Ahmad Tariq Bhatti: A Presentation by
Ahmad Tariq Bhatti: A Presentation by
It was found at Boeing, the aircraft manufacturing company, during WW-II period, that the time taken to assemble an individual aircraft declined as the number of aircrafts assembled increased. It was noted that the rate of improvement (known as rate of learning) was so regular that it was presented in the form of a mathematical formula. Thus, the labor hours required for the assembly of aircrafts could be predicted with reasonable precision. The name given to this effect of increased efficiency was Learning Curve (LC) phenomenon. The phenomenon was tested in a number of manufacturing setups across the industries and it was found invariably everywhere. However, the learning rate of laborers differed from one industry to another.
2/18/2013 Learning Curve Phenomenon 2
Definition
The mathematical expression of the phenomenon that,
when complex and laborintensive procedures are repeated, unit labor time tend to decrease at a constant rate.
LC models mathematically this reduction in unit production time.
The Concept
It was found that the cumulative average time per unit decreased by a fixed percentage each time the cumulative production doubled. In aircraft industry, the percentage by which cumulative average time per unit decreased was typically 80%. Similarly different learning rates were noted for different industries. Let us examine an example of production where learning rate is noted at 90%:
Units
1 2 4
8
16 32
72.90 (81x90%)
65.61 (72.90x90%) 59.05 (65.61x90%)
343.90
409.51 568.56
2/18/2013
An Illustrative Model
No. of Units Order #
Per order
1 2
Cumulative Production
3
1
2 3 4 5 6
2/18/2013
1
1 2 4 8 16
1
2 4 8 16 32
2,000
1,600 (2,000 x 80%) 1,280 (1,600 x 80%) 1,024 (1,280 x 80%) 819 (1,024 x 80%) 655 (819 x 80%)
13,104
20,960
5
The Shape of LC
Learning Curve W. 80% LR
2500
2,000
2000 1500 1000 500 1 0 1 2 3 4 5 6 2 4 8 16 32
1,600
1,280
1,024
819
655
The Formula
=
Where, Y = the cumulative average time required to produce X units a = the time required to produce the first unit of output b = the learning /improvement rate/index of learning X = number of units to be produced Important Note , This formula calculates only direct labor time against given number of units. The direct labor cost shall be calculated, thereafter, by multiplying the time calculated by this formula with standard labor rate.
2/18/2013
Calculation
The cumulative average time taken to produce 10 and 20 units is calculated as follows:
= .
Y= 2000x0.476431
Y= 953 hours
= .
Y = 2000 x 0.381126
Y = 762 hours
(Data used from table given at slide 5)
2/18/2013
Solution
= Where: Y = Average time/batch = 81/12 = 6.75 hours a= 15 hours X = 12
Calculation
To calculate b:
6.75 = 15 x 12 12 = 6.75/15 = 0.45 b log12 = log 0.45 b = Log 0.45/Log 12 = (- 0.3468/1.0792) = - 0.3213 Now putting value of b in formula (a) at slide10 b = Log of learning rate/Log2 -0.3213= Log of learning rate / 0.3010 Log of learning rate = 0.3010 x (-0.3213) = -0.09671 Log of learning rate = -0.09671 Find the value (-0.09671) in anti-log table. The value -0.09671 converts to 80% i.e. the learning rate.
2/18/2013 Learning Curve Phenomenon 11
Solution
# of units 1 2 4 8 Average Time/ Unit Hours 4.000 3.600 (4.00 x 90%) 3.240 (3.60 x 90%) 2.916 (3.24 x 90%) Cumulative Time Hours 4 7.2 12.960
23.328
12
2/18/2013
Solution
Y = average time per unit a = time taken for the first unit b = 85% = - 0.2345 Y = 100 x 140.2345 = 53.856 Average time per unit for a batch containing 14 units = 53.856 hours Total time for a batch containing 14 units = 14 x 53.856 = 753.984 hours
2/18/2013
13
Labor & related cost: -- Direct Labor (100 hours @ AED.8 each)
-- Variable Overheads (100 hours @ AED. 2 each) Total cost of 1st 50 units
800
200 2,000
2/18/2013
14
Calculation
Solution
Quantity
Units 50 100
Total Time
Hours 100 160 (1.6 x 2 x 100)
Amount
AED. 1,000 480 120
1,600
800
2,400
15
Important Note
The LC formula is used to estimate direct labor time for a given number of units and thus is helpful in the calculation of direct labor cost estimates. Further, the learning effect is applied to those variables also that are dependent upon direct labor time for their time and cost estimation. The concept of LC is not applied to direct material costs or overhead costs relating to production. The concept of LC is applicable where operations are complex and carried out manually by labor. Where operations are so simple that apply very low level of intelligence, there shall be little scope for learning effect. Hence, there shall be no LC.
2/18/2013 Learning Curve Phenomenon 16
Applications
Pricing Decisions
It requires the ability of the management to use the learning effect to forecast and make the cost reductions and obtain a considerable lead over the competitors by giving better prices.
Work Scheduling
Useful in the management of delivery orders and related schedules. Scheduling labor work requirements.
Pricing Contracts
The LC has been quite useful in determining the likely costs relating to various contracts. It provides a rational basis for price negotiation and cost control.
Inventory Management
The LC concept can be used in the planning, budgeting and purchasing of inventory.
2/18/2013 Learning Curve Phenomenon 17
Abbreviations Used
#
1 2
Abbreviation
AED LC
Description
Emirati Dirham Learning Curve
3
4
LR
WW-II
Learning Rate
World War Two
2/18/2013
18
References
Management & Cost Accounting by Colin Drury 5/e Cima Official Terminology Business Finance by Joel G. Siegel, Jae K. Shim, Stephan W. Hartman
2/18/2013
19
2/18/2013
20