I-3 WSD 12-PS 27-0
I-3 WSD 12-PS 27-0
SECTION 27
General 27.01 (1) The Contractor shall ensure as a priority in all activities connected
with the Works, the safety and health of all persons on or adjacent to
the Site.
(2) The Contractor shall provide and employ on the Site only such
personnel who have received adequate training including safety and
health training relevant to their tasks and adopt safe working
practices at all times and shall ensure his sub-contractors comply
with this requirement.
(3) The Contractor shall not allow any person to work on the Site who
has repeatedly breached safety requirements. A notice of such
sanction shall be displayed at a prominent place on the Site.
Legislation, 27.02 (1) The Contractor shall keep one set each of the following legislation,
Regulations regulations and/or codes of practice on the Site including, but not
and/or Codes of limited to :
Practice
Legislation
AECOM PS 27/ 1
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
AECOM PS 27/ 2
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
AECOM PS 27/ 3
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(2) The Contractor shall display advisory and warning signs, labels
and/or posters for the promotion and enhancement of safety and
health and notices concerning the availability of the legislation and
documents stated above at prominent locations around the Site
including site offices, workshops and canteens.
AECOM PS 27/ 4
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
SAFETY PLAN
Safety Plan 27.03 The Contractor shall in accordance with SCC Clause 23 prepare and submit
to the Engineer six copies of the Safety Plan signed by the Site Agent and the
Safety Officer. It shall contain details of the following 14 key elements of a
safety management system:
- safety policy
- safety organization
- safety and health training
- safety rules and regulations
- safety committees
- safety and health inspections
- job hazard analysis
- personal protective equipment
- accident/incident investigation
- emergency preparedness
- safety promotion
- health assurance programme
- evaluation, selection and control of sub-contractors
- process control programme
(b) declare that safety and health are given priority in all aspects of
the Works and in discharging its contractual obligations.
(d) identify the key senior personnel for overall co-ordination and
implementation of the policy,
AECOM PS 27/ 5
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(a) define clearly the safety and health responsibilities of staff at all
levels including those of sub-contractors,
(c) list the names and telephone numbers of the senior manager,
site agent, Safety Officer and Safety Supervisors administering
and ensuring compliance with the Safety Plan, together with
their disciplines and the geographical area of the Works under
the supervision of each Safety Supervisor, revised and
re-issued at any time necessary to reflect accurately the current
arrangement for safety supervision,
(d) state the powers vested in the safety staff which would enable
them to take urgent and appropriate action to make safe the
Site and the Works and to prevent unsafe working practices or
other infringements of the Safety Plan or statutory regulations,
(e) state the name of the personnel responsible for updating the
Safety Plan, and
AECOM PS 27/ 6
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(c) Specific rules and regulations laid down by the client for Works
to be carried out within premises that are occupied, partially
occupied and/or controlled by the client, and
AECOM PS 27/ 7
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(a) procedures for the recording and regular review of the risk
assessments and the developed safe working procedures and
method statements to ensure that the risk control measures
contained therein are suitable and relevant to the Works being
undertaken; these should include those prepared by
sub-contractors, and
(b) means to ensure that the risk control measures contained in the
risks assessments, safe working procedures and method
statements are clearly written down and communicated to those
supervising and carrying out the Works and that their
implementation are being regularly monitored.
AECOM PS 27/ 8
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(a) the keeping of accidents statistics and their analysis with a view
to identifying trends and developing measures for prompt
implementation against recurrences, and
AECOM PS 27/ 9
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(g) the first aid personnel and facilities, including arrangements for
transporting the injured, and
AECOM PS 27/ 10
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
AECOM PS 27/ 11
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
- Housekeeping
- Traffic control and transportation
- Fire prevention measures and fire fighting equipment
- Excavation
- Working in confined spaces
- Hand dug caissons
- Diving
- Hot work
- Electrical equipment and installations
- Welding/cutting operations
- Personal protective equipment
- Conveyance, handling and use (blasting) of explosives
- Lifting operation involving cranes and hoists etc.
