Concrete Structures Technical Specifications (From Parsons)
Concrete Structures Technical Specifications (From Parsons)
03
503-1
503.03
503-2
503.03
503-3
503.03
137
138 Place falsework or centering upon footing safe against undermining
139 and softening when footing type foundations are to be used. Show bearing
140 value of soil in shop drawings of falsework or centering.
141
142 When used, space, drive, and remove falsework piling as accepted by
143 the Engineer. Set falsework to give finished structure camber specified.
144 Construct arch centering in accordance with centering plans accepted by the
145 Engineer. Make provisions for gradual lowering of centers and for rendering
146 arch self-supporting. Use jacks to correct slight settlement that may occur
147 during placement of concrete.
148
149 In design of bottom slab plywood forms and timber joists for concrete
150 box girders, top slab loads may be omitted when placing top slab separately
151 from webs and bottom slab.
152
153 If lost post method of concrete box girder deck forming is used, 2 by 6
154 continuous mudsills beneath posts will not be required when 2 by 4 or smaller
155 timber posts, with soft wood wedges, are used for supports.
156
157 Use manufactured items conforming to AASHTO standards. When
158 items are not covered by AASHTO, use standards of nationally known
159 organizations such as AISC for steel, ACI for concrete, and NFPA for lumber.
160 In all cases, furnish data listing manufacturer's design criteria conforming to
161 design specifications and recommendations, or perform tests, as necessary,
162 to show adequacy of proposed device.
163
164 Install falsework lighting in accordance with Section 633 – Falsework
165 Lighting.
166
167 (C) Forms.
168
169 (1) Construction. Use wood or metal forms that are mortar tight
170 and sufficiently rigid to prevent distortion due to pressure of concrete
171 and other loads, including vibration, incidental to construction.
172 Construct and maintain forms to prevent joints from opening.
173
174 Unless otherwise indicated in the contract documents, place
175 minimum 3/4 inch by 3/4 inch chamfer at sharp corners. Give girder
176 and coping forms a bevel or draft to ensure easy removal.
177
178 Set and maintain forms true to lines designated. When forms
179 appear to be unsatisfactory, either before or during concrete
180 placement, the Engineer may stop work until defects are corrected.
181
503-4
503.03
181
182 When forms are submerged in water and concrete is placed in
183 the dry, make forms watertight below high water level.
184
185 Cover knotholes and damaged areas in wood forms with metal
186 patches.
187
188 Control rate of depositing concrete in forms to prevent form
189 deflection or form panels that exceed permitted deflections. When
190 structure height is greater than 6 feet, submit rate of depositing
191 concrete.
192
193 Use forms for concrete surfaces not completely enclosed or
194 hidden below permanent ground surface that conform to
195 requirements, in this subsection, for exposed-surface forms. Interior
196 surfaces of underground drainage structures will be considered
197 completely enclosed surfaces.
198
199 Before using forming systems for exposed surfaces, submit
200 form design and materials data for each system.
201
202 Design and construct forms for exposed concrete surfaces so
203 that formed surface of concrete does not undulate excessively
204 between studs, joists, form stiffeners, form fasteners, or walls.
205 Undulations exceeding either 3/32 inch or 1/270 of center-to-center
206 distance between studs, joists, form stiffeners, form fasteners, or walls
207 will be considered to be excessive. The Engineer will reject portions
208 of concrete structure with surface undulations over limits specified
209 herein.
210
211 Form exposed surfaces of each concrete structure element
212 with same forming material or with materials that produce similar
213 concrete surface textures, color, and appearance.
214
215 For exposed surfaces, provide form panel facing consisting of
216 continuous sections of form facing material, unbroken by joint marks,
217 against which concrete is placed.
218
219 (2) Form Lumber. Use form lumber, except for curved and
220 special surfaces, of five ply panel boards or dressed shiplap, used
221 with or without form liners. Rough lumber may be used for unexposed
222 surfaces in finished structure. Three-ply panel boards may be used
223 for forming soffit of unexposed portions of box girder top slabs.
224
503-5
503.03
503-6
503.03
270 shape. Countersink bolts and rivet heads. Design clamps, pins, or
271 other connecting devices to hold forms rigidly together and to allow
272 removal without injury to concrete. Metal forms that are rough or
273 crooked will not be allowed.
