The document outlines the construction schedule for Tower-03 of the GHR Callisto project by Spectra Constructions, detailing the slab work and finishing work timelines. It includes specific start and end dates for each floor's roof slab, plastering, block work, railings, and waterproofing, indicating the completion status of various tasks. The project spans from September 2023 to September 2025, with some tasks marked as completed, in progress, or not yet started.

Uploaded by

srimantasurveyor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views8 pages

Tower 3

The document outlines the construction schedule for Tower-03 of the GHR Callisto project by Spectra Constructions, detailing the slab work and finishing work timelines. It includes specific start and end dates for each floor's roof slab, plastering, block work, railings, and waterproofing, indicating the completion status of various tasks. The project spans from September 2023 to September 2025, with some tasks marked as completed, in progress, or not yet started.

Uploaded by

srimantasurveyor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Spectra Constructions and Infrastructure Pvt Ltd.

Project: GHR Callisto, Kolluru


LocationTower-03, structure Work

TOWER-3 STRUCTURE SLAB SCHEDULE


S.NO DESCRIPTION OF WORK DURATION STARTING DATE
1 B2 roof slab 47 9/1/2023
2 B1 roof slab 65 9/28/2023
3 Stilt roof slab 62 12/2/2023
4 1st Roof Slab 27 2/3/2024
5 2nd Roof Slab 19 3/2/2024
6 3rd Roof Slab 25 3/22/2024
7 4th Roof Slab 16 4/17/2024
8 5th Roof Slab 22 5/4/2024
9 6th Roof Slab 22 5/27/2024
10 7th Roof Slab 21 6/19/2024
11 8th Roof Slab 17 7/11/2024
12 9th Roof Slab 24 7/20/2024
13 10th Roof Slab 27 8/14/2024
14 11th Roof Slab 19 9/10/2024
15 12th Roof Slab 18 9/29/2024
16 13th Roof Slab 15 10/18/2024
17 14th Roof Slab 18 11/3/2024
18 15th Roof Slab 20 11/22/2024
19 16th Roof Slab 21 12/12/2024
20 17th Roof Slab 54 1/3/2025
21 Duplex Roof Slabs 30 5/15/2025
22 Pergola Beams 45 5/25/2025
RE SLAB SCHEDULE
ENDING DATE REMARKS
10/18/2023 Slab casting completed
12/2/2023 Slab casting completed
2/2/2024 Slab casting completed
3/1/2024 Slab casting completed
3/21/2024 Slab casting completed
4/16/2024 Slab casting completed
5/3/2024 Slab casting completed
5/26/2024 Slab casting completed
6/18/2024 Slab casting completed
7/10/2024 Slab casting completed
7/28/2024 Slab casting completed
8/13/2024 Slab casting completed
9/10/2024 Slab casting completed
9/29/2024 Slab casting completed
10/17/2024 Slab casting completed
11/2/2024 Slab casting completed
11/21/2024 Slab casting completed
12/12/2024 Slab casting completed
1/2/2025 Slab casting completed
2/26/2025 Slab casting completed
6/14/2025 Inprogress
7/9/2025 Not Yet Started
Spectra Constructions and Infrastructure Pvt Ltd.
Project: GHR Callisto, Kolluru
Locati Tower-03, Finishing Work

Tower-03, Finishing Work


Sl.No Pour Duration Remarks
Start Finish
Plaster
1 1st Floor 7-Sep-24 23-Sep-24 16.00 Completed
2 2nd Floor 24-Sep-24 4-Oct-24 10.00 Completed
3 3rd Floor 5-Oct-24 13-Oct-24 8.00 Completed
4 4th Floor 14-Oct-24 28-Oct-24 14.00 Completed
5 5th Floor 29-Oct-24 13-Nov-24 15.00 Completed
6 6th Floor 14-Nov-24 6-Dec-24 22.00 Completed
7 7th Floor 7-Dec-24 26-Dec-24 19.00 Completed
8 8th Floor 27-Dec-24 7-Jan-25 11.00 Completed
9 9th Floor 8-Jan-25 4-Apr-25 86.00 Completed
10 10th Floor 5-Apr-25 15-May-25 40.00 In Progress
11 11th Floor 16-May-25 31-May-25 15.00 Not Yet Started
12 12th Floor 1-Jun-25 16-Jun-25 15.00 Not Yet Started
13 13th Floor 17-Jun-25 2-Jul-25 15.00 Not Yet Started
14 14th Floor 3-Jul-25 18-Jul-25 15.00 Not Yet Started
15 15th Floor 19-Jul-25 3-Aug-25 15.00 Not Yet Started
16 16th Floor 4-Aug-25 19-Aug-25 15.00 Not Yet Started
17 17th Floor 20-Aug-25 4-Sep-25 15.00 Not Yet Started
18 18th Floor 5-Sep-25 20-Sep-25 15.00 Not Yet Started

