Preferred Purple Line Mode: 14 TH TH TH
Preferred Purple Line Mode: 14 TH TH TH
This section of the staff memo reviews the issues related to the preferred mode of the Purple
Line raised by MPAG members, in testimony at the MTA hearings, by other interested citizens
and stakeholders, elected officials and staff. The staff’s analysis is supplemented by other
technical sources and input from the MTA Project Team, MPAG members, or other interested
parties.
The staff recommends light rail as the preferred mode for the Purple Line.
Vehicle Capacity
In late October, staff asked the MTA to provide estimates for the peak directional line load
(ridership) and the assumptions regarding mode capacities used in the AA/DEIS.
The AA/DEIS notes that the ―TSM and BRT vehicle fleets could be a combination of articulated
or standard buses.‖15
Directional line capacity is dependent on the service frequency and the bus or train’s capacity,
among other things. The peak hour capacity of 2,100 shown in Table 7 for the BRT alternatives
assumes that additional BRT vehicles are used during the busiest hour in the afternoon to
accommodate the demand. It also assumes that each BRT vehicle can accommodate 140
passengers.
13
The MTA assumptions for Peak Hour Capacity include the following: For BRT – 10 vehicles per hour times 140
people per vehicle plus 5 trippers per hour times 140 people per vehicle. ―Trippers‖ are extra buses placed in
operation for only the period of time needed to accommodate the demand – in this case it is theoretically the busiest
consecutive 15 minutes during the peak period. For LRT – the assumption is 10 trains per hour with each train
consisting of 2 cars, each car carrying 140 people.
14
SSTC is the Silver Spring Transit Center
15
See Subsection 2.6.5, page 2-31.
36
There are numerous articles and professional references on transit capacity. The Transportation
Research Board’s Transit Capacity and Quality of Service Manual (2nd Edition) suggests a good
range for BRT vehicle capacity is 100 to120 for a high floor vehicle.16
Another good reference for comparing LRT and BRT is a presentation by Jay Evans Consulting
in 2005 at the Institute of Transportation Engineers annual meeting.17 The presentation includes
an objective look at the issues of capacity and costs. BRT vehicle capacity is estimated to range
from 110 to 120, including more than one-third as standees. Mr. Evans concludes the
presentation by noting:
―No rapid transit mode is singly superior in all contexts. Consideration of ‗right sizing‘ should
be paramount in decision making.‖
Fifteen BRT vehicles an hour would accommodate 1,800 passengers if you assume 120
passengers per BRT vehicle (lower than the MTA estimate presented in the above table). Ten
LRT trains an hour would accommodate 2,700 passengers an hour (per the MTA estimate) if you
assume two cars per train and each car accommodating 135 passengers.18 Under those
assumptions, the BRT vehicles would accommodate the estimated peak hour directional line load
on two of the three alternatives.
The staff is concerned that BRT may not provide enough capacity to serve expected demand,
especially given the Purple Line’s connections with the Metrorail system, the forecasted peak
hour passenger demand, and the fact that the forecasting model does not capture other external
factors such as the risk that fuel costs rise faster than inflation.
any BRT option must operate in mixed traffic for several blocks to execute the
―turnaround‖ required at the Bethesda terminus, so the ability to maintain schedules on
very short headways is unrealistic.
Individual station boarding and alighting demands become more unpredictable as
headways are reduced, so that buses will not serve equal demands.
The typical traffic signal cycle length (generally up to 150 seconds in peak periods)
means that should signal priority treatments fail, an individual BRT vehicle could fall one
―headway‖ behind schedule.
16
See Transit Capacity and Quality of Service Manual – 2nd Edition (Exhibit 4-17)
17
See the following link for the slide show: http://www.ite.org/meetcon/2005AM/Evans_Tues.pdf
18
A 90 foot light rail vehicle is estimated to have a capacity equivalent to 1.5 passengers per foot length of the car,
or 135 passengers (Source: Transit Capacity and Quality of Service Manual – 2nd Edition – page 5-29).
19
See Transportation Research Record: Journal of the Transportation Research Board, No. 1927, 2006, pages 11-21.
37
Staff finds that the capacity advantage of LRT is one deciding factor in developing a
recommendation for a preferred mode.