274
275 (7) Reuse of Forms. Maintain shape, strength, rigidity,
276 watertightness, and surface smoothness of reused forms. Resize
277 warped or bulged lumber before using.
278
279 (D) Removal of Falsework and Forms. Before removing shoring
280 beneath beams or girders, remove forms from columns to allow the Engineer
281 to inspect condition of column concrete.
282
283 Remove supports using method that permits concrete to uniformly and
284 gradually take stresses caused by its own weight.
285
286 In continuous or rigid frame structures, release falsework only after
287 last concrete (excluding concrete above bridge deck) in that span and first
288 adjoining spans on each side have been in place for 14 days. For falsework
289 removal, consider spans with a single hinge within span to be continuous.
290 Consider hinges of suspended spans within a bridge, as ends of bridge, for
291 determining shoring requirements. In structures of these types, remove
292 falsework gradually and uniformly over whole length.
293
294 After placing concrete, remove or release falsework and forms no
295 earlier than removal times specified in Table 503.03-1 – Removal of
296 Falsework and Forms. The Engineer will determine exact removal time.
297
TABLE 503.03-1 - REMOVAL OF FALSEWORK AND FORMS
Railing and Barriers – 4 Hours and Concrete Has Hardened
Centering Under Beams, Arches, And Other Members - 14 Days
Slabs With Maximum
Thickness of (Inches) 9 12 more than 12
Removal Time (Days) 7 10 14
Walls, Columns, and 40
Vertical Sides of Beams 2 5 10 20 30 or
With Maximum Height of More
(Feet)
Removal Time (Days) 0.5 1 2 3 5 7
Note: Where forms also support vertical or horizontal loads imposed on
slab or beam soffits, use longer requirements for removal time.
503-7
503.03
298
299 Do not release falsework for cast-in-place prestressed portions of
300 structures until after prestressing steel has been tensioned.
301
302 Do not release falsework supporting overhangs and girder stems that
303 slope 45 degrees or more off vertical until 7 days after placing deck concrete.
304 If reshoring system is installed, falsework supporting sides of girder stems
305 that slope less than 45 degrees off vertical may be removed prior to placing
306 deck slab concrete. Design reshoring system, consisting of lateral supports,
307 to resist rotational forces acting on stem, including those caused by
308 placement of deck slab concrete. Install reshoring system immediately after
309 each form panel is removed and prior to release of supports for adjacent form
310 panel.
311
312 Do not remove falsework and forms supporting bottom slab of box
313 girders until 14 days after final top slab is placed. Remove forms for webs of
314 box girders before placing deck slab. Forms supporting concrete top slab of
315 box girder may be left in place. Completely remove interior forms in box
316 girders except those permitted to remain in place. Where minimum crawl
317 space dimensions and unobstructed access to enclosed utilities are provided,
318 interior forms of box girders may be left in place. Clear and sweep loose
319 material from inside of box girder.
320
321 Removal time of falsework may be reduced to 10 days when concrete
322 test specimens develop compressive strengths equal to or greater than
323 required 28-day compressive strength. Cure concrete test specimen in
324 accordance with paragraph 9.4 of AASHTO T 23.
325
326 After removing forms of railing or barriers, protect exposed concrete
327 surfaces from damage after form removal.
328
329 Falsework for concrete box culverts and other concrete structures with
330 top slabs or decks lower than roadway pavement and with spans of 14 feet or
331 less, may be released when concrete strength reaches 1,500 psi, provided
332 top slab is reshored and the curing of the concrete is not interrupted. Do not
333 impose loads (including backfill) on structure until concrete attains required
334 28-day compressive strength.
335
336 (E) Loading. Inducing loading, outside its own weight, onto any part of a
337 structure, except abutment walls and wing walls, will not be allowed until the
338 following conditions have been met: at least 15 days have elapsed since
339 placing concrete; and test specimens show that concrete has developed
340 compressive strength of either 3,000 psi or required 28-day compressive
341 strength, whichever is greater.
