System Formwork

The document provides details about the formwork used for the construction of the basement structure of Ludhiana City Centre. Some key points: - Larsen and Toubro was contracted to construct the RCC basement structure for the project. - Formwork is a temporary structure used to hold wet concrete in desired shape until it hardens. The document discusses the planning, design, and components of formwork used. - Traditional formwork using ballies was replaced with a more stable, reusable, and safer system formwork called Doka formwork.

Uploaded by

amurugesan
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
80% found this document useful (5 votes)
3K views

System Formwork

The document provides details about the formwork used for the construction of the basement structure of Ludhiana City Centre. Some key points: - Larsen and Toubro was contracted to construct the RCC basement structure for the project. - Formwork is a temporary structure used to hold wet concrete in desired shape until it hardens. The document discusses the planning, design, and components of formwork used. - Traditional formwork using ballies was replaced with a more stable, reusable, and safer system formwork called Doka formwork.

Uploaded by

amurugesan
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 59

FORMWORK

Larsen and toubro limited

Presentation by:
Rachna Rajput
(1030227)

08/28/09 1
LARSEN & TOUBRO LIMITED
ECC DIVISION
LUDHIANA CITY CENTRE
CONSTRUCTION OF RCC BASEMENT STRUCTURE

08/28/09 2
By : A.K. Mishra
THE CLIENT: TODAYHOMES AND
INFRASTRUCTURE
JOINT VENTURE WITH
LUDHIANA
IMPROVEMENT TRUST

ARCHITECT: CP KUKREJA AND


ASSOCIATES

CONTRACTOR : LARSEN AND TOUBRO


LIMITED

08/28/09 3
LUDHIANA CITY
CENTRE
 LOCATED IN HEART OF LUDHIANA
 BUILT ON 25 ACRES OF LAND
 4 SIDE OPEN PLOT
 MAXIMUM NUMBER OF CAR PARKS UNDER
ONE ROOF
 ONLY DEVELOPMENT OF INDIA WITH 5 STAR
HOTEL,SHOPPING MALL,IT/OFFICE
SPACE,HEALTH CARE,LIBRARY,MUESEAM
UNDER 1 ROOF
 BIGGEST ATRIUM:2 LAKH SQUARE FEET
08/28/09 4
LUDHIANA CITY CENTRE
CONSTRUCTION OF RCC BASEMENT
STRUCTURE
Project Highlights
 JOB VALUE : 12400 lacs
 DATE OF LOI: 30:1:2006
 DATE OF COMMENCEMENT: 15:02:2006
 DATE OF COMPLETION: 14:02:2007
 DURATION OF
PROJECT : 12 months
08/28/09 5
THE WORK

FORMWORK PLANNING AND


DESIGN OF ITS VARIOUS
COMPONENTS

08/28/09 6
WHAT IS

FORMWORK?
FORMWORK IS A MOULD USED TO SHAPE
CONCRETE UNTIL IT ATTAINS SUFFICIENT
STRENGTH TO CARRY ITS OWN WEIGHT
 CAN BE ASSEMBLED BY UNSKILLED
LABOUR

 CONSTITUTES 30% OF THE COST AND 60%


OF THE TIME IN CONCRETE
CONSTRUCTION

 GOOD FORMWORK RESULTS IN


08/28/09 SPEED,QUALITY,ECONOMY AND SAFETY 7
TRADITIONAL
APPROACH
 BALLIES USED AS SUPPORT FOR
SHUTTERING

 UNSAFE AND UNRELIABLE

 LOW REUSE VALUE

 DOES NOT PRODUCE GOOD QUALITY


CONCRETE
08/28/09 8
CHOICE OF RIGHT TYPE
OF FORMWORK
 FORMWORK SHOULD BE ABLE TO BE
DESHUTTERED AND DISMANTLED FAST
 SAFETY TO BE IMPROVED BY SITE
PERSONNEL
 OVERALL COST SAVINGS
 GOOD SURFACE FINISH TO BE ACHIEVED
 OPTIMUM STOCK OF FORMWORK FOR SIZE
OF WORKFORCE AND SPECIFIED TIME
SCHEDULE