The AA/DEIS finds that the difference in emission levels among the various alternatives is
insignificant.20This finding is consistent with other technical comparisons of BRT and LRT
emissions. Transportation Research Record 1927 provides a summary comparison of the variety
of BRT and LRT technologies and concludes that LRT is superior to BRT in that LRT produces
lower regional or urban emissions levels.21 However, the combined consideration of energy
sources and greenhouse gas emissions has generated substantial discussion that requires further
review, particularly in the selection of appropriate LRT vehicle technology. Additional analysis
of the alternative LRT vehicle energy and emissions characteristics should be included in the
FEIS. Therefore, at the moment, staff finds that vehicle emission and greenhouse gas levels
should not be a deciding factor in developing a recommendation for a preferred mode.
Potential noise and vibration impacts were assessed using criteria established by the Federal
Transit Administration (FTA). The assumption was that BRT service would be operated using
60-foot articulated buses and the LRT trains would consist of trains with two 90-foot articulated
cars.
In general, there is moderate noise impact associated with the BRT alternatives at the following
locations in the County:
Leonard Drive
16th Street – Between East West Highway and Spring Street
Wayne Avenue – Between Cedar Street and Cloverleaf Road
Wayne Avenue – Between Dartmouth Avenue and Dale Drive
Wayne Avenue – Between Mansfield Road and Sligo Creek Parkway
Arliss Street – Between Flower Avenue and Walden Road
Residences Near Lyttonsville Operations and Maintenance Facility
The impacts from the BRT alternatives are expected to average one to three dBA above the FTA
impact limits. Noise mitigation for the BRT line operations is anticipated to be four-foot wall
type barriers.
Noise mitigation for LRT line operations will take the form of vehicle skirts on all light rail
vehicles and right-of-way walls on either side of the transitway within the entire length of the
20
See page 4-48 of the AA/DEIS.
21
See Transportation Research Record: Journal of the Transportation Research Board , No. 1927, 2006, pages 31-
37, for a relatively recent article comparing the emission levels of BRT and LRT vehicles for CO, NOx, and VOC:
http://www.actfortransit.org/docs/2008JulLRTvsBRTemmissions.pdf
38
Georgetown Branch right-of-way. No noise impacts are anticipated from LRT line operations as
a result of these mitigation measures.
The potential for wheel squeal noise associated with the LRT operations exists at between five to
eight locations in the County, depending on the alternative. The locations are primarily within
300 feet of Wayne Avenue.22
Wayne Avenue and Fenton Street Wayne Avenue – From Mansfield Road East to Tunnel
Arliss Street – From the Tunnel Through Turning from Piney Branch onto
the Turn onto Piney Branch Road University Boulevard
22
See pages 4-54, 4-55 and 4-56 of the AA/DEIS – along with Figure 4.8-1.
39
Mitigation options for wheel squeal noise include23:
Vibration impacts for the BRT alternatives would occur at the edge of Columbia Country Club
under the Medium and High Investment Alternatives.
The LRT alternatives are expected to produce vibration impacts along the Georgetown Branch
right-of-way at three locations:
East-West Highway
Edgevale Court
Boundary of Columbia Country Club
Also, for all three alternatives, within the Georgetown Branch right-of-way, structures located
within 40 feet of the proposed LRT centerline are expected to experience vibration levels at or
above the FTA impact threshold for Category 2 land uses.24
The AA/DEIS indicates the preferred mitigation for ground borne vibration is the proper
maintenance of wheels and rails and that with maintenance, the impacts would cease.25
The staff finds the noise and vibration analysis in the AA/DEIS is consistent with established
FTA procedures and criteria. The proposed and potential mitigation techniques for line
operations are reasonable for the noise elements that have been investigated. Site-specific
mitigation techniques, however, have not yet been identified.
Adopted Plans that include the Purple Line in some form include:
This Plan designates the Georgetown Branch right-of-way as suitable for use as the Silver Spring
and Bethesda Trolley and the Capital Crescent Trail between Silver Spring and Bethesda. The
23
See presentation by David A. Towers P.E. at the following link:
https://www.commentmgr.com/projects/swne/docs/RailTransitNoiseVibration.pdf
24
A category 2 land use includes residences and buildings where people normally sleep.