342
503-8
503.03
503-9
503.03
503-10
503.03
434 Top slab of box girders may be placed 10 days after placing
435 bottom slabs and stems, provided concrete test specimens of bottom
436 slab and stem concrete have attained compressive strength equal to
437 or greater than 3,000 psi. Cure concrete test specimens in
438 accordance with paragraph 9.4 of AASHTO T 23.
439
440 Place concrete in columns in one continuous operation.
441
442 Allow concrete to set at least 12 hours before placing columns,
443 caps, or beams.
444
445 Do not place horizontal members or sections until concrete in
446 supporting vertical members or sections has consolidated and
447 shrinkage has occurred. When plans require construction joints, allow
448 at least 12 hours to elapse between concrete placements.
449
450 Do not place concrete in superstructure until column forms
451 have been stripped sufficiently to determine character of column
452 concrete. Do not allow superstructure loads to be placed on bents or
453 piers until bents have been in place at least 14 days.
454
455 Do not place concrete in suspended span until adjacent
456 continuous spans are complete in place.
457
458 In structures with one or two hinges in a span, place supporting
459 ends of hinges, including top slabs, before placing supported end.
460
461 Do not place concrete sidewalks and curbs not monolithic with
462 bridge deck until falsework for spans has been released.
463
464 (4) Chutes and Troughs. The use of aluminum for chutes,
465 tremies, troughs or pipes will not be allowed. Place concrete so as to
466 avoid segregation of materials and displacement of reinforcement.
467
468 When plans require steep slopes, equip chutes with baffle
469 boards, or furnish chutes in short lengths that reverse direction of
470 movement.
471
472 Use of long troughs, chutes, and pipes of minimum 6-inch
473 diameter will be allowed only with written authorization by the
474 Engineer. Incline chutes or pipes to allow concrete to flow at required
475 consistency. Addition of water to concrete mix to promote free flow in
476 chutes of low inclination will not be allowed.
477
503-11
503.03
477 Do not drop concrete into forms from vertical distance of more
478 than 5 feet unless confined by closed chutes or pipes.
479
480 Keep chutes, troughs, and pipes clean and free from coatings
481 of hardened concrete by thoroughly flushing them with water after
482 each run. Discharge flushing water away from in-place concrete.
483
484 (5) Vibrating. Consolidate concrete, except for concrete placed
485 under water, using high frequency internal vibrators. Minimum
486 transmitted vibration frequency shall be 4,500 impulses per minute,
487 and shall be such as to visibly affect mass of concrete of 1-inch slump
488 over radius of at least 18 inches. Use sufficient number of vibrators to
489 properly consolidate incoming concrete within 15 minutes after
490 depositing concrete in forms. Make at least two vibrators available at
491 structure site when placing more than 25 cubic yards of concrete.
492 Apply vibrators at uniformly spaced points and not farther apart than is
493 visibly effective. Attaching vibrators to or holding them against forms
494 or reinforcing steel will not be allowed. Insert vibrators in vertical
495 position at a uniform spacing over the entire concrete placement area.
496 Dragging vibrators through concrete will not be allowed.
497
498 External vibrators accepted by the Engineer may be used to
499 consolidate concrete when concrete is inaccessible for adequate
500 consolidation, provided forms are constructed sufficiently rigid to resist
501 displacement or damage from external vibration.
502
503 When required, supplement vibration by hand spading with
504 suitable tools to ensure proper and adequate compaction. Manipulate
505 vibrators to work concrete thoroughly around reinforcement and
506 imbedded fixtures; and into corners and angles of forms. Using
507 vibrators to cause concrete to flow or run into position, instead of
508 placing, will not be allowed. Vibrate sufficiently to compact, but avoid
509 prolonging vibration to the point where segregation occurs.
510
511 (6) Depositing Concrete Underwater. Do not deposit concrete
512 underwater except cofferdam seals, tremie concrete, and drilled shaft
513 concrete. Use seal concrete conforming to Section 601 – Structural
514 Concrete for cofferdam seal concrete deposited underwater. Deposit
515 drilled shaft concrete underwater in accordance with Section 511 –
516 Drilled Shafts.
517
518 Place concrete underwater in a compact mass in its final
519 position by tremie or closed-bottom dump bucket. Do not disturb
520 deposited concrete after placement. Maintain still water at point of
521 deposit.
