What You Should Know About PMP Formulas
What You Should Know About PMP Formulas
com)
Content of Presentation
Aims of Presentation What & Why of Formulas Types and Classes of Types and Classes of
formulas Earned Value Calculations PERT Calculation Estimation Classes Project selection Criteria Communication Channels
For PMP Aspirants
formulas-cont Probabilities Procurement Depreciation Control Limits (Sigmas') Project Network calculations Other Important Formulas
10/4/2013
Aims of Presentation
To provide a ONE STOP junction to view all
formulas and more likely ones used for PMP Exam To help PMP aspirants to acquire a clear understanding of the related formulas as an aid for a quick exam review
10/4/2013
symbols and formation rules of a given logical language A formula is a concise way of expressing information symbolically The informal use of the term formula in science refers to the general construct of a relationship between given quantities In a general context, formulas are applied to provide a mathematical solution for real world problems.
Source: Wikipedia
10/4/2013 For PMP Aspirants 4
the configuration of concepts/theories Snap shot of concepts /theories Understand concepts/theories evaluate concepts/theories Apply concepts/theories
For PMP Aspirants 5
10/4/2013
Project/Performance Management (EVPM) is a project management technique for measuring project performance and progress in an objective manner The fundamental values focused on are,
PV - Planned Value or Budgeted Cost of Work scheduled
(BCWS) AC - Actual Cost or Actual cost of work Performed (ACWP) EV - Earned Value or Budged Cost of Work Performed (BCWP)
10/4/2013
Description Budgeted Cost of Work Scheduled Budgeted Cost of Work Performed Actual Cost of Work Performed/Produced Schedule Variance Cost Variance Schedule Performance Index-measures effectiveness Cost Performance Index-measures efficiency Estimate at Complete Budget at Complete Variance at Complete To Complete Performance Index
than planned
< 1 bad (over budget); the cost of completing the work is higher than
planned; = 1 means that the cost of completing the work is right on plan (good);
SPI
> 1 is good (ahead of schedule) the work is performed
10/4/2013
10
EV = % Complete* BAC
CV% = EV/CV * 100% SV% = EV/SV* 100% SPI = EV / PV (schedule efficiency) CPI = EV / AC (cost efficiency)
10/4/2013 For PMP Aspirants 11
Forward Pass
= [Pessimistic+(4*Most
Likely)+Optimistic]/6
[(Pessimistic Optimistic)/6]^2 = [(P-O)/6]^2 SUM[(Pessimistic Optimistic)/ 6^]2 = SUM of all [(P-O)/6]^2 = (P-O)/6 = Square Root of Variance = Calculate (Best + Worst)/2
10/4/2013
14
activity do not include leads and lags may include range of possible results
e.g. a) 2weeks +/- 2days (i.e. 8 days to 12 days range for a target date of 10 days) b) 15% probability of exceeding 2 weeks (i.e. 85% likely that the activity will take 2 weeks or less) Range of Activity duration = EAD-SD
10/4/2013
15
Classes of Estimates
Order of Magnitude estimate = -25% to +75% Preliminary estimate = - 15% to + 50%
10/4/2013
16
PV = FV / (1+r)^n FV = PV * (1+r)^n NPV = Select biggest number. A discount method ROI = Select biggest number. A comparative method IRR = Select biggest number. A comparative discount method Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment. A nondiscount method BCR = Benefit / Cost Ratio CBR = Cost / Benefit Ratio Opportunity Cost = The value of the project not chosen. Expected Value = Probability(%) x Consequence($)
For PMP Aspirants 17
10/4/2013
Contract Incentives
Savings = Target Cost - Actual Cost
10/4/2013
18
CP STD. DEV. = + +
COMMON CAUSE or RANDOM CAUSE-
10/4/2013
10/4/2013
20
-Depreciation Expense = Asset Cost / Useful Life -Depreciation Rate = 100% / Useful Life
Accelerated depreciation: 1. Double Declining Balance Method:
-Depreciation Rate = 2 * (100% / Useful Life) -Depreciation Expense = Depreciation Rate * Book Value at Beginning of Year
10/4/2013 For PMP Aspirants
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Depreciation rate = fraction of years left and sum of the digits (e.g. 4/15th)
Book Value
21
Description of Formula (Purchase Value Salvage Value)/No of Useful Years 1. SUM OF THE YEARS DIGITS METHOD Depreciation Rate = Sum of the Years of Useful life , Divided into the Remaining Value of the Asset, (BOOK VALUE) each year; Taken From the Highest Value to the Lowest, Calculated Yearly Over the Useful Life of the Asset. In the Last Year the Full Amount Remaining is Charged. 2. DOUBLE DECLINING BALANCE METHOD The Percent of Depreciation is Applied on the Depreciation Value of the Item Remaining Each Year. The last year or two values are rounded off to End the Calculation. The Usual Depreciation Rate applied is 50%.
For PMP Aspirants 22
10/4/2013
less than the control limits Float on the critical path = 0 days Pareto Diagram = 80/20 Time a PM spends communicating = 90% Crashing a project = Crash least expensive tasks on critical path. Just In Time inventory = 0% (or very close to 0%.)
For PMP Aspirants 23
10/4/2013
Probability
EMV = Probability * Impact in currency
Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's
10/4/2013
24
10/4/2013
25
Congrats!