25
See page 4-56 and 4-57 of the AA/DEIS.
40
plan includes a single track (as opposed to a double track) over certain segments of the
alignment.26
This Plan reconfirms a light rail and trail combination on the Georgetown Branch alignment
between the Silver Spring and Bethesda CBDs as described in the Georgetown Branch Master
Plan Amendment.
This Plan reconfirms the connection of light rail service to the Silver Spring CBD using the
Georgetown Branch right-of-way, with a terminal located near the Metrorail south entrance in
the Bethesda CBD.
This Plan reconfirms the Georgetown Branch Transitway as part of the design for the new SSTC.
The Plan doesn’t preclude consideration of a Purple Line north or east of the SSTC but does call
for the Sector Plan to be revisited for any changes to right-of-way or easement acquisition, land
use, design, and zoning recommendations, if they would have regional benefits.27 This is
important with respect to the Functional Master Plan since one of its purposes is to provide
specific policy guidance on a Purple Line alignment east of the SSTC. This policy guidance is
expected to be adopted in concurrence with the State and federal decision-making schedule and
will therefore be in place to guide land use planning efforts and transportation decisions during
implementation.
East Silver Spring Master Plan, December 2000 and Takoma Park Master Plan, December 2000
Both of these plans include recommendations to provide rail transit stops along University
Boulevard, New Hampshire Avenue, and Piney Branch Road if a rail transit system is approved
along University Boulevard. Maps in both plans depict an alternative rail alignment connecting
the SSTC with a Takoma/Langley Transit Center.28
Staff finds that master plan conformance should be a consideration when considering the
preferred mode for the Purple Line. The existing applicable plans recommend light rail.
26
Additional detail on the extent of the single track configuration is presented later in this staff memo – in the
section on the consideration of issues related to the alignment of the Purple Line.
27
See Silver Spring CBD Sector Plan, February 2000, page 100, for full discussion.
28
See East Silver Spring Master Plan, December 2000, page 83, and Takoma Park Master Plan, December 2000,
page 103.
41
Urban Design and Economic Development
The staff finds there are three locations along the alignment where urban design considerations in
the context of the selection of a preferred mode need to be examined.
Woodmont East
The Georgetown Branch Master Plan Amendment – January 1990 identifies a trolley with a
station in Bethesda that connects to the southern end of the Metrorail platform and the street
above via high capacity elevators. All of the LRT alternatives in the AA/DEIS include a similar
arrangement (see diagram to
right).29 Two of the three BRT
alternatives in the AA/DEIS also
feature the connection to the
southern end of the Bethesda
Metrorail platform. The Low
Investment BRT alternative is the
only BRT alternative that would
not have a station at this location.
The connection to the Bethesda
Metrorail station for the Low
Investment BRT alternative is
where the existing bus bays are
located.
The staff finds there are three primary design considerations to take into account with respect to
the Woodmont East area and the mode of the Purple Line:
29
The County has programmed funds for the design of a new southern entrance to the Bethesda Metrorail station.
See the following link for additional information:
http://www.montgomerycountymd.gov/content/omb/MasterPDF/07-12/500722.pdf
30
None of the costs of the trail are separated from the overall capital costs of any of the alternatives.
42
surface via a switchback ramp located just west of the tunnel.
Second, all of the Medium and High BRT alternatives provide for an at-grade trail within the
tunnel and therefore there is no ramp as noted above under the High Investment LRT
Alternative. The BRT vehicles in the Medium Investment and High Investment Alternatives
enter the plaza area from Woodmont Avenue and continue eastbound through the plaza area to
the station platform located in the tunnel (see drawing below). The BRT vehicle travel pattern at
this location is one way (eastbound) only. The vehicles would move through the area every six
minutes during weekday peak periods and every ten minutes mid-day.
Finally, all of the LRT alternatives include ―tail-tracks‖ that would extend west from the tunnel
area into the plaza area for an undetermined distance. The image below is provided by the MTA.