522
503-12
503.03
503-13
503.03
565
566 (G) Joints.
567
568 (1) Construction Joints. Place construction joints only at
569 locations indicated in the contract documents, perpendicular to
570 principal lines of stress and at points of minimum shear.
571
572 After placing substrate concrete to construction joint and letting
573 concrete set, thoroughly clean by abrasive blast cleaning, the entire
574 joint surface, including projecting reinforcement. Remove laitance,
575 curing compound, and other material foreign to concrete, and expose
576 cleaned coarse aggregate, and roughen construction joint surface to
577 full amplitude of approximately 1/4 inch, after curing period or
578 immediately before placing concrete on substrate concrete at
579 construction joint, whichever occurs first.
580
581 Before placing new concrete, draw forms tightly against
582 concrete already in place. Thoroughly clean, water blast laitance and
583 foreign material, and saturate old surface with water to a saturated
584 surface-dry condition immediately before placing new concrete. Place
585 concrete in substructures so that horizontal construction joints are
586 truly horizontal. Where possible, place joints such that they will be
587 hidden from view in finished structure. Where vertical construction
588 joints are necessary, extend reinforcing bars across joint to make
589 structure monolithic. Do not place construction joints through paneled
590 wing walls or other large surfaces that are to be treated architecturally.
591
592 When construction joint is necessary because of emergency,
593 furnish and place reinforcing steel across construction joint as ordered
594 by the Engineer, at no increase in contract price or contract time.
595
596 (2) Expansion Joints. Construct expansion joints of type and in
597 location indicated in the contract documents. Expansion joints may be
598 of friction, open, filled compression, mortise, or special type.
599
600 (a) Metal Friction Joints. Metal friction joints include cast
601 iron or bronze plates. Anchor plates in correct position. Plane
602 sliding surfaces true and smooth by following direction of
603 movement of structure with planing tool. Do not impede
604 movement by allowing surfaces to make contact, except for
605 bearing surfaces.
606
607 (b) Open Joints. Construct open joints of removable
608 bulkheading forms so that forms may be removed without
609 damage to concrete.
610
503-14
503.03
503-15
503.03
661 (3) Contraction Joints. Place contraction joints in walls and other
662 structures at spacing of not more than 30 feet on centers, at locations
663 indicated in the contract documents, at abrupt changes in height or
664 thickness, and at obtuse corners unless otherwise directed by the
665 Engineer.
666
667 (H) Waterproofing. Make concrete surfaces smooth and free from holes
668 and projections that might puncture waterproofing membrane. Dry and clean
669 surfaces thoroughly of dust and loose materials before waterproofing. Do not
670 waterproof in wet weather or when temperature is below 65 degrees F.
671
672 Waterproofing includes coat of primer applied to concrete surface,
673 firmly bonded membrane composed of two layers of saturated fabric
674 conforming to ASTM D 1668,, and three moppings of waterproofing asphalt.
675
676 Apply coat of primer to surface, extending 12 inches on each side of
677 joint. Allow primer to dry before first application of asphalt. Heat asphalt to
678 temperature between 300 degrees F and 350 degrees F. Mop asphalt
679 thoroughly onto surface.
680
681 Place 18-inch-wide strip of fabric immediately on hot asphalt.
682 Carefully press fabric into place to eliminate trapped air bubbles and to obtain
683 close contact with surface.
684
685 Apply second layer of asphalt onto fabric, 3 inches beyond edges.
686 Immediately following operation, press second layer of fabric into place on
687 top of first layer.
688
689 Apply third and final layer of asphalt onto fabric, 3 inches beyond
690 edges. Use 12-inch laps at ends of fabric.
691
692 Apply primer to concrete surface at rate of one gallon per 100 square
693 feet. Apply asphalt at rate of 15 gallons per 100 square feet of finished work.
694
503-16
503.03
694
695 (I) Joint Sealing.
696
697 (1) Joint Seal (Poured) for Bridge Deck. Immediately before
698 applying joint sealer, clean joints thoroughly by abrasive blasting.
699 Remove mortar, laitance, scale, dirt, dust, oil, and other foreign
700 matter, then blow out joint with high pressure, oil-free compressed air
701 to remove residue.