- Manual handling
- Scaffolding and working platforms
- Ladders and accesses
- Hand tools and portable power driven tools
- Use and storage of hazardous substances including
chemicals
- Working over water or adjacent to water
- Working at height
- Structural steel erection
- Floor and wall openings and stairways
- Lighting
AECOM PS 27/ 12
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
SAFETY ORGANIZATION
Safety 27.04 The Contractor shall provide to the Engineer's Representative at monthly
organisation intervals an updated safety organization chart containing a complete list of all
sub-contractors, whether directly employed by the Contractor or not, on the
Site and the Works and the name of the Safety Supervisor for each such
sub-contractor, insofar as the employment of a Safety Supervisor is expressly
set out in the Contract or in the absence of such requirement then by any
enactment or statutory requirement. The list shall also include the names of
the Safety Officer and Safety Supervisors, and the names of Safety
Representatives and the respective labour groups or teams they belong.
Telephone numbers of these safety staff shall also be shown on the chart.
SAFETY OFFICER
Safety officer 27.05 (1) "Safety Officer" means a person registered as a safety officer in
accordance with the Factories and Industrial Undertakings (Safety
Officers and Safety Supervisors) Regulations (FIU(SO&SS)R) and
employed by the Contractor to carry out the duties of a Safety Officer
as specified in the Contract and duties specified in the
FIU(SO&SS)R.
AECOM PS 27/ 13
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(2) The Contractor shall employ at least one Safety Officer who shall be
approved by the Engineer. If the total number of workers employed
on the Works or in connection with the Contractor whether in the
employ of the Contractor or his sub-contractor is equal to or more
than 50, the Safety Officer shall devote the whole of his time to this
Contract in the discharge of his duties. Where the number of
workers thus employed exceeds 200, then the number of full-time
Safety Officer to be provided shall be :
201 to 700 2
701 to 1200 3
1200 and above 4
If the total number of workers employed is less than 50, the Safety
Officer may be engaged part time for this Contract but with
sufficient presence on the Site to perform the duties of a Safety
Officer. The time thus spent on site shall be not less than 12 hours
per week excluding attendance of the Site Safety and Environmental
Management Committee meeting and the Site Safety and
Environmental Committee meetings.
(3) The Contractor shall not commence any construction work on the
Site without the appointment of the required number of Safety
Officer(s) unless expressly permitted by the Engineer in writing.
(4) The duties of the Safety Officer shall be solely directed towards
safety and health matters. In addition to the duties stipulated in the
Factories and Industrial Undertakings (Safety Officers and Safety
Supervisors) Regulations, the Safety Officer shall :
(c) Ensure that sub-contractors and all persons working on the Site
are made aware of and comply with the Safety Plan.
(d) Carry out internal safety audits for the Safety Plan at intervals
of not less than once every six months, which format, scope
and programme are to be proposed and agreed with the
Engineer. In this respect, the internal safety audits can be
carried out either by the Safety Officer or a Registered Safety
Auditor (RSA).
AECOM PS 27/ 14
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(5) The Safety Officer shall maintain a safety diary which shall record all
matters related to safety and health, including Safety Supervisors'
reports, details of safety inspections and audits, accidents, dangerous
occurrences, safety related incidents, etc. The Safety Officer shall
check to ensure that all unsafe situations are promptly rectified and
the dates of their completion duly recorded in the safety diary. The
safety diary shall be made available for inspection by the Engineer
upon request and copy thereof shall be submitted to the Engineer
upon request.
(6) The Contractor shall empower the Safety Officer to order any person
working on the Site to suspend any unsafe operation or to take urgent
action to make safe the Site or the Works or to disallow any practice
which may infringe the Safety Plan or any statutory safety
requirement.
(7) The Safety Officer shall carry out comprehensive safety inspection
on all activities on the Site at weekly intervals. The safety
inspection shall identify any unsafe operation or potential hazards
using a check-list agreed by the Engineer's Representative. The
Safety Officer shall give prior notice to the Engineer's Representative
of the date and time of the weekly inspection and shall allow the
Engineer's representative to attend the inspection.
(8) If the Safety Officer is unable to perform his duties for any reason,
the Safety Officer shall be replaced as soon as practicable but in any
case within 14 days. The Safety Officer shall not be replaced
without consent by the Engineer.
(9) The Safety Officer shall be clearly identified on the Site by wearing
an armband or a safety helmet appropriately marked in Chinese and
English.
