedule Of Materials Schedule Of Specialized Agencies Schedule Of Direct Cost Schedule Of Indirect Cost Schedule Of Liquidity
Master Programme
Construction Schedule
With all activities along with all the connectivity to other tasks
Helpful in tracking the project through out the project life cycle
Master Programme
Take account of all the activities to be carried out in the respective month
Cumulative cost when plotted against the time will generate the S-Curve of invoice
Unit
Rate
Qty
M1
M2
M3
M4
M5
M6
01
Useful
for higher Management to review the Project progress as it provides the overview of the project condition
Takes
When
plotted along the planned dates as per Master Construction Programme will exhibit the delay in terms of time
SL NO
MILESTONE EVENT
START DATE
FINISH DATE
REMARKS
1 2 3 4
CASTING OF BASEMENT ROOF SLAB (Main Building) CASTING OF BASEMENT ROOF SLAB (Future block) CASTING OF GROUND FLOOR ROOF SLAB CASTING OF 1ST FLOOR ROOF SLAB
5
6 7 8 9
10 11 12 13 14
Takes record of all the major Plant & Machinery employed either own or hired
Helpful in scheduling the release of a particular machinery from one project to other
Release Dt
Remarks
Schedule Of Staff
Traces the requirement and release of the most important resource i.e. Manpower
Helpful in restricting the staff at the project location and hence the overhead cost
Schedule Of Staff
Requirement Sl.No. 1 2 3 Description CONSTRUCTION MANAGER PLANNING ENGINEER BILLING ENGINEER SITE WORKS 1 2 3 SITE ENGINEER : DAY SHIFT SITE ENGINEER : NIGHT SHIFT FINISHING ENGINEER REINFORCEMENT 1 REINFORCEMENT IN-CHARGE FORMWORK ENGINEER 1 2 FORMWORK ENGINEER CARPENTRY FOREMAN SERVICES 1 2 3 QA/QC ENGINEER SAFETY ENGINEER P & M MECHANICAL ACCOUNTS / ADMIN 1 2 3 ACCOUNTANT TIME KEEPER STORE KEEPER Name From To Reported On Remarks
Schedule Of Labor
Most important as it optimizes the head count of labor of both skilled and unskilled type
Absence of tracking of the labor count may lead to delay in planned activities
Helpful in deciding the shifting and release of the labor at any point of the time throughout the project cycle
Schedule Of Labor
SL NO
CATEGORY OF WORKMEN
M1
M2
M3
M4
M5
M6
UNSKILLED WORKMEN
MASONS
MASON HELPER
CARPENTERS
CARPENTER HELPERS
REINFORCEMENT FITTERS
FITTER HELPERS
GRAND TOTAL
Schedule Of Materials
Helps in restricting the storage space at the Project by optimizing the quantity of material
Schedule Of Materials
SL NO MATERIAL DESCRIPTION UOM TOTAL QTY M1 M2 M3 M4 M5 M6
QTY 1 2 3 4 5 6 7 8 9 10 11 12 15 13 14 15 CEMENT SAND - MEDIUM SAND - FINE REINFORCEMENT STEEL STRUCTURAL STEEL 200 MM THK SOLID BLOCKS 100 MM THK SOLID BLOCKS SOLING STONE - 6" 40MM AGREGATE 20MM AGREGATE QUARY DUST RED MURRUM KOTTA CERAMIC TILE VERTIFIED TILE MOSAIC BAGS CUM CUM MT MT NOS NOS CUM CUM CUM CUM CUM SQM SQM SQM SQM
QTY
QTY
QTY
QTY
QTY
Take account of the schedule of the specialized works such as Waterproofing, Anti-termite Treatment, Mosaic flooring, testing & commissioning of control & relay panels (electrical) etc.
Helpful in accessing the time to start the process of selection of Specialized Agencies in good time
6
7 8 9 10 11 12
RM T
SQ M SQ M
A price that can be completely attributed to the production of specific goods or services is the Direct Cost
Direct costs refer to materials, labor and expenses related to the production of a product.
Indirect costs are costs that are not directly accountable to a cost object (such as a particular project, facility, function or product. These are those costs which are not directly related to production. Indirect costs may be either fixed or variable. Indirect costs include administration, personnel and security costs.
Other
costs, such as depreciation or administrative expenses, are more difficult to assign to a specific product, and therefore are considered indirect costs.
