System Formwork
System Formwork
Presentation by:
Rachna Rajput
(1030227)
08/28/09 1
LARSEN & TOUBRO LIMITED
ECC DIVISION
LUDHIANA CITY CENTRE
CONSTRUCTION OF RCC BASEMENT STRUCTURE
08/28/09 2
By : A.K. Mishra
THE CLIENT: TODAYHOMES AND
INFRASTRUCTURE
JOINT VENTURE WITH
LUDHIANA
IMPROVEMENT TRUST
08/28/09 3
LUDHIANA CITY
CENTRE
LOCATED IN HEART OF LUDHIANA
BUILT ON 25 ACRES OF LAND
4 SIDE OPEN PLOT
MAXIMUM NUMBER OF CAR PARKS UNDER
ONE ROOF
ONLY DEVELOPMENT OF INDIA WITH 5 STAR
HOTEL,SHOPPING MALL,IT/OFFICE
SPACE,HEALTH CARE,LIBRARY,MUESEAM
UNDER 1 ROOF
BIGGEST ATRIUM:2 LAKH SQUARE FEET
08/28/09 4
LUDHIANA CITY CENTRE
CONSTRUCTION OF RCC BASEMENT
STRUCTURE
Project Highlights
JOB VALUE : 12400 lacs
DATE OF LOI: 30:1:2006
DATE OF COMMENCEMENT: 15:02:2006
DATE OF COMPLETION: 14:02:2007
DURATION OF
PROJECT : 12 months
08/28/09 5
THE WORK
08/28/09 6
WHAT IS
FORMWORK?
FORMWORK IS A MOULD USED TO SHAPE
CONCRETE UNTIL IT ATTAINS SUFFICIENT
STRENGTH TO CARRY ITS OWN WEIGHT
CAN BE ASSEMBLED BY UNSKILLED
LABOUR
08/28/09 9
SYSTEM
FORMWORK-L&T
EARLIER CALLED DOKA
FORMWORK
INVERSIBLE
FAST ERECTION
MORE STABLE
SAFE IN USE
08/28/09 10
FORMWORK
STEP1.) PLANNING
CONFIRMING HQ ON THE NEW JOBS BAGGED
CONSTRUCTION PROJECT
STEP2.)
FINALIZING FORMWORK MATERIALS
08/28/09 11
CONTD….
RECEIVING NEW TARGETS ON
PRODUCTIVITY FROM HQ
08/28/09 12
COMPONENT DETAILING
FOUNDATION FORMWORK
HDT TOWER
SLAB/BEAM FORMWORK
WALL/COLUMN FORMWORK
08/28/09 13
FOUNDATION
FORMWORK
STEEL PANELS OF STANDERED SIZES
MINIMIZE MAKING AT SITE
USE OF VERSATILE COMPONENTS LIKE
STEEL WALERS(2 ISMC BACK 2BACK) AND
ALIGNMENT PROPS
EASY ASSEMBLY WITH DIMENSIONAL
ACCURACY
08/28/09 14
08/28/09 15
FOUNDATION
FORMWORK MATERIAL
CONTD.
08/28/09 16
CONTD…
08/28/09 17
CONTD….
08/28/09 18
AFTER ERECTION
Steel panel
Pipe waler
clamp
Pipe waler
Alignment
prop
welar
08/28/09 19
HDT TOWER
BASIC FRAME
HORIZONTAL BRACE
DIAGNOL BRACE
TAKES LOAD OF 250KN
HIEGHT ADJUSTMENTS UPTO 800MM
POSSIBLE
TRANSPORT DEVICES CAN BE ATTATCHED
08/28/09 20
COMPONENT
DETAILING
08/28/09 21
CONTD….
08/28/09 22
AFTER ERECTION
Coupler and
spring lock pin
Foot plate
Tower
spindle
08/28/09 23
WALL/COLUMN
FORMWORK
SHOP MADE SHUTTER
08/28/09 24
COMPONENT
DETAILING
08/28/09 25
CONTD….
08/28/09 26
CONTD……
08/28/09 27
COLUMN FORMWORK
WORKING AT 4.8M
HIEGHT
08/28/09 28
COLUMN FORMWORK
08/28/09 29
WALL FORMWORK 1.8M
HIEGHT
08/28/09 30
SLAB/BEAM
FORMWORK
SHEATHING MEMBER
H-BEAM(SECONDARY MEMBER)
WELAR(PRIMARY MEMBER)
HDT TOWER
08/28/09 31
AFTER
ERECTION
Sheathing
H-beam
welar
tower
08/28/09 32
DESIGN OF
FORMWORK
FORMWORK MUST SUPPORT ALL THE
VERTICAL AND LATERAL LOADS
ALL LOADS ARE ASSUMED TO BE
UNIFORMLY DISTRIBUTED
BEAMS SUPPORTED OVER 3 OR MORE
SPANS ARE TAKEN AS CONTINUOUS
APPROXIMATE FORMULAE ARE USED
08/28/09 33
AN IMPORTANT
POINT
SHEATHING SPAN DECIDES H-BEAM SPACING
08/28/09 34
DESIGN PROCEDURE
EXAMPLE
LOADS TO BE TAKEN
DEAD LOAD(1)
(THICKNESS OF MEMBER*DENSITY OF
CONCRETE)
LIVE LOAD(2)
SELF WEIGHT(3)
DESIGN LOAD,W=(1)+(2)+(3)
08/28/09 35
DESIGN PROCEDURE
CHECKS TO BE APPLIED
BENDING MOMENT CONDITION
SHEAR FORCE CONDITION
DEFLECTION CONDITION
THE MINIMUM OF ALL 3 SPANS IS
TAKEN AS SPAN FOR THE MEMBER
ACCORDING TO HEIGHT OF WALL OR
COLUMN THE REQUIRED LENGTH OF
H-BEAM(AN I SECTION )
HIGH STRENGTH TIE SYSTEM BEAR
LARGE CONCRETE PRESSURE
08/28/09 36
DESIGN PROCEDURE
CONTD….