SAFETY SUPERVISORS
Safety 27.06 (1) "Safety Supervisor" means a person employed by the contractor or
supervisors his sub-contractors on the Site to carry out the duties of a Safety
supervisor as stipulated in the Factories and Industrial Undertakings
(Safety Officers and Safety Supervisors) Regulations. The Safety
Supervisor shall carry out safety inspections on all active parts of the
Site for which he is responsible at least at daily intervals using an
appropriate comprehensive checklist agreed by the Engineer. All
completed safety checklist shall be signed by the Safety Officer to
ensure prompt follow-up actions have been taken on unsafe
situations.
AECOM PS 27/ 15
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
SAFETY REPRESENTATIVES
Safety 27.07 (1) In addition to the Safety Officer and Safety Supervisors, the
representatives Contractor shall appoint the foreman or ganger of each labour group
or team working on the Site to act as Safety Representatives. The
Safety Representative shall be responsible for ensuring that the
directives from the Contractor, the Safety Officer and Safety
Supervisors on safety and health matters are duly carried out, safety
practices are adopted and protective clothing and equipment are used
by the work force at all times on the Site. Normally, each gang of
workers shall have one Safety Representative. He shall be made
aware of his responsibilities and the group of workers on the Site
whose activities he is required to supervise. Every worker working
on the Site shall be made aware of the roles of the Safety
Representatives and from which Safety Representative he may seek
advice or receive instructions on safety and health matters.
AECOM PS 27/ 16
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
SAFETY TRAINING
Safety training 27.08 (1) The Contractor shall regularly review the training needs of all
persons employed on the Works or in connection with the Contract
and prepare a long-term training programme. Each month the
Contractor shall submit a proposed training programme to be
provided in the next month for the Engineer's approval. It shall
contain the topics, dates, venues, the target participants of the
proposed training and the names and qualification of the trainers.
AECOM PS 27/ 17
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(5) The Contractor shall also ensure that all card holders will carry their
LDRGC and Silver Card whilst working on the Site.
(6) The Contractor shall pay a token allowance of $650 to each skilled
worker of specified trades as set out in sub-clause (3) of this PS
Clause after he or she has successfully completed a Silver Card
Course and received a Silver Card. If a skilled worker of a
specified trade set out in sub-clause (3) of this PS Clause has
completed a revalidation course and received a revalidated Silver
Card, the Contractor shall pay a token allowance of $350 to each
skilled worker of specified trades. The skilled worker is responsible
for the payment of the course fee. However, the token allowance
will not be paid if the course is attended:
At the end of each month, the Contractor shall prepare and submit a
certified monthly statement of workers who have successfully
completed the trade specific advanced safety training course to the
Engineer using the proforma attached in Appendix 27.01 to this
Particular Specification. Copies of the Silver Card, the original
receipts signed by the workers for the receipt of the token allowance
and a certified payroll record indicating the trades and salaries of the
workers shall be made available for inspection if requested by the
Engineer.
(7) The Contractor shall only arrange skilled workers to attend the trade
specific advanced safety training course that is relevant to the trades
and works in which he/she is employed under the Contract. The
Engineer has a right to disapprove the payment on the trade specific
advanced safety training to a skilled worker if he / she is found on the
Site and not working for the trades and works in which he / she has
received the training.
AECOM PS 27/ 18
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(8) (a) All persons employed on the Works or in connection with the
Contract whether in the employ of the Contractor or his
sub-contractors shall receive “site specific induction training”.
(b) Site specific induction training and its refresher shall take the
form of an one-hour talk conducted by the Safety Officer in
accordance with PS sub-clause 8 (e) below.
(d) The Safety Officer shall prepare the talk based on Part II of the
“Site Safety & Health Induction Training Manual” published
by the Hong Kong Construction Association Ltd.
AECOM PS 27/ 19
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(9) (a) The Contractor shall provide tool box talks as a frequency of
one talk per worker on Site every two weeks commencing from
the date of commencement of the Works subject otherwise to
any change in frequency as may be approved by the Engineer.
The Contractor shall also ensure that the topic of every talk
given to a worker is relevant to his / her trade and the work that
he / she will perform under the Contract and a worker shall
attend no more than one talk on the same topic in any
two-month period.
