ENGINEERING
,PROCUREMENT,CONSTRUCTION
(EPC)PROJECT AT ONGC PLATFORM – STUDY
PRAVIN POHANE MMS (OPERATIONS)
SEM III
Mumbai High Field located about 165 km from
Mumbai base
ØNQD is well cum process
platform.
ØTo increase the
production from North
field of Mumbai High, an
additional well fluid
handling facility to be
created on NQD platform
UNMAN PLATFORM
OIL WELLS
RIG OVER
UNMAN
PLATFORM
NQD ENHANCEMENT PROJECT
•OWNER : OIL & NATURAL GAS CORPORATION LTD.
•LOCATION : MUMBAI HIGH NORTH FIELD
•PROJECT DESCRIPTION : 1) PRE-ENGINEERING SURVEY
2) DESIGN ENGINEERING
3) PROCUREMENT
4) FABRICATION
5) LOADOUT, SEA FASTENING
6) TRANSPORTATION
7) INSTALLATION, HOOK UPS
8) TESTING,COMMISSIONING
•LUMPSUM COST : Rs. 178.38 Crores.
•AWARD DATE : 05.09.2008
PROJECT OBJECTIVES
• To study overall project.
• To study different activities involved
in it.
• To study progress reports & analyze
the performance of activities.
• To find causes of delay in project
activities.
• To suggest possible solutions for
better project management in
future.
TEST SURGE
SEPARA TANK
TOR
PROJECT MILESTONES &
COSTWISE WEIGHTAGES
SURVEY
1. Pre Engineering Survey.
3. Pre Installation / Construction
Survey.
5. Post Installation Survey.
STUDY & ANALYSIS
OF DESIGN ENGINEERING
Vendo
r
DESIGN APPROVAL STATUS
DESIGN
ENGINEERING ANALYSIS
OBSERVATION
S
• Inexperienced
Design
Engineering staff.
• Lack of Co
ordination.
• Lack of
monitoring.
OFFSHORE ACTIVITIES
2. Mobilization Activity.
4. Project Activity.
6. Demobilization Activity.
MARINE VESSELS INVOLVED
SUPPLY BOAT
ACCOMODATION BARGE
TUG BOAT PULLING DUMB
BARGE
ANALYSIS OF
MOBILIZATION ACTIVITY
Stand BY :6 Days
Clearance /Approval:
3days
ANALYSIS OF
PROJECT ACTIVITY
ANALYSIS OF
DEMOBILIZATION ACTIVITY
PROJECT PERFORMANCE CURVE
Analysis of
Project Performance Curve.
1) Delay in approval of final
drawings, purchase
specifications.
2) Late delivery of long lead items
like separator, surge tank & other
imported piping material.
3) Fabrication catch up plan for
24X7.
4) Offshore activity performance was
PROPOSED PROJECT
PLAN ON MS PROJECT.
ACTUAL PROJECT
PLAN ON MS PROJECT.
POSSIBLE SOLUTIONS
FOR DESIGN ACTIVITY
• Centralized Design Engineering
Team.
• Design Agency to deploy engineer to
DOEIL base.
• Formats of reports to review.
FOR PROCUREMENT ACTIVITY
• Approved Purchase Specifications
given to vendors in time.
• Vendor Development program.
POSSIBLE SOLUTIONS
FOR MOBILIZATION ACTIVITY
• Marine activity Planning well in
advance.
• Fully dedicated logistic Team.
FOR OFFSHORE ACTIVITY
• Planning for next day work.
• Equipment Break down to minimize.
• Estimation for effective man hours.
BIBLIOGRAPHY
BOOKS
• Operations Research – HIRA GUPTA
• Fundamentals of Project management- LEWIS
JAMES
PROJECT REPORTS STUDIED
• Daily Progress Report (DPR)
• Weekly Progress Report (WPR)
• Monthly Progress Report (MPR)
• Document Control Index (DCI)
• Marine Log Book.