08/28/09 9
SYSTEM
FORMWORK-L&T
 EARLIER CALLED DOKA
FORMWORK
 INVERSIBLE
 FAST ERECTION
 MORE STABLE
 SAFE IN USE

08/28/09 10
FORMWORK
STEP1.) PLANNING
 CONFIRMING HQ ON THE NEW JOBS BAGGED

 IDENTIFYING TIME AND MATERIALS FOR

CONSTRUCTION PROJECT
STEP2.)
 FINALIZING FORMWORK MATERIALS

REQUIREMENTS FOR THE PROJECT


 COLLATE THE REPORTS FROM RUNNING SITES

AND CHECK SEPARABILITY FROM OTHER SITES


WITHIN THE REGION
 SENDING REQUEST FOR TRANSFER OF

RESOURCES IF AVAILIBILIY IS CONFIRMED

08/28/09 11
CONTD….
 RECEIVING NEW TARGETS ON
PRODUCTIVITY FROM HQ

 COMPARING THE RUNNING


LMP COST FROM THE ACTUAL

 IDENTIFYING TRAINING NEEDS


OF STAFF

08/28/09 12
COMPONENT DETAILING
 FOUNDATION FORMWORK

 HDT TOWER

 SLAB/BEAM FORMWORK

 WALL/COLUMN FORMWORK

08/28/09 13
FOUNDATION
FORMWORK
 STEEL PANELS OF STANDERED SIZES
MINIMIZE MAKING AT SITE
 USE OF VERSATILE COMPONENTS LIKE
STEEL WALERS(2 ISMC BACK 2BACK) AND
ALIGNMENT PROPS
 EASY ASSEMBLY WITH DIMENSIONAL
ACCURACY

08/28/09 14
08/28/09 15
FOUNDATION
FORMWORK MATERIAL
CONTD.

08/28/09 16
CONTD…

08/28/09 17
CONTD….

08/28/09 18
AFTER ERECTION
Steel panel
Pipe waler
clamp
Pipe waler

Alignment
prop

welar

08/28/09 19
HDT TOWER
 BASIC FRAME
 HORIZONTAL BRACE
 DIAGNOL BRACE
 TAKES LOAD OF 250KN
 HIEGHT ADJUSTMENTS UPTO 800MM
POSSIBLE
 TRANSPORT DEVICES CAN BE ATTATCHED

08/28/09 20
COMPONENT
DETAILING

08/28/09 21
CONTD….

08/28/09 22
AFTER ERECTION

Coupler and
spring lock pin

Foot plate

Tower
spindle

08/28/09 23
WALL/COLUMN
FORMWORK
 SHOP MADE SHUTTER

 ACCORDING TO THE HIEGHT OF WALL OR


COLUMN SPLICING CAN BE DONE

 ISMC WALERS ARE USED FOR BEARING

08/28/09 24
COMPONENT
DETAILING

08/28/09 25
CONTD….

08/28/09 26
CONTD……

08/28/09 27
COLUMN FORMWORK
WORKING AT 4.8M
HIEGHT

08/28/09 28
COLUMN FORMWORK

08/28/09 29
WALL FORMWORK 1.8M
HIEGHT

08/28/09 30
SLAB/BEAM
FORMWORK
 SHEATHING MEMBER

 H-BEAM(SECONDARY MEMBER)

 WELAR(PRIMARY MEMBER)

 HDT TOWER

08/28/09 31
AFTER
ERECTION
Sheathing
H-beam

welar

tower

08/28/09 32
DESIGN OF
FORMWORK
 FORMWORK MUST SUPPORT ALL THE
VERTICAL AND LATERAL LOADS
 ALL LOADS ARE ASSUMED TO BE
UNIFORMLY DISTRIBUTED
 BEAMS SUPPORTED OVER 3 OR MORE
SPANS ARE TAKEN AS CONTINUOUS
 APPROXIMATE FORMULAE ARE USED