702
703 Apply joint sealer after the Engineer inspects and accepts joint;
704 and only when concrete and ambient temperatures are not less than
705 50 degrees F and no greater than temperature allowed by
706 manufacturer.
707
708 Apply joint sealer so that joints are filled without forming air
709 holes and discontinuities. Top of joint sealer shall be 1/4 inch below
710 finished surface.
711
712 Remove joint sealer that does not do the following: cure to
713 homogeneous and rubber-like compound; bond to joint faces; or
714 comply with other requirements of this section.
715
716 Reclean joint and place new joint sealer at no increase in
717 contract price or contract time.
718
719 After completion of joint sealing, prohibit vehicles from traveling
720 over joints until the Engineer grants permission.
721
722 (2) Joint Seal (Preformed) for Bridge Deck. Immediately before
723 installing joint sealer, clean joint thoroughly to remove mortar,
724 laitance, scale, dirt, dust, oil, and other foreign matter.
725
726 Install seal so that it will not be abraded by traffic and will
727 effectively keep foreign material from entering joint. Correct spalls
728 and protrusions in joint before installation.
729
730 Install preformed seal in one continuous piece without field
731 splices.
732
733 Place seal so that its top edge is 1/4 inch below riding surface,
734 and in a plane normal to sides of groove.
735
736 Place top edge of gasket in contact with vertical walls of joint.
737 Repair spalls and other unsound concrete. Depress seal below minor
738 spalls so that its top edge is in contact with vertical wall of joint.
739
503-17
503.03
503-18
503.03
786 in-place curing. Cure full width of concrete bridge decks using a combination
787 of impervious membrane curing and water curing. Cure concrete surfaces
788 that are to receive Class 2 Rubbed Finish, by water curing or forms-in-place
789 curing. Cure surfaces of construction joints by application of water curing or
790 non-membrane curing compound that seals concrete without reducing
791 interface bonding capacity. Before applying curing compound, submit
792 proposed curing methods, including copies of test results and manufacturer's
793 catalogue. Precast concrete members may be steam cured in accordance
794 with Subsection 504.03(G) - Curing.
795
796 (1) Water Curing. Water cure by keeping concrete continuously
797 wet with fresh water, using water sprays, acceptable water saturated
798 coverings, or ponding. Keep wood forms that remain in place
799 sufficiently damp to prevent opening at joints and drying of concrete.
800
801 After surface water has evaporated, apply moisture to concrete
802 surface using fog spray nozzle. Continue applying moisture to surface
803 until regular curing begins. Use adequate water supply and sufficient
804 moisture to fog and water cure concrete without damaging surface or
805 texture of concrete.
806
807 Begin water curing for bridge decks after curing compound is
808 applied and immediately after concrete surface is hard enough to
809 receive water without damaging surface or texture of concrete.
810 Continue water curing until end of specified curing period.
811
812 Prevent curing water from falling on traveled roadways under
813 structure. Channel curing water away from falsework and structure
814 foundations.
815
816 (2) Impervious Membrane Curing. Seal concrete surface
817 thoroughly with liquid membrane-forming compound. Apply
818 compound uniformly in two or more applications. Use ratio of at least
819 1 gallon for each 125 square feet of concrete surface.
820
821 Use curing compounds that will not permanently darken
822 concrete on exposed surfaces of completed structure. Except for full
823 width of bridge decks, do not apply membrane curing compound on
824 surface to which concrete is to be bonded or to which waterproofing or
825 epoxy is to be applied.
826
827 Keep concrete surfaces moist before applying impervious
828 membrane. If membrane film is broken or damaged during specified
829 curing period, apply new treatment to affected area, duplicating first
830 application.
831
503-19
503.03
503-20
503.03
503-21
503.03
924 (3) Class 6 Float Finish. Attain Class 6 Float Finish as follows:
925
926 (a) Finishing Bridge Decks and Bridge Approach Slabs.
927 For bridge decks and bridge approach slabs, obtain smooth
928 riding surface of uniform texture, true to required grade and
929 cross section.
930
931 Place concrete in bridge decks and bridge approach
932 slabs at a minimum finished deck placement rate of 20 linear
933 feet per hour. Measure rate along centerline of roadway.