(b) The Contractor shall propose the topics of the tool box talks at
a frequency specified in PS sub-clause (a) having regard to the
activities of the Site and the prevailing safety concern at that
time. They shall be submitted with the proposed monthly
training programme to the Engineer for his approval. The
Engineer has the right to disapprove the training programme
when the proposed topic is considered not relevant to the trade
of the workers or the prevailing work activities. Moreover,
the Engineer can request the Contractor to review the topics to
cater for special safety concern. For workers undertaking
scaffolding work including truss-out bamboo scaffolds,
demolition work and works in confined spaces, they should be
provided with suitable tool box talks prior to the
commencement of these works. Workers not having attended
the concerned tool box talks shall not be allowed to undertake
these works.
(c) The content of the tool box talks shall be based on training kits
published by the Hong Kong Construction Association Ltd.
(HKCA). Where such a proposed topic is not amongst one of
those published by HKCA kits, the Contractor shall develop
training kits to a similar standard for approval by the
Engineer’s Representative.
(d) The Contractor shall ensure that “tool box talks” are conducted
by Safety Officers or Safety Supervisors or gangers who are
competent trainers and have received training on safety training
techniques organized by the Hong Kong Construction
Association Ltd., CITA or other approved training
organizations.
AECOM PS 27/ 20
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(e) Payment for this item shall be made on a per worker per talk
basis based on a frequency of one talk per worker every two
weeks subject otherwise to any change in frequency approved
by the Engineer and the Engineer being satisfied that the talks
have been conducted in accordance with this PS clause. Any
tool box talks conducted in excess of the specified frequency
and without approval from the Engineer shall be deemed to
have been borne by the Contractor in the rates inserted
elsewhere in the Schedule of Rates.
(11) The Contractor’s Site Agent or Safety Officer shall certify the
accuracy of attendance records on site specific induction training and
tool box talks before they are submitted to the Engineer for payment.
If requested by the Engineer, the Contractor shall give at least
24-hour notification on the time and venue of each tool box talk to
the held, so that the Engineer could arrange his / her staff to take
attendance record for measurement.
(12) The Contractor shall ensure that all site management and supervisory
staff, who are employed on the Works whether employed by the
Contractor or sub-contractors of all tiers, shall attend, if they have
not done so, and complete the basic training commensurate with their
duties, as follows:
AECOM PS 27/ 21
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(b) The term “supervisory staff” means gangers and foremen. The
basic training required to be attended by supervisory staff shall
include:
(13) The Contractor shall keep on Site records of all safety training
received by his staff including those on refresher training and make
them available for inspection by the Engineer’s Representative upon
request.
RISK ASSESSMENT
Risk assessment 27.09 The Contractor shall carry out, review and submit to the Engineer risk
assessments for works scheduled to start at least for the next two months.
The works shall be broken down into jobs/tasks for hazard identification and
evaluation of the level of risk by competent persons. The documentation
shall contain the hazards identified, the likelihood and consequence of the
hazards occurring, the level of risk thus evaluated, the proposed risk
mitigation/control measures and the anticipated residual risks, and identify
the respective risk controller. The results of such risk assessments and
documentation shall be endorsed by the Safety Officer and the Site Agent.
In addition, they shall be incorporated into the Safety Plan or relevant safety
working procedures or method statements. In addition, the Contractor shall
also maintain an updated register of all risk assessments carried out, and
update the relevant safety checklist based on the safety measures
recommended in each new risk assessment.
Site safety and 27.10 (1) The Contractor shall establish a Site Safety and Environmental
Environmental Committee (SSEC) which shall be responsible for ensuring the
Committee implementation of the Safety Plan and the Environmental
Management Plan (EMP), reviewing and monitoring the
effectiveness of the safety, health and environmental measures taken
and seeking the co-operation and commitment of staff at all levels.
AECOM PS 27/ 22
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(2) The Site Safety And Environment Committee shall be chaired by the
Site Agent with members comprising a representative at senior
management level from the Contractor's headquarters or the project
manager, the Safety Officer, Environmental Officer, all Safety
Supervisors, all Environmental Supervisors, selected Safety
Representatives and other staff of the Contractor or sub-contractors
as may be considered necessary. It shall meet at monthly or more
frequent intervals discussing all matters relating to the
implementation of the Safety Plan and the EMP. The first meeting
shall be held no later than 30 days after the date for commencement
of the Contract Period. The Contractor may invite any other party
such as the Labour Department, Environmental Protection
Department, Fire Services Department, Police or representatives of
utility undertakers to attend the meeting and provide advice as
necessary.