08/28/09 33
AN IMPORTANT
POINT
 SHEATHING SPAN DECIDES H-BEAM SPACING

 H-BEAM SPAN DECIDES WALER SPACING

 WELAR SPAN DECIDES TOWER SPACING

“SPAN” HERE MEANS THE DISTANCE BETWEEN


TWO REACTION POINTS

08/28/09 34
DESIGN PROCEDURE
EXAMPLE
LOADS TO BE TAKEN
 DEAD LOAD(1)
(THICKNESS OF MEMBER*DENSITY OF
CONCRETE)

 LIVE LOAD(2)

 SELF WEIGHT(3)

 DESIGN LOAD,W=(1)+(2)+(3)

08/28/09 35
DESIGN PROCEDURE
CHECKS TO BE APPLIED
 BENDING MOMENT CONDITION
 SHEAR FORCE CONDITION
 DEFLECTION CONDITION
THE MINIMUM OF ALL 3 SPANS IS
TAKEN AS SPAN FOR THE MEMBER
 ACCORDING TO HEIGHT OF WALL OR
COLUMN THE REQUIRED LENGTH OF
H-BEAM(AN I SECTION )
 HIGH STRENGTH TIE SYSTEM BEAR
LARGE CONCRETE PRESSURE
08/28/09 36
DESIGN PROCEDURE
CONTD….
 DESIGN DONE FROM TOP TO BOTTOM
 1. SHEATHING MEMBER
 2.H-BEAM(SECONDARY MEMBER)
 3.WELAR(PRIMARY MEMBER)
 HDT TOWER

08/28/09 37
 SELF WEIGHT OF CONCRETE WITH
REINFORCEMENT=25KN/M^3

 SELF WEIGHT OF FORMWORK VARIES


BETWEEN 0.5KN/M^2 TO .75KN/M^2

 MINIMUM LIVE LOAD =2.5KN/M^2

 MINIMUM DESIGN LOAD=5.0 KN/SQM

08/28/09 38
 SHEATHING MEMBER:
END CONDITION ASSUMED TO BE A PROPPED
CANTILEVER
 BM=W*L^2/8<=.2KNM/M

 SHEAR=5*W*L/8<=6.16KN/M

DEFLECTION=W*L^4/(185*E*I)<=1.852*10^-3M
MINIMUM OF ABOVE THESE 3 SPANS IS TAKEN
AS SPACING BETWEEN H-BEAMS

08/28/09 39
 SECONDARY MEMBER(H BEAM):
END CONDITION IS ASSUMED TO BE SIMPLY
SUPPORTED
 LOAD INTENSITY =DESIGN LOAD*SPAN OF

SHEATHING MEMBER
 BM=W*L^2/8<=3KNM

 SHEAR=W*L/2<=6KN

 DEFLECTION=5*W*L^4/(384*E*I)

MINIMUM OF ALL 3 IS TAKEN AS SPAN FOR


H-BEAM

08/28/09 40
 WELAR (PRIMARY MEMBER)
SIMPLY SUPPORTED END CONDITION IS
ASSUMED
 NOW WIDTH OF LOADING IS THE SPAN FOR

H-BEAM AND W=DESIGN LOAD*WIDTH OF


LOADING
 BM=W*L^2/8<=12.67KNM/M

 SHEAR=W*L/2<=103.4KN/M

 DEFLECTION=5*W*L^4/(384*E*I)<=6.67*10^-3

MINIMUM OF THESE 3 IS TAKEN AS THE


DISTANCE BETWEEN 2 TOWERS

08/28/09 41
08/28/09 42
DESIGN FOR
WALL/COLUMN

FORMWORK
CONCRETE EXERTS A FLUID PRESSURE Dh
ON THE FORMWORK
 Pmax=

D[C1*R^.5-(C2*K*(H-C1*R^.5)^.5) OR
Dh
whichever is smaller
VALUE OF C1
FOR WALLS=1
FOR COLUMNS=1.5
08/28/09 43
 VALUE OF C2 DEPENDS ON CONSTITUENT
MATERIALS OF CONCRETE
 D=WEIGHT DENSITY OF CONCRETE
 H=VERTICAL FORM HIEGHT
 h=VERTICAL POUR HIEGHT
 K=TEMPERATURE COEFFICIENT TAKEN AS
(36/T+16)^2
 R=RATE OF RISE M/H
 T=TEMPERATURE OF CONCRETE AT PLACING
(degree celsius)