Some stakeholders have suggested that the tail tracks are an area where light maintenance
activities could be carried out. Tail tracks would be used periodically to store a train before it
was returned to Lyttonsville or placed into service at the beginning of peak period service.
43
Woodmont East is located in the northeast quadrant of Woodmont Avenue and Bethesda Avenue
and is the western terminus of the Purple Line. Other aspects of Woodmont East of note include
the following:
It is where the Interim Capital Crescent Georgetown Branch Trail meets the completed
Capital Crescent trail that continues south to Georgetown.
It is across from an approved planned mixed use joint development project on the
existing County Parking Lot 31 site.
With the completion of the Bethesda Row mixed use project, it has for many become a
significant activity center that is active both day and night.
Consideration of a preferred mode for the Purple Line in the context of urban design and
Woodmont East should take into account the following31:
The Low BRT Alternative along Jones Bridge Road does not extend south to Woodmont
East and is therefore the only option that avoids Woodmont East and the impact of
having the transitway in the plaza and tunnel.
The Low BRT Alternative along Jones Bridge Road is the only option where the trail is
not completed between Jones Mill Road and Woodmont East.
The Low BRT Alternative along Jones Bridge Road is the only option that would not
provide for direct pedestrian connection to Woodmont East.
The Medium and High BRT Alternatives are the only alternatives on the Georgetown
Branch right-of-way that feature both the transitway and trail to continue through the
tunnel at grade.
The Medium and High BRT Alternatives are the only alternatives that involve Purple
Line vehicles moving through the plaza area from one end to the other.
The LRT Alternatives are the only alternatives where Purple Line vehicles could be
parked in the plaza area – even if infrequently and for very short periods of time.
The Low and Medium LRT Alternatives do not provide for a trail through the tunnel.
The High LRT alternative includes a trail that continues through the tunnel above the trail
in a confined space.
A summary of the considerations related to urban design, Woodmont East, and the mode of the
Purple Line is presented below:
31
There is admittedly some overlap between mode and alignment when discussing Woodmont East (and other areas
or issues as well). We have chosen to include the discussion at this point in the report because the different
alignments at this end of the Purple Line are largely based on the mode under consideration. That is not the case for
most other areas (not all) along the alignment.
44
TABLE 8 – Summary of Woodmont East Urban Design Issues
Maintains
Improves Trail
Status Quo Avoids
Connectivity Accommodates
At Transit Reinforces
To/From Improved Trail
Woodmont Vehicle In Street
Alternative Woodmont In Tunnel
East and Plaza On Activation
East and Without Grade
Avoids Regular In Area
Points East Changes32
Impacts To Basis
and South
Trail
Low BRT Yes No No Yes No
Medium BRT No Yes Yes No Yes
High BRT No Yes Yes No Yes
Low LRT No Yes No Yes Yes
Medium LRT No Yes No Yes Yes
High LRT No Yes No Yes Yes
After reviewing the issues in the context of mode, the staff finds there are advantages and
disadvantages with either mode (and the associated alignments as well). Any conclusion as to the
―best‖ mode would depend on the weight given the considerations we have focused on or other
factors not considered. Staff finds that the urban design considerations do not establish a
basis for favoring either LRT or BRT at the Woodmont East plaza site.33
32
The trail connection through the tunnel is not depicted in Concept Plan drawings BM-05 and BH-05 for the
Medium and High BRT alternatives.. The staff has confirmed with the MTA project team that this connection is
included in these alternatives.
33
It should be noted that the Vision Division staff does not support BRT operating through the plaza.
34
While similar in concept, there are differences as well. The Portland vehicle is a streetcar and is smaller than the
Purple Line vehicles. Also, there is a single track in the photo and the Purple Line would have a double track or two-
way transitway.
35
The library site is a key consideration when considering alignment, however and that discussion is presented later
in the staff memo.
45
University Boulevard and Takoma/Langley Transit Center
There are different concepts for how the Purple Line would operate along University Boulevard
and connect with the Takoma/Langley Transit Center. The differences are important because the
area (like Woodmont East and the proposed location of the Silver Spring Library) are in areas
with high volumes of pedestrian activity.