(3) The Contractor shall give an advance notice of every Site Safety And
Environmental Committee meeting to the Engineer's Representative
who will attend the meeting in person or nominate a representative to
attend the meeting as an observer.
(4) The following items shall, amongst others, be discussed at the Site
Safety And Environmental Committee meeting:
AECOM PS 27/ 23
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
AECOM PS 27/ 24
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
Site safety and 27.11 (1) The Engineer shall establish a Site Safety And Environmental
environmental Management Committee (SSEMC) to monitor the adequacy of the
management Safety Plan and the Environmental Management Plan (EMP) and
committee ensure their implementation on Site by the Contractor, and to
enhance communication between the Engineer and the Contractor on
safety, health and environmental matters. The Site Safety And
Environmental Management Committee shall be chaired by the
Engineer or his Representative and shall meet at monthly or more
frequent intervals. The first meeting shall be held no later than 30
days after the date for commencement of the Contract Period.
(2) The Contractor shall provide all necessary assistance required for the
proper functioning of the Site Safety And Environmental
Management Committee and shall be represented on the Committee
by a representative at senior management level from the Contractor’s
headquarters or the project manager, the Site Agent, the Safety
Officer, the Environmental Officer, Safety Supervisors and
Environmental Supervisors. The Contractor shall act without delay
upon the decisions or recommendations made by the Committee on
matters of safety, health and environmental. The above arrangements
are entirely without prejudice to and do not relieve the Contractor
from any contractual or legal obligation with respect to safety, health
and environmental. Where a Specialist Contractor is directly
employed, a representative at the senior management level from the
Specialist Contractor’s headquarter or his project manager, Site
Agent, Safety Officer, Environmental Officer, Safety Supervisors
and Environmental Supervisors shall also attend this meeting.
(4) The following items shall, amongst others, be included in the agenda
of each SSEMC meeting:
AECOM PS 27/ 26
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(5) The Engineer may invite any other parties, such as Labour
Department, Environmental Protection Department, Fire Services
Department, Police, representatives from utility undertakers and the
departmental Safety Advisory Unit to attend the Site Safety And
Environmental Management Committee meeting and provide advice
as necessary.
(6) The Engineer or his Representative shall prepare the minutes of the
Site Safety and Environmental Management Committee meeting for
distribution to all attending parties within 10 working days of the
meeting. The minutes of each meeting shall be signed by the
Engineer or his representative and the Site Agent.
Weekly safety 27.12 (1) The Contractor should arrange a weekly safety walk attended by the
walk Contractor’s Safety Officer and Site Agent or his delegate and the
Engineer’s nominated site representative to inspect the Site checking
that safety and health conditions are being maintained on the Site.
It shall include, but not be limited to:
AECOM PS 27/ 27
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(2) The Contractor shall prepare and agree with the Engineer's
Representative a comprehensive checklist for use during safety walk
and site inspections. It shall contain a table listing out the
deficiencies identified during the walk/inspection with the proposed
rectification measures, the names of the persons responsible for
taking any necessary rectification measures and the corresponding
completion dates. More than one comprehensive checklist may
need to be prepared by the Contractor to suit the variety of works at
various portions of the Site.
(3) Immediately after the safety walk, the comprehensive checklist shall
be agreed and signed by the Safety Officer and the Engineer's
nominated site representative and a copy kept by the Engineer's
Representative. The Contractor shall take prompt action to rectify
those deficiencies identified during the walk and shall report the
status of actions taken at the forthcoming SSMC meeting.
Sub-contractors 27.13 (1) The Contractor shall provide each sub-contractor with sets of site
rules and regulations, safe working procedures and safety obligations
to ensure compliance.
(2) The Contractor shall, for contracts where more than two contractors
are working in close proximity, establish a safety co-ordination
system to liaise amongst the sub-contractors and to maintain a safe
working environment.
AECOM PS 27/ 28
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
Reporting 27.14 (1) In addition to the requirements of the General Conditions of Contract
Clause 29, the Contractor shall complete any other forms as the
Commissioner for Labour may require including, but not limited to,
forms requesting supplementary information used by the Labour
Department for the purpose of accident analysis. Copies of such
forms should be made available for inspection by the Engineer upon
request.