08/28/09 44
PRESSURE DISTRIBUTION DIAGRAM

Pmax/D

P max

08/28/09 45
DESIGN OF WALER –
DESIGNED AS LATERALLY
UNSUPPORTED BEAM
 SIGMAbc=.66*Fcb*Fy/(Fcb^n+Fy^n)^1/n
Fcb=ELASTIC CRITICAL STRESS(N/MM^2)

Fy= YIELD STRESS OF STEEL IN( N/MM^2)


N=FACTOR TAKEN AS 1.4
 Fcb=K1*(X+K2*Y)*C2/C1
 PERMISSIBLE SHEAR STRESS=0.4*Fy
 PERMISSIBLE DEFLECTION=L(SPAN)/325
 BENDING STRESS=M/Z
 SHEAR STRESS=F/Aweb
08/28/09 46
STRIPPING TIME
FOR FORMWORK
 VERTICAL FORMWORK TO COLUMN, WALL
AND BEAM :16-24HOURS

 SOFFIT FORMWORK TO SLABS(PROPS TO BE


REFIXED AFTER REMOVAL OF FORMWOK) :3DAYS

 SOFFIT FORMWORK TO BEAMS :7DAYS

08/28/09 47
SAFETY IN
FORMWORK
 BEFORE ERECTION OF STEEL FRAME
STAGING THOROUGH INSPECTION
 DIAGNOL BRACES SHOULD BE IN PROPER
POSITION
 ALL CONNECTING DEVICES SHOULD BE IN
PLACE
 BRACING SHOULD BE PROVIDED IF TOWER
HEIGHT INCREASES 6M
 AT HIEGHTS SAFETY BELTS SHOULD BE
USED BY WORKMEN

08/28/09 48
Ladder Safety
Follow the 4:1 rule when using extension ladders

6 m (20 ft)

1.5 m (5 ft.)

08/28/09 49
–Erect First Tower – Adjust and ensure the
top level is same. Connect all pin bracing

08/28/09 50
08/28/09 51
08/28/09 52
Use of lifeline
above 2m

08/28/09 53
LABOUR
PRODUCTIVITY
 PRODUCTIVITY IS MAXIMUM OUTPUT FROM
MINIMUM INPUT

 UNITS ARE SQM/MANDAY

 WORKING OF 8 HRS=1MANDAY

 PRODUCTIVITY=
SHUTTERING AREA ACHIEVED DURING THE
MONTH/MANDAYS

08/28/09 54
MATERIAL
PRODUCTIVITY
 MATERIAL PRODUCTIVITY IS COMPARED
WITH STANDERED PRODUCTIVITY
 STANDERED PRODUCTIVITY CALCULATED
ON THE BASIS OF SHUTTERING AREA
COMPLETED AND KG MONTH PER SQM
 TOTAL REQUIRED KG=
SHUTTERING AREA *KG MONTH PER SQM

08/28/09 55
 ACTUAL PRODUCTIVITY IS
TAKEN AS AVERAGE STOCK
LEFT

 PRODUCTIVITY IN %=
(ACTUALPRODUCTIVITY/STANDE
RED PRODUCTIVITY)*100

08/28/09 56
RATE ANALYSIS
ON THE BASIS OF NUMBER OF CARPENTER
KHALASI AND HELPER,NUMBER OF HOURS
OF WORK AND RATE/HR THE TOTAL AMOUNT
IS CALCULATED FOR SHIFTING ,FIXING AND
REMOVING
PRODUCTIVITY IN SQM/MANDAYS IS
CALCULATED

08/28/09 57
BATCHING OF
CONCRETE
 PAN TYPE BATCHING PLANT
 CAPACITY OF 60M^3/HR
 WEIGHED BATCHING
 MIXING
 TRANSPORTATION
 PLACING

08/28/09 58
THANK YOU