The BRT Alternatives have the transitway in either shared (Low Investment) or dedicated
(Medium and High Investment) curb or outside lanes along University Boulevard. The LRT
Alternatives envision the alignment in the median of University Boulevard – at grade in the case
of the Low and Medium Investment Alternatives and elevated in the case of the High Investment
Alternative. The drawings below depict the different approaches.
Low & Medium Investment BRT Alternatives Low & Medium Investment LRT
Alternative
The most important urban design considerations in this area are as follows.
36
High Investment BRT is described in one place in the narrative of the AA/DEIS as being in the median of
University Avenue (see page 3-12) and in another (page 2-16 and 2-20) as being in dedicated (outside) lanes (as
shown on page 2-14 but in the shared configuration as part of the Low Investment BRT Alternative). The plan
drawings (drawing number BH-19 in the Conceptual Plans Technical Report) indicate the station platforms would
be on the outside lanes and on an aerial structure over University Boulevard. As of this writing, the staff finds the
plan drawings are the accurate representation of the concept plan for the High Investment BRT at this location.
46
pedestrian connectivity
pedestrian safety
impacts on street activity along University Boulevard and New Hampshire Avenue
access to the Purple Line and the proposed new Transit Center .
Recent improvements to this intersection include the installation of a fence in the median of both
University Boulevard and New Hampshire Avenue to channel pedestrian flow toward crosswalks
as well as improved sidewalk connectivity. Overall design of future improvements should
continue to place an emphasis on reinforcing and controlling pedestrian flow across both state
highways, to and from the Purple Line platform, and to and from the Transit Center.
The AA/DEIS plan drawings for this area indicate where sidewalks are to be relocated as a result
of the construction of the Purple Line. A comparison of the plans suggests that some sidewalk
connectivity may be lost under the light rail alternatives. An example of this can be seen when
examining the area on University Boulevard between Gilbert Street and Merrimac Drive.
Segments that do not appear to have sidewalks include an area on the south side of University
Boulevard immediately west of Carroll Avenue and the north side of University Boulevard west
(and east) of Merrimac Drive.37 The staff has reviewed this issue with the MTA project team and
they have indicated that there will be no net loss of sidewalk segments along University
Boulevard resulting from the construction of the Purple Line. We will continue to review this
with the overall objective of insuring that the plans reflect no loss of connectivity and a sidewalk
width of at least eight feet – consistent with the County standard and Master Plan
37
See drawings BM-18 and LM-18 of the plan drawings in the Conceptual Plans Technical Report for comparison.
47
recommendations for shared use paths on both sides of University Boulevard that also include a
(minimum) five foot planted buffer be located between the roadway and the sidewalk.38
Pedestrian access and mobility was also recently examined by a study funded under the COG’s
Transportation/Land Use Connections Program. This study recommended that light rail be
designated as the preferred mode of the Purple Line noting the following:
―It is preferable that the Purple Line be light rail rather than Bus Rapid Transit. Light rail is
more predictable for pedestrians seeking to cross the travel way and creates less noise and
pollution which is especially important for those on foot. If the Purple Line is Bus Rapid Transit,
special effort will be needed to ensure pedestrian access, mobility and comfort, given the vital
link between pedestrians and transit. The Sector Plan process will look into this in working with
MTA to develop recommendations for the Purple Line.‖39
The AA/DEIS does not indicate any material difference between the modes with respect to noise
in this area nor any material difference with respect to pollution overall. As noted above, the plan
drawings in the AA/DEIS seem to indicate that sidewalk connectivity may be more of an issue
with the median alignment of Light Rail than the BRT alignment that operates in the outside
lane.40 We do know from the sections posted on the project web site that the median alignment
requires on average an additional ten feet of right-of-way in this area.
Finally, there is the issue of the mode and the potential for economic revitalization. Mayor Bruce
Williams of the City of Takoma Park has forwarded a letter to Chairman Hanson expressing the
City’s support for light rail and noting that light rail is:
―critical to joint economic revitalization efforts in the Takoma/Langley commercial district BRT
would not give the strong economic shot in the arm‖ …
In addition to the City of Takoma Park, Prince George’s County Council Chairman Samuel H.
Dean also submitted testimony at a recent MTA Purple Line public hearing in favor of light rail.