(2) Further to PS sub-clause (1) above, the Contractor shall notify the
Engineer immediately of any accident occurring on the Site
involving dangerous occurrence or death or serious personal injury.
The initial notification may be made verbally. A written
notification with details shall be made within 24 hours of the
occurrence of the accident.
(4) The Contractor shall submit a monthly report for consideration at the
meeting of the Site Safety Management Committee. It shall be
prepared by the Safety Officer and duly endorsed by the Site Agent,
to the Engineer containing the following information:
(c) proposed training programme for the next month and training
carried out in the previous month,
AECOM PS 27/ 29
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(5) Within 14 days from the request of the Engineer, the Contractor shall
submit a written report to explain the high accident rates and to
propose measures to improve the safety performance of the Site.
Further safety 27.15 (1) Safety, rescue and health matters shall be given a high degree of
measures publicity on the Site. The Contractor’s safety policy statement,
emergency procedures and any rescue organization shall be made
known to all persons on the Site. Such information shall include an
emergency telephone list including the names and contact telephone
numbers of the appropriate divisional police, fire and ambulance
stations, utility undertakers and Labour Department’s Operation
Division. Copies of the above information and safety posters, in
Chinese and English languages, shall be displayed at prominent
places on the Site. A notice board shall be erected near the entrance
of the Site for the display of safety posters, up-to-date accident
records and the names of the Safety Officer and the Site Agent.
(2) The Contractor shall ensure that all tools, plant, equipment and
temporary facilities and all other items used in carrying out the
Works how-so-ever provided are in a safe, sound and good condition,
are capable of performing the functions for which they are intended,
and where required by the law or by the relevant codes of practice,
are licensed and/or have been issued with the necessary permits for
use.
(5) Fences and/or nets of adequate strength shall be provided along all
edges where workers may be liable to fall into water. If it is not
possible to provide such fences and nets, persons working over or
immediate adjacent to water shall wear a life jacket or a suitable
buoyancy aid or a personal fall arrestor (as it appropriate) when so
working.
AECOM PS 27/ 30
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(7) Alcoholic drinks and other substances which may impair judgement
shall be prohibited from the Site. The Contractors shall remove any
person under the influence of such substances from the Site
immediately.
(10) All lifting gear including slings, shackles and such like equipment
shall be colour coded for identifying lifting gear which require
re-inspection or disposal. Details of the colour coding system are
given in Appendix 27.02 to this Particular Specification.
(11) All material hoists installed shall be fitted with fail-safe interlocking
hoistway gates such that the driving mechanism is operable only
when all gates are closed and latched; and hoists shall not be
operated manually when one gate is opened. A single channel
communication from the user to the operator of the hoist shall also be
provided.
(12) All persons engaged in works with risks of receiving foot injuries
including but not limited to pneumatic drilling work and manual
handling work shall be provided with safety boots when they are
engaged in such works. The cost of provision of safety boots shall
be deemed to have been allowed in the Contract Rates. Safety
boots shall comply with BS EN 345 – Part 1, BS 345- Part 2 or
equivalent standards.
AECOM PS 27/ 31
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(b) hazards,
(15) Receptacles with full containment on four sides to prevent the falling
out of materials shall be used for the lifting and transportation of
reinforcement links, stirrups, short pieces of splice or reinforcement
U-bars, couplers and the like. The safe working load shall be
marked on the receptacle after being tested by a competent examiner.
The colour coding system for lifting gear shall also apply to these
receptacles.
(16) The lifting of reinforcement bars shall be by the use of wire slings.
No cradles shall be used for the lifting of reinforcement bars unless
they are properly designed and with their safe working load certified.
(18) Construction vehicles and plant used on Site shall be equipped with
audible signals on reversing. Other form of warning signals and / or
banksman shall be provided as necessary to guide such reversing
movements if audible signals are causing nuisance to nearby
residents particularly at night. For quarry operations, no person
shall operate or drive any mechanical equipment at or near the edge
of any face, side, tip or embankment in a quarry unless a banksman is
in attendance.
AECOM PS 27/ 32
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(19) Where there are more than one tower cranes operating within the Site
and there is a possibility of overlapping crane movements, the
Contractor shall develop, implement and maintain a safe system of
work to prevent the overlapping of tower cranes lifting operation.