In accordance with the schedule of Invoice and Master Construction Programme gives the capital requirement for the current month
Should be handled carefully as any missing part may lead to financial disorders
MISCELLANEOUS WORKS
PART C : ROAD WORKS EXCAVATION ROAD PAINTING STORM WATER DRAIN WORKS COMPOUND WALL Cum Sqm Mtr Rmt
17
18 19 20 21
SUNDRIES
SECURITY CHARGES SAFETY EXPENSES TEMP. STRUCTURES LABOUR COLONY TOTAL
The essential meaning of project controlling is to guarantee the final realization of project objectives
No controlling is needed without a target !!!
The project has been base lined and work has started Is everything going according to plan? Next step in the process: figure out your status figure out the problems figure out what you need to do to fix them figure out what the impact might be
BCWS
BCWP $
time
REVISED PLAN
Material consumption
Quality and safety
Controlling Factors
Reduce time - Increase cost Reduce time - Improve cost-effectiveness Improved quality Reduce maintenance cost
Cost
Objective Triangle
Time
Higher quality Less time
Quality
The Main tasks of controlling is to approach the balance of project objectives systematically in a conflicting situation
written status reports Progress status- planed to actual progress updates regarding the action required, risks, problems, and issues comparisons of actual costs to budgeted costs, The cost/benefit analysis from the starting
Controlling Points
Selection of controlling point should be based on the controlling target, method, and personnel
Project information
Controlling cycles
Functional tasks
be project objective oriented be based on the nature of the project of variety of controlling areas and procedures
be depicted as a three-dimensional framework Project functional tasks Project information Controlling cycles of the controlling tasks can be organized within this framework
All
Controlling System
Project
information Various project data generated from whole process tasks Different tasks carried out by various functional positions
Functional
Market Price
Controlling
Quality Stand.
Scheduled Date
Objective Controlling
Method of Comparison
Dynamic Controlling
Assumption: An accurate management control system yields accurate data Basic principles: Report on periodic basic Weekly Monthly
Only ask for the data that you really need and use Tailor the data to match how youre managing
Key
Role
of Stack holder
Strategy
of Organisation
Plan
Scope
Milestones
/ Project Status
Comparisons
Action
Plan
Charter
Project
Frame Work
A formal
document providing authority to a project manager to conduct a project within scope, quality, time and cost and resource constraints as laid down in the document. usually includes a mission statement, including background, purpose, and benefits, a goal, objectives, scope, assumptions and constraints.
It
It
Project Framework
Project Title:
Project description:
One sentence to describe the project
End date:
What triggered the start of the project? What are the goals/objectives of this project? Why are we undertaking it? All projects start with a business problem/issue to solve
Project Framework
The main risks:
What are the barriers to achieving project success (ie the major risks)? For each of these risks, what steps will be undertaken to minimize them?
Stakeholders:
Client (sponsor): Project Manager: Project team: Steering committee: Other stakeholders: Groups who will impact the project or be impacted by the project and describe how they will be engaged. Tasks already started:
Milestones:
Date
Key deliverable
Charter
Project
Frame Work
Scope
Design Reviews
Budgets
Reviews
Planning
Reviews
Risk Analysis
/ Action Plan
Plans
Risk Analysis
Value Additions Productivity Budget
Review Procedures
Closeout
Cost
time
technical
What is EVMS?
A project management technique for measuring project performance and progress in an objective manner.
It
In
a single integrated system, Earned Value Management is able to provide accurate forecasts of project performance problems, which is an important contribution for project management.
spent to date: rs64,000 time elapsed: 6 months units produced: 8 complete, 2 partial
How
How
are you doing, and how do you know how you are doing?
far along are you? (64%, 50%, >40%)
Progress = Movement Forward to measure progress, there must be a standard against which the forward movement may compared
be
measurement baseline
Value is key concept - how much progress did I make against my original plan? - expressed in cost or time
baseline
cost
earned value
time
BCWP
How much did this done work cost? What was the total job supposed to cost? What do we now expect the total job to cost?
ACWP
BAC
Estimate at Completion
EAC
Analysis of Variances
BCWP - BCWS
SV (%) =
100%
Cost Variance
CV ($)
BCWP - ACWP
CV (%) =
100%
Schedule Status
TIME NOW
BCWS
BCWP
MONTHS BEHIND
contractor gain
Negative VAC: EAC > BAC share area contractor partial loss EAC > ceiling overrun contractor loss (100%)
Government
develops top level EAC for comparison government will limit progress payments if EAC is greater than ceiling government needs forecast of fund requirements still have time to change the final outcome
May