Mr. Dean’s testimony included the following comments about Langley Park:
―..This priority development and redevelopment area of the County offers some of the most
valuable TOD opportunities once it is confirmed that the Purple Line will be built. And will be
built as light rail, which provides the demonstrable public sector commitment that the
development community often looks for before investing in first tier suburban communities such
as ours.‖
38
The state standard width for a sidewalk in this area is five feet.
39
See item number 8, pages 16 and 17, Takoma/Langley Crossroads Pedestrian Access and Mobility Study, July
2007, COG.
40
It should be noted that the Study was completed over a year in advance of the release of the AA/DEIS and
therefore the report authors did not have access to the AA/DEIS findings related to noise, pollution, or potential
issues related to sidewalk connectivity.
48
There are a number of studies that have examined the impact transit has on property values
including a 2007 study conducted by the University of Waterloo.41 The study included a
literature review that compared past analysis of the impact of both BRT and LRT systems. The
results are summarized in the accompanying charts. As noted in the charts, there is no
discernable difference between the two modes.
41
Presentation entitled ― Land Use Impacts of New Bus and Subway Services‖, August 2007 TRB Conference,
Jeffery Casello and Clarence Woudsma, University of Waterloo
42
For complete working paper see the following link: http://www.mwcog.org/uploads/committee-
documents/bF5fVl1Z20080425144722.pdf. The report was prepared by HDR/HLB Decision Economics.
49
With respect to comparing bus and rail the report notes:
―Bus investments can outperform rail alternatives in terms of absolute rate of return, but rail
investment can generate significantly greater absolute levels of economic benefit and net
benefit.‖
Finally, the Takoma/Langley Sector Plan joint planning process now underway with Prince
George’s County and the City of Takoma Park has included an examination of whether LRT or
BRT is the preferred mode for the Purple Line. While not a final decision, there is consensus
among the staff (and some public officials as noted above) that LRT would better serve the
vision of a more compact, pedestrian friendly Crossroads area.
A summary of the comparison of BRT and LRT in the context of urban design (including the
potential for economic development) would therefore include the following:
LRT relative to BRT could make sidewalk connectivity more of a challenge in the
Takoma / Langley area based on the extra space required for the median location for LRT
compared to the curb lane design treatment for BRT considered in the AA/DEIS.
A recent and fairly broad based literature survey comparing the impact of BRT and LRT
on property values does not seem to suggest one mode is inherently better.
Based upon one recent analysis of a region-wide improvements in the Cincinnati area,
BRT may offer a greater return per dollar invested but LRT’s total and net benefit far
exceed that of BRT.
Takoma Park and Prince George’s County have formally endorsed light rail – both citing
economic development as a reason. The on-going Sector Planning effort will likely reach
a similar conclusion.
Staff finds that the urban design and economic development considerations we have
examined for the Takoma/Langley area favor LRT but that it should not be a deciding
factor for the entire alignment.43
Cost, cost effectiveness. and ridership estimates in the AA/DEIS were developed by the MTA
using methodology that is both specified and reviewed by the FTA.
Estimated capital costs vary significantly by mode as noted in the graph below:
43
It is important to note when considering the relative advantages and disadvantages of BRT and LRT in the
context of economic development in particular, our assumption is that the BRT level and quality of service is the
same as for the LRT system. Once that assumption is acknowledged, available objective studies we were able to
locate do not lead the staff to conclude that one mode is preferable to another. It is the level and quality of transit
service, the commitment to pedestrian access and safety reflected in the design of the surrounding public realm near
the station areas, and the extent the transit service offers the potential user a real alternative to trips by auto that help
create a place and set the stage for economic development and revitalization.
50
FIGURE 7 – Capital Costs
Estimated annual operating costs also vary by mode but the variance is not quite as large as the
capital costs:
Estimated average weekday ridership in 2030 does not vary as much by mode:
51
FIGURE 9 – Estimated Weekday Ridership (2030)
Finally, the FTA measure of cost effectiveness, the ―annualized cost per hour of user benefit‖,
varies (one mode relative to the other) in a range somewhat similar to that of the annual
operating costs44:
44
The cost effectiveness rating for the Low LRT alternative exceeds the FTA threshold and therefore would not
attain a rating sufficient to secure funding under the FTA’s New Start funding program.