DESIGN DONE FROM TOP TO BOTTOM
1. SHEATHING MEMBER
2.H-BEAM(SECONDARY MEMBER)
3.WELAR(PRIMARY MEMBER)
HDT TOWER
08/28/09 37
SELF WEIGHT OF CONCRETE WITH
REINFORCEMENT=25KN/M^3
08/28/09 38
SHEATHING MEMBER:
END CONDITION ASSUMED TO BE A PROPPED
CANTILEVER
BM=W*L^2/8<=.2KNM/M
SHEAR=5*W*L/8<=6.16KN/M
DEFLECTION=W*L^4/(185*E*I)<=1.852*10^-3M
MINIMUM OF ABOVE THESE 3 SPANS IS TAKEN
AS SPACING BETWEEN H-BEAMS
08/28/09 39
SECONDARY MEMBER(H BEAM):
END CONDITION IS ASSUMED TO BE SIMPLY
SUPPORTED
LOAD INTENSITY =DESIGN LOAD*SPAN OF
SHEATHING MEMBER
BM=W*L^2/8<=3KNM
SHEAR=W*L/2<=6KN
DEFLECTION=5*W*L^4/(384*E*I)
08/28/09 40
WELAR (PRIMARY MEMBER)
SIMPLY SUPPORTED END CONDITION IS
ASSUMED
NOW WIDTH OF LOADING IS THE SPAN FOR
SHEAR=W*L/2<=103.4KN/M
DEFLECTION=5*W*L^4/(384*E*I)<=6.67*10^-3
08/28/09 41
08/28/09 42
DESIGN FOR
WALL/COLUMN
FORMWORK
CONCRETE EXERTS A FLUID PRESSURE Dh
ON THE FORMWORK
Pmax=
D[C1*R^.5-(C2*K*(H-C1*R^.5)^.5) OR
Dh
whichever is smaller
VALUE OF C1
FOR WALLS=1
FOR COLUMNS=1.5
08/28/09 43
VALUE OF C2 DEPENDS ON CONSTITUENT
MATERIALS OF CONCRETE
D=WEIGHT DENSITY OF CONCRETE
H=VERTICAL FORM HIEGHT
h=VERTICAL POUR HIEGHT
K=TEMPERATURE COEFFICIENT TAKEN AS
(36/T+16)^2
R=RATE OF RISE M/H
T=TEMPERATURE OF CONCRETE AT PLACING
(degree celsius)
08/28/09 44
PRESSURE DISTRIBUTION DIAGRAM
Pmax/D
P max
08/28/09 45
DESIGN OF WALER –
DESIGNED AS LATERALLY
UNSUPPORTED BEAM
SIGMAbc=.66*Fcb*Fy/(Fcb^n+Fy^n)^1/n
Fcb=ELASTIC CRITICAL STRESS(N/MM^2)
08/28/09 47
SAFETY IN
FORMWORK
BEFORE ERECTION OF STEEL FRAME
STAGING THOROUGH INSPECTION
DIAGNOL BRACES SHOULD BE IN PROPER
POSITION
ALL CONNECTING DEVICES SHOULD BE IN
PLACE
BRACING SHOULD BE PROVIDED IF TOWER
HEIGHT INCREASES 6M
AT HIEGHTS SAFETY BELTS SHOULD BE
USED BY WORKMEN
08/28/09 48
Ladder Safety
Follow the 4:1 rule when using extension ladders
6 m (20 ft)
1.5 m (5 ft.)
08/28/09 49
–Erect First Tower – Adjust and ensure the
top level is same. Connect all pin bracing
08/28/09 50
08/28/09 51
08/28/09 52
Use of lifeline
above 2m
08/28/09 53
LABOUR
PRODUCTIVITY
PRODUCTIVITY IS MAXIMUM OUTPUT FROM
MINIMUM INPUT
WORKING OF 8 HRS=1MANDAY
PRODUCTIVITY=
SHUTTERING AREA ACHIEVED DURING THE
MONTH/MANDAYS
08/28/09 54
MATERIAL
PRODUCTIVITY
MATERIAL PRODUCTIVITY IS COMPARED
WITH STANDERED PRODUCTIVITY
STANDERED PRODUCTIVITY CALCULATED
ON THE BASIS OF SHUTTERING AREA
COMPLETED AND KG MONTH PER SQM
TOTAL REQUIRED KG=
SHUTTERING AREA *KG MONTH PER SQM
08/28/09 55
ACTUAL PRODUCTIVITY IS
TAKEN AS AVERAGE STOCK
LEFT
PRODUCTIVITY IN %=
(ACTUALPRODUCTIVITY/STANDE
RED PRODUCTIVITY)*100
08/28/09 56
RATE ANALYSIS
ON THE BASIS OF NUMBER OF CARPENTER
KHALASI AND HELPER,NUMBER OF HOURS
OF WORK AND RATE/HR THE TOTAL AMOUNT
IS CALCULATED FOR SHIFTING ,FIXING AND
REMOVING
PRODUCTIVITY IN SQM/MANDAYS IS
CALCULATED
08/28/09 57
BATCHING OF
CONCRETE
PAN TYPE BATCHING PLANT
CAPACITY OF 60M^3/HR
WEIGHED BATCHING
MIXING
TRANSPORTATION
PLACING
08/28/09 58
THANK YOU
08/28/09 59