Block work
1 1st Floor 18-May-24 11-Jun-24 24.00 Completed
2 2nd Floor 13-Jun-24 7-Jul-24 24.00 Completed
3 3rd Floor 8-Jul-24 16-Jul-24 8.00 Completed
4 4th Floor 17-Jul-24 1-Aug-24 15.00 Completed
5 5th Floor 2-Aug-24 24-Aug-24 22.00 Completed
6 6th Floor 25-Aug-24 20-Sep-24 26.00 Completed
7 7th Floor 21-Sep-24 21-Oct-24 30.00 Completed
8 8th Floor 22-Oct-24 6-Nov-24 15.00 Completed
9 9th Floor 7-Nov-24 27-Nov-24 20.00 Completed
10 10th Floor 28-Nov-24 8-Dec-24 10.00 Completed
11 11th Floor 9-Dec-24 14-Dec-24 5.00 Completed
12 12th Floor 15-Dec-24 30-Dec-24 15.00 Completed
13 13th Floor 31-Dec-24 11-Jan-25 11.00 Completed
14 14th Floor 12-Jan-25 19-Feb-25 38.00 Completed
15 15th Floor 20-Feb-25 14-May-25 83.00 Completed
16 16th Floor 15-May-25 9-Jun-25 25.00 Not Yet Started
17 17th Floor 10-Jun-25 5-Jul-25 25.00 Not Yet Started
18 18th Floor 6-Jul-25 10-Aug-25 35.00 Not Yet Started

Railing
1 1st Floor Completed
2 2nd Floor Completed
3 3rd Floor Completed
4 4th Floor Completed
5 5th Floor Completed
6 6th Floor Completed
7 7th Floor 25-Apr-25 15-Jun-25 in Progress
8 8th Floor 15-Jun-25 in Progress
9 9th Floor 15-Jun-25 in Progress
10 10th Floor 15-Jun-25 in Progress
11 11th Floor 15-Jun-25 in Progress
12 12th Floor 15-Jun-25 in Progress
13 13th Floor 15-Jun-25 in Progress
14 14th Floor 16-Jun-25 26-Jul-25 Not Yet Started
15 15th Floor 26-Jul-25 Not Yet Started
16 16th Floor 26-Jul-25 Not Yet Started
17 17th Floor 26-Jul-25 Not Yet Started
18 18th Floor 26-Jul-25 Not Yet Started

Waterproofing
1 1st Floor Completed
2 2nd Floor Completed
3 3rd Floor Completed
4 4th Floor Completed
5 5th Floor Completed
6 6th Floor Completed
7 7th Floor 15-Apr-25 11-May-25 In progress
8 8th Floor 12-May-25 22-May-25 10.00 Not Yet Started
9 9th Floor 23-May-25 2-Jun-25 10.00 Not Yet Started
10 10th Floor 3-Jun-25 13-Jun-25 10.00 Not Yet Started
11 11th Floor 14-Jun-25 24-Jun-25 10.00 Not Yet Started
12 12th Floor 25-Jun-25 5-Jul-25 10.00 Not Yet Started
13 13th Floor 6-Jul-25 16-Jul-25 10.00 Not Yet Started
14 14th Floor 17-Jul-25 27-Jul-25 10.00 Not Yet Started
15 15th Floor 28-Jul-25 7-Aug-25 10.00 Not Yet Started
16 16th Floor 8-Aug-25 18-Aug-25 10.00 Not Yet Started
17 17th Floor 19-Aug-25 29-Aug-25 10.00 Not Yet Started
18 18th Floor 30-Aug-25 9-Sep-25 10.00 Not Yet Started