The system shall include, but not limited to, the following:
ELECTRICAL SAFETY
Electrical safety 27.16 (1) A Registered Electrical Worker (REW) of the appropriate grade
under the Electricity Ordinance (EO) shall be employed by the
Contractor throughout the Contract to handle the entire temporary
electrical systems and installations on the Site.
AECOM PS 27/ 33
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(2) Upon completion of the temporary electrical system (TES) and after
each alteration / repair to the existing TES, the Contractor shall
arrange his REW / Registered Electrical Contractor (REC) under the
EO to complete an individual Work Completion Certificate (WR1) as
required by the Code of Practice for the Electricity (Wiring)
Regulations (COP) issued by the Electrical and Mechanical Services
Department. If a REC is not employed, the Contractor shall then
assume the responsibilities of a REC and sign on the WR1 together
with the REW employed by the Contractor as per Code No. 19B (d)
of the COP. Each of such Certificates shall include a circuit
diagram clearly indicating which portion(s) of the TES is / are
covered, and, where appropriate, other necessary supporting
documents.
(4) The sheath of all electric portable cables shall be of heavy-duty type
or otherwise adequately protected against mechanical damage if laid
on ground. They shall be hung overhead as far as possible.
Ordinary PVC cables, if employed, shall be enclosed in metallic
conduits or trunkings and properly maintained.
(5) The Contractor shall develop checklists for carrying out regular
routine inspections and checking and monthly comprehensive
checking of the TES. The checklists shall be developed by the
Contractor and agreed by the Engineer’s Representative.
Comprehensive checking shall include, but not be limited to,
checking of temporary generators, functional test of earth leakage
circuit breakers, integrity of cables and connections, measurement of
earthing resistance and those items listed in Checklists Nos. 3 and 4
of the COP where appropriate. The checklist should be signed by
the REW after each inspection and / or checking.
(7) The Contractor shall keep and maintain updated circuit diagrams,
WR1 (complete with supporting documents) and records of
inspection and checking of the TES by REW / REC in a dedicated
file for inspection by the Engineer’s site supervisory staff upon
request.
AECOM PS 27/ 34
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(8) During weekly safety walks and when requested by the Engineer’s
site supervisory staff, the Contractor shall open the cover plates of
temporary electricity distribution boards for inspection of the
conditions of the internal wiring and / or carry out testing
immediately. Updated schematic circuit diagram shall also be
affixed inside the cover of the temporary distribution boards.
(9) All temporary electrical distribution boards shall be kept locked and
accessible only by authorized persons appointed by the Contractor,
e.g. REW and / or general foreman. Legible warning notices
(Danger – Electricity) in both Chinese and English, names and
telephone numbers of such authorized persons shall be posted on the
temporary distribution boards.
(10) For work carried out in occupied buildings, unless prior approval has
been obtained and proper and safe arrangement has been made, the
Contractor shall not connect his fixed electric equipment directly to
any existing permanent distribution boards. Such connection shall
only be made through temporary distribution boards equipped with
proper protective devices.
(11) All arc welding machines and electrode holders shall comply with
BS638 : Part 7, IEC 60974-1 (or BS EN60974-1) and BS
EN60974-11 or equivalent standards. The welding machines
should be fitted with no-load voltage reducing device for protection
against electric shock at the output side. Welding machines shall be
enclosed and the metal casing shall be effectively connected to earth.
Cable terminals of the welding machines shall be effectively
insulated.
AECOM PS 27/ 35
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(13) Voltage in excess of 110V shall only be used for heavy equipment
such as hoists, tower cranes, etc. with an earth leakage circuit breaker
installed and in proper function. Portable and hand-held tools and
temporary site lighting shall be operated at a voltage of 110V or less
supplied from a step-down transformer with its output winding
centre-tapped to earth and comply with BS3535 : Part 2 : 1990 or
equivalent. All cables shall be terminated within the transformer
enclosure of Class I and IP 55 and the outgoing circuit shall be
provided with short circuit protector. In confined and damp
environment, the voltage of temporary lighting and hand-held tools
shall not exceed 25V.
