Power Management System by ABB
Power Management System by ABB
ABB
ABB AS - 3
ABB
Power Control
}
}
}
Load Shedding
Object Control
Synchronization
ABB AS - 4
ABB
In-depth knowledge of the electrical process 20 years experience in PMS implementations across the world (green-field and brown-field plants) Standard software, well documented, tested, proven technology Fast Response Time for Load Shedding and Power Control High Resolution and Accuracy of Sequence of Event recording Comply to class 3 EMC immunity Single responsibility: One supplier for PMS integrated with switchgear, protection, governor, excitation, transformer, tapchanger, Motor Control Centre, Variable Speed Drive, etc. Experience with EPCs like: ABB Lummus, Bechtel, Chiyoda, Fluor Daniel, Foster Wheeler, JGC, Kellogg, Larson & Tubro, Mitsubisi, Snamprogetti, Technip, Toyo, Toshiba, etc.
ABB AS - 5
ABB
Load Shedding Active and Reactive Power Control Supervision, Control and Data Acquisition (SCADA):
Generator and Turbine Transformer and Tapchanger Circuitbreaker, Disconnector and Earthing switches
Motor
Synchronization
ABB AS - 6
ABB
PMS :
ENMC : Electrical Network Monitoring and Control system ELICS : ELectrical Integrated Control System
etc.
ABB AS - 7
ABB
Drivers
Fonts Utilities
ABB AS - 8
ABB
Object approach
Technical Spec.
Mech. Drawing
Elec. Diagram
Simulation Model
Control Program
Test Report
ABB AS - 9
ABB
ABB AS - 10
ABB
Server
Operator Station
Engineering Station
Control Network
DCS
ProfiNet IO
IEC 61850
MV M G M M M
LV
ABB AS - 11
Substation 1
Substation 2
Substation N
ABB
Substation Z
ControlIT
AC 800M
Built in redundant Ethernet Very low power consumption Communication & fieldbus interfaces Hot swap of communication- and I/O modules
ABB AS - 12
ABB
Load Shedding
ABB
ABB AS - 14
ABB
Fast Exact Flexible Co-ordinated Deterministic Security and Reliability Accurate Event Logging Operator Guidance Independent Back-up System (Click here for details)
ABB AS - 15
ABB
15MW G1
20MW
G2
30MW
M1
M2
M3
M4
M5
M6
M7
ABB AS - 16
ABB
6 kV levelG (back-up)
M M
400 V level
G G G
ABB AS - 17
ABB
33 kV
M M
Substation 2 6 kV
Substation N 6 kV
Power Flow
ABB AS - 18
1 s.
RED bays (Load Shed Groups): Open Command 5-10 ms. CB position 1 s. Power Flow 1 s.
ABB
G1
G2
M1
M2
M3
M4
M5
M6
5MW 5MW (3) (7)
M7
M8
Busbar Left 1. 0 MW 2. 2 MW 3. 2 MW 4. 2 MW 5. 7 MW 6. 9 MW 7. 9 MW 8. 9 MW
Busbar Right 1. 0 MW 2. 0 MW 3. 5 MW 4. 5 MW 5. 5 MW 6. 5 MW 7. 10 MW 8. 12 MW
ABB AS - 19
ABB
G1
G2
M1
M2
M3
M4
M5
M6
5MW 5MW (3) (7)
M7
M8
Busbar L + Busbar R = 1. 0 MW 0 MW 2. 2 MW 0 MW 3. 2 MW 5 MW 4. 2 MW 5 MW 5. 7 MW 5 MW 6. 9 MW 5 MW 7. 9 MW 10 MW 8. 9 MW 12 MW
Cont. 1 0 MW 2 MW 7 MW 7 MW 12 MW 14 MW 19 MW 21 MW
ABB AS - 20
ABB
Power Balance:
G1
G2
PGen + PSR PLoad + PInhibit PSR = 5 MW 16 + 5 21 + 11 21 32 Shed 11 MW Check Table Shed Prio 5 Shed M1, M3 and M5
M1
M2
M3
M4
M5
M6
5MW 5MW (3) (7)
M7
M8
ABB AS - 21
ABB
Generator trip
MW
2.2
MW
1.8
1.8 MW
2.1 MW
ABB AS - 22
ABB
ABB AS - 23
ABB
4.8 MW
1.5 MW 50.12. Hz
3.3 kV
MW
0.0
MW
1.8
1.8 MW
2.1 MW
Ethernet TCP/IP
ABB AS - 24
ABB
4.8 MW
1.5 MW 50.12. Hz
3.3 kV
MW
0.0
MW
1.8
1.8 MW
2.1 MW
ABB AS - 25
ABB
ABB AS - 26
ABB
ABB
ABB AS - 28
ABB
Turbine Control
Droop or isochronous Manual control (Droop) Manual MW setpoint Automatic frequency control Automatic setpoint control (MW sharing) Automatic mode change:
PMS provides:
ABB AS - 29
ABB
Generator Control
Primary AVR:
Droop or voltage control Manual control (Droop) Manual setpoint control (setpoint is PF) Automatic Voltage Control (AVR receives raise/lower from PMS) Automatic setpoint control (MVar sharing)
PMS provides:
ABB AS - 30
CB trip
ABB
In island operation:
Connected to grid:
ABB AS - 31
Objectives
ABB
Generator Control
5.7 MW 7.2 MW 1.5 MW 50.12. Hz 3.3 kV
MW
2.2
MW
1.8
1.8 MW
2.1 MW
1.6
3.3 3.3 50.0 50.0 2.2 2.2 0.9 0.9 0.9 0.9 120.0 120.0 20.0 20.0
ABB AS - 32
ABB
ABB AS - 33
Alarm annunciation
Event Time Tagging Disturbance Recording Local storage of trip-events Communication to PMS
ABB
Synchronisation
Automatic Synchronisation
Manual Synchronisation Adjust voltage magnitude Adjust voltage frequency Adjust voltage angle Rough adjustments by PMS Fine tuning by a Synchroniser Close the breaker by the Synchoniser
ABB AS - 34
ABB
ABBs response
Power Management system including Load Sheding system based on dynamic fast loadbalance Power Control.
Customers benefits
ABB AS - 36
ABB
QatarGas II LNG
Customers needs
Experienced PMS supplier to be able to cope with new concept for LNG Compressor drives systems
ABBs response
Intelligent Power Management System controlling: 3* STGs (each 44 MW) 1* GTG (33 MW) 6* VFD/GTG (each 45 MW) including: * NOx constrains considerations * Power flow limitations to QG 1 and QG 3 & 4 * Contingency Load Shedding.
ABB AS - 37
Customers benefits
ABB
Extension of Power Distribution System with 100 MW to 300 MW for two extra LNG trains
ABBs response
Intelligent Power Management System including Load Shedding and Power Control Is-limiters between the three 33 kV substations (triangle configuration)
Customers benefits
ABB AS - 38
No need for a 132 kV substation including six 132/33 kV Power Transformers Reliable operation and avoiding black-outs.
ABB bv - 60
ABB
ABB AS - 39
AFPC, Omar refinery in Syria ABF, Petronas MLNG Satu, Dua & Tiga in Malaysia StatOil Gullfaks, LNG Hammersfest & BP Amoco Valhall QatarGas II, III & IV, PS2 & PS3 in Qatar
ABB
ABB AS - 40
ABB
Power control including voltage control, frequency control, sharing power among generators and tie-line(s).
FEEDER TERMINAL
REF541
Decreased number of operators Event driven maintenance Transformer Overload Management Single Window concept Minimized cabling and engineering The Optimizing Power shortcurrents Human Control, the Machine stability by Standby a Interfaces circuitbreaker of the Optimization, operation for all or the of secure the available power to critical loads Optimized network design
1MRS xxxxxx
98 15 0
In = 1/5 A (I)
9 50 9
ABB AS - 41
Reduce investment costs The total switched-off In case of a accumulated shortage of electrical power,
n+1 Limit electrical theswitching Criteria, electrical electrical the sub-systems number SCADA, generationimport of none generator etc. during can are and be peak performed integrated distribution starts and by in Serial by interfaces off the with protection important &time control loads No need for big oversizing of primary equipment the Maintaining the are system reduce Energy a spaghetti network trigger and peak Management adynamic good not for based of maintenance by a Power plant the charges System Factor units according avoid to wiring load &operators cable tables ducts
ABB