52
As noted in the graphs, LRT alternatives cost more and generate more riders, although not in
proportion to the difference in the estimated capital and operating costs. Proponents of BRT
often cite this relationship as a reason to select BRT over LRT. LRT proponents often counter
with the argument that the future (beyond 2030) cost per passenger will favor LRT for the Purple
Line because the additional passengers can be accommodated without adding more buses.
As previously noted, there is considerable discussion on how, and to what extent, the cost profile
required under the FTA New Starts program should be used to select the mode. One reason is
that the secondary economic benefits attributable to either mode are simply not captured in the
current process for evaluating projects. Complicating the issue in Maryland is the fact that the
MTA currently has three active planning projects underway (the Purple Line in Montgomery and
Prince George’s County, the Corridor Cities Transitway in Montgomery County, and the Red
Line in Baltimore). Some advocate selecting BRT for the Purple Line because doing otherwise
could potentially jeopardize funding for the Corridor Cities Transitway.
The staff recognizes that serious consideration needs to be given to the cost implications of any
recommendation on the selection of the mode for the Purple Line. The overriding fact that we
think needs to be considered at this point, however, is that a decision should first be based upon
the following goals:
There are many issues related to infrastructure funding at the local, state, and federal level. Some
of the issues are as fundamental as to whether the current funding programs at the federal and
state level need to be completely restructured to better insure long term funding for transit. A
2007 Study commissioned by the Maryland General Assembly provided some insight to the size
of the challenge as depicted in the chart below:
FIGURE 11 –
53
As shown in the chart, the projected funding level under the current program structure will cover
only the operating costs of the state’s transit systems. Critical other needs such as purchasing
replacement buses and train cars (system preservation) and system expansion are not expected to
be covered by the projected transit funding level after about 2012.45
The chart also depicts the proportion of the state funds that the New Starts projects comprise. In
the overall program – both in the near term and later – the three New Starts projects represent
around 25% of the total during the years that they would require the highest level of funding
relative to the other program activities (operating costs, system preservation, and expansion).
Staff finds that cost –and cost effectiveness ratings favor BRT but should not be a deciding
factor in determining whether the Purple Line should be BRT or LRT.
Public Testimony
Staff characterizes the public testimony as generally more favorable to LRT as compared to BRT
for those citizens speaking in favor of a public transitway. This is a trend notable in many study
corridors where the two modes are presented as alternatives; light rail is generally perceived as
being more comfortable and providing a more permanent investment in a community. In the
Purple Line corridor, staff notes that many of the stakeholders testifying in favor of BRT over
LRT cite the preservation of the Capital Crescent Trail among the reasons. Staff suggests that
while concerns regarding impacts to the Capital Crescent Trail are valid, they are related to the
choice of alignment, not mode.
Representatives of the Prince George’s County Executive Branch and County Council have
already expressed a preference for LRT in testimony to MTA. Both counties will need to concur
on the Purple Line mode to present a convincing case to state and federal officials that the
project should move forward.
Staff finds that the public and elected official testimony that generally favors LRT over
BRT should be considered, but not be the deciding factor in determining the Purple Line
mode.
Our examination of what we find to be the key issues related to the selection of the mode for the
Purple Line leads us to conclude that the preferred mode should be light rail.
The first is that the ridership estimates indicate that the peak hour directional line load in
the design year (2030) could approach 2,000 passengers per hour. A BRT system could
45
The chart does not reflect recent announcements by the state related to anticipated reductions in the level of funds
available in the Transportation Trust Fund resulting from the current economic environment. In addition, the chart
list one New Starts project (the ―Green Line‖ in Baltimore) that has effectively been placed ―on hold‖ by the state
with respect to the funding of planning, engineering, or construction activity.
54
have difficulty accommodating that ridership without resorting to more frequent service
that could introduce operational instability.
There are uncertainties in any forecast. LRT provides a margin for error if the forecast for
2030 is conservative and additional capacity to accommodate the incremental ridership
growth beyond 2030.
LRT is consistent with our adopted Master Plans, and generally supported by current
public testimony.
55