Site safety cycle 27.17 The Contractor shall practise “Site Safety Cycle” (SSC) to improve and
promote the safety and health of the Site. Site Safety Cycle shall begin when
there are workers working on the Site, and shall cease by the date of
substantial completion of the Works, or at a date proposed by the Contractor
and approved by the Engineer. The activities for Site Safety Cycle for one
day, one week and one month are referred to as the “Daily Cycle”, “Weekly
Cycle” and “Monthly Cycle” respectively. Details of the activities and the
provisions for holding the activities are described below. For simplicity, the
Pre-work Exercise and Safety (PES) meeting, Hazard Identification Activity
(HIA) meeting and Pre-work Safety Checks of the Daily Cycle are
collectively referred to as the “Pre-work Activities”.
AECOM PS 27/ 36
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(i) The Contractor shall arrange and hold PES meetings each
about 10 to 15 minutes for all the persons employed on
the Works.
(iii) The first few minutes of PES meeting shall start with a
physical exercise set by the Contractor. After that, the
leader of the PES meeting shall address the attendees on
the prevailing safety and health matters related to the
Site, such as common hazards and control measures,
general fire and safety precautions, specific safety
concerns, general defects and irregularities observed in
inspections, accidents or near misses etc.. Besides, the
Contractor shall also make use of the PES meetings to
announce common safety matters in execution and
co-ordination of the Works on the Site among
sub-contractors and workers, or presenting awards to
workers and / or sub-contractors in recognition of their
good safety performance.
AECOM PS 27/ 37
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(iii) The leader of each HIA meeting shall prepare the training
materials before conduction, which shall include, but is
not limited to, hazards and control measures specific to
the works or trades, special safety concerns, assurance of
safety requirements and measures, reprimand of repeated
irregularities and malpractice etc. Besides, the leaders of
the HIA meetings shall also encourage workers to give
their views in the HIA meetings. Where necessary, Site
Agent, Safety Officer and / or Safety Supervisors who are
more experienced in provision of training shall provide
guidance and assistance to the leaders of HIA meeting
before conducting the meeting. The training materials
prepared for and the discussion during the HIA meeting
shall be recorded in a HIA table, a sample of which is
shown in Appendix 27.03 to this Particular Specification.
The HIA Table shall be kept in the Contractor’s site
office for ready inspection by the Engineer’s
Representative or his / her staff upon request.
AECOM PS 27/ 38
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(v) The Contractor can use the register for the PES meeting
for taking attendance of the HIA meeting if the attendees
have not split up into small groups. Otherwise, the
Contractor shall use separate sheets for registering
attendees of individual groups of the HIA meetings, and
attach to the register of the PES meeting held on the same
day for ready inspection by the Engineer’s Representative
or his/her staff upon request. Furthermore, the Contractor
shall complete one HIA table for each HIA meeting held
for individual groups pursuant to PS Clause
27.17(1)(b)(iv) above.
AECOM PS 27/ 39
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(i) The Contractor shall arrange the Site Agent or his / her
representative to carry out safety inspection of the Site
daily, particularly for those areas identified for
improvements in weekly safety co-ordination meetings,
Weekly Safety Walks, Site Safety Management
Committee meetings or Site Safety Committee meetings
pursuant to PS Clauses 27.17(2)(a), 27.17(2)(b),
27.17(3)(a) and 27.17(3)(b) respectively. The Site Agent
or his / her representative shall check and ensure that the
safety instructions given in PES meetings or HIA
meetings have been observed and carried out.
AECOM PS 27/ 40
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(iv) all machinery and power sources have been turned off;
(v) all openings are properly covered and all edges are
provided with fall protection measures;
(vi) all nailed timber, planks and/or sheets are piled and put
aside away from main accesses;
AECOM PS 27/ 41
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
AECOM PS 27/ 42
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(c) The Contractor shall propose the location for the erection of the
safety bulletin board and the hard-paved area pursuant to PS
Clause 27.17(5) where Pre-work Activities will be held for the
approval of the Engineer’s Representative.
AECOM PS 27/ 43
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc
Contract No. 3/WSD/12 Particular Specification
Replacement and rehabilitation of water mains, stage 4 phase 1
- remaining mains on Hong Kong Island
(d) The Contractor shall maintain the hard-paved area and the
cover throughout the Contract, and shall demolish and reinstate
the area to the satisfaction of the Engineer’s Representative
prior to completion of the Works unless otherwise agreed by
the Engineer.
AECOM PS 27/ 44
p:\60050541\tender document\3_wsd_12\final\ps\ps_text\e-3_wsd_12-ps_27-0.doc