934 Employ experienced operators and concrete finishers to finish
935 deck. Keep necessary finishing tools and equipment on hand
936 at work site and in satisfactory condition for use.
937
938 Unless acceptable lighting facilities are provided,
939 complete finishing operations during daylight hours.
940
941 Immediately before placing bridge deck concrete, check
942 falsework and wedges. Minimize settlement and deflection due
943 to added weight of bridge deck concrete. Furnish suitable
944 instruments, such as settlement gages, to permit ready
945 measurement of settlement and deflection by the Engineer.
946
947 When settlement or other unanticipated events occur,
948 stop deck concrete placement until corrective measures have
949 been submitted and accepted. If accepted corrective
950 measures have not been provided prior to initial concrete set,
951 stop concrete placement and install bulkhead at location
952 designated by the Engineer. Remove concrete placed beyond
953 bulkhead.
954
955 Place bridge deck and bridge approach slab concrete in
956 uniform heading, approximately perpendicular to roadway
957 centerline. Limit rate of concrete placement to that which can
958 be finished before beginning of initial set. Do not place deck
959 surface concrete more than 10 feet ahead of strike off. Spread
960 concrete to uniform height, such that required strike off does
961 not exceed 3 inches of concrete.
962
963 Finish bridge decks and bridge approach slabs with
964 concrete wearing surfaces in accordance with Subsection
965 503.03(M)(3)(a)1. - Machine Finishing.
966
967 Bridge decks and bridge approach slabs with asphalt
968 wearing surfaces may be finished as described in this
969 subsection.
503-22
503.03
970
971 During finishing operation while concrete is still plastic,
972 test surface with 10-foot straight edge. Test surface from side
973 or from transverse finishing bridges, in presence of the
974 Engineer. Make necessary corrections to attain required
975 tolerance, with minimum amount of remedial work after
976 concrete has hardened.
977
978 After concrete has hardened sufficiently, test finished
979 surface in presence of the Engineer with 10-foot straight edge.
980 Surface for concrete deck finish shall not vary more than 1/8
981 inch from lower edge of straight edge.
982
983 Where concrete of bridge deck and bridge approach
984 slab is to be covered with minimum 1-inch-thick layer of
985 bituminous surfacing, earth, or other cover, surface of concrete
986 shall not vary more than 1/4 inch from lower edge of 10 foot
987 straight edge.
988
989 Grind high areas in hardened surface, leaving finished
990 texture that is not smooth or polished. Produce final surface
991 with uniform texture of transverse grooves, with tine
992 dimensions in accordance with Subsection 503.03(M)(3)(a)1. -
993 Machine Finishing.
994
995 Submit method of correcting low areas. Begin
996 remediation of low spots only after the Engineer accepts
997 submittal.
998
999 Strike off bridge deck surfaces under curbs, railings, and
1000 sidewalks to same plane as roadway. Leave bridge deck
1001 surfaces under curbs, railings, and sidewalks undisturbed when
1002 future widening is shown on Plans.
1003
1004 When deck width is 4 feet or less, finishing methods
1005 other than those specified herein may be used, provided
1006 completed deck surface conforms to specified requirements.
1007
1008 Perform remedial measures on completed bridge decks
1009 and bridge approach slabs not meeting specified requirements,
1010 at no increase in contract price or contract time.
1011
1012 1. Machine Finishing. Strike off and finishing
1013 machines shall be of the self-propelled types, operating
1014 on rails and conforming to specified requirements.
1015
503-23
503.03
503-24
503.03
503-25
503.03
1108
1109 Position tines so that their widths are
1110 perpendicular to groove direction. Make grooves 1/8 to
1111 3/16 inch in depth.
1112
1113 2. Manual Finishing. After placing and
1114 consolidating concrete, finish to provide a uniform
1115 surface.
1116
1117 Use template or strike board to alternately tamp
1118 and strike off concrete, and move forward with
1119 combined longitudinal and transverse motions. Leave
1120 uniform mortar or grout film of suitable consistency on
1121 concrete surface after last pass of template or strike
1122 board.
1123
1124 Use template or strike board of rigid construction,
1125 capable of resisting deflection and distortion when in
1126 use.
1127
1128 Set supports or headers to required elevations to
1129 form bridge deck and bridge approach slab surfaces to
1130 line and grade indicated in the contract documents.
1131 Allow for anticipated settlement, camber, and deflection
1132 when computing elevations.
1133
1134 Furnish and install supports or headers such that
1135 they shall not deflect under applied loads.
1136
1137 Supports or headers for deck concrete placement
1138 shall be completely in place for full length of concrete
1139 placement and shall be secured before placing deck
1140 concrete.
1141
1142 Following completion of preliminary finish and
1143 from transverse bridges, float deck for concrete wearing
1144 surface in direction parallel to roadway centerline.
1145
1146 Transverse finishing bridges, from which floats
1147 are to be operated, shall completely span bridge
1148 roadway area to be floated. Provide easily moveable
1149 finishing bridges of rigid construction, free of wobble
1150 and springing during floating operation. Use sufficient
1151 number of finishing bridges to permit floating operation
1152 to follow preliminary finishing operations without undue
1153 delay. Use not less than two transverse finishing
503-26
503.03
1154 bridges.
1155
1156 Float with two separate wooden floats, each
1157 between 12 to 16 feet long. Use float boards 1 inch
1158 thick and 4 to 8 inches wide, with rigid ribs. Provide
1159 adjusting screws at not more than 24-inch centers
1160 between rib and float board. Maintain float board flat
1161 and true. Equip each float with adjustable handles at
1162 each end. Rib and truss each float, as necessary, to
1163 ensure float board has a true, rigid surface.
1164
1165 Operate floats with combined longitudinal and
1166 transverse motions, planing off high areas and floating
1167 material removed into low areas. Lap each pass with
1168 previous pass by half-length of float. Continue floating
1169 until smooth surface is obtained.
1170
1171 Place first float into operation as soon as
1172 concrete surface condition permits. Keep first float in
1173 continuous operation until subsidence has taken place.
1174
1175 Operate second float as far back of first float as
1176 concrete workability permits.
1177
1178 After completing floating operation, texture deck
1179 surface in accordance with Subsection
1180 503.03(M)(3)(a)1. - Machine Finishing.
1181
1182 (b) Sidewalks and Median Strips. Provide final finish for
1183 concrete sidewalks and median strips using wooden float. The
1184 Engineer will determine degree of roughness. Provide
1185 abrasive coating for top surfaces of decks, ramps, and
1186 approach ramps for pedestrian structures and top surfaces of
1187 sidewalks.
1188
1189 Create abrasive coating by sprinkling 1/4 pound of grain
1190 per square foot, uniformly, on fresh concrete. Finish surface
1191 with wooden float.
1192
503-27
503.03
1192
1193 (N) Cleaning Up. Upon completion of finishing operation and before final
1194 acceptance of structure, remove falsework, excavated or useless material,
1195 rubbish, and temporary buildings. Replace or restore public or private fences
1196 or property damaged during prosecution of work. Leave bridge site and
1197 adjacent highway in neat and presentable condition. Remove excavated
1198 material or falsework placed in stream channel during construction before
1199 final acceptance.
1200 503.03
1201 503.04 Measurement. Concrete will be paid on a lump sum basis.
1202 Measurement for payment will not apply.
1203
1204 The Engineer will consider wingwalls to be a part of the structure.
1205
1206 503.05 Payment. The Engineer will pay for the accepted concrete on a contract
1207 lump sum basis. Payment will be full compensation for the work prescribed in this
1208 section and the contract documents.
1209
1210 The Engineer will pay for the following pay item when included in the proposal
1211 schedule:
1212
1213 Pay Item Pay Unit
1214
1215 Concrete _______________________ Lump Sum
1216
1217 The Engineer will pay for excavation and backfill for foundations in
1218 accordance with and under Section 205 – Excavation and Backfill for Bridge and
1219 Retaining Structures and Section 206 – Excavation and Backfill for Drainage
1220 Facilities.
1221
1222 The Engineer will pay for reinforcing steel in accordance with and under
1223 Section 602 - Reinforcing Steel.
1224
1225
1226 END OF SECTION 503
503-28