Alignment Option Study
Alignment Option Study
4-lane of the existing 2 lane road from Parsarma to Araria NH-327E in the State of Bihar
8.1 GENERAL
Consultant has carried out the detailed study of existing road alignment of the project
corridor, for which consultant’s team visited the project site to identify, the various possible
alignment routes and the finding of the same are presented in this chapter.
Accordingly, it was observed that the existing alignment of Project road have deficient and
sub-standard geometry at many locations. Substantial amount of built up areas with dense
habitation were also observed as the alignment pass through major towns. Ribbon
development along the project road are also observed at many locations.
The existing alignment has been appreciated and studied based on available data,
reconnaissance survey, road and inventory data etc. All these deficiencies are required to
be improved to comply with IRC standards and accordingly improvement options are
discussed herewith in subsequent clauses.
The existing road alignment passes through two districts of Bihar namely Supaul and
Araria. The existing length of the project highway based on present development of two
lane/ two lane paved shoulder is about 108 km. The district boundaries of both districts
are: From km 204.00 to km 135.300 at JBC Canal i.e. length 68.7 km in Supaul District
and km 135.300 to km 94 i.e. length 41 km approx. in Araria district. The existing road has
2-Lane/ 2-Lane with paved shoulder in the project stretch.
The road stretch from Araria to Galgalia is also under up-gradation to 4-lane with divided
carriageway.
Right of Way
As per the details obtained from reconnaissance, the Right of Way varies from 16m to
24m.
The project highway traverses rural section as well as urban built-up areas and passes
through important towns of Supaul, Pipra, Tribeniganj, Raniganj and runs through the
districts of Supaul and Araria.
Railway crossings
There are 2 no. of existing railway crossing present on the project road. ROB construction
for both crossings i.e. in Supaul town and Araria town are under progress.
A new railway line from Supaul to Araria is under construction by Central railways. This
new line is supposed to cross the project road at two locations. These lines cross project
road at Km 151.950 and 176.000.
The Project stretch involves protected notified forest along the project within existing ROW
after black top surface for which forest diversion and tree cutting permission shall be
required. The project stretch does not involve any requirement of environment clearance.
No wild life sanctuary affected along the project road and within Eco sensitive zone.
Utilities
Utilities like telephone cables, O.F.C. lines, water pipelines and electric lines run along and
across the project highway which are required to be relocated.
The existing project road having various religious structure along the road and for
widening / upgradation for two lane to four lane, most of these religious structures will
affect. After detail inventory of project stretch, following structure affected in widening of
project road in spite of bypass provision in built up areas.
Side
S. Ex. Distance Religious
LH RHS Name of Village
No. Chainage C/L Mtr Structure
S
District Araria
1 97+500 LHS 15.00 Temple Araria markit
2 101+100 RHS 5.50 Temple Araria markit
3 101+250 RHS 7.50 Mosque Rajokhar
4 101+750 LHS 7.00 Mosque Rajokhar
5 102+050 LHS 12.00 Kabristan Rajokhar
6 102+950 LHS 11.00 Mosque Rajokhar
7 104+100 RHS 6.00 Mosque Rupoli
8 105+900 LHS 5.00 Temple Chatiyona
9 106+300 RHS 10.55 Temple Chatiyona
10 106+750 LHS 10.00 Ashram Chatiyona
11 107+100 LHS 5.00 Temple Chatiyona
12 107+950 LHS 5.00 Temple Naranpur
13 107+955 RHS 5.00 Temple Naranpur
14 109+600 RHS 8.50 Temple Kharhar Azad chock
15 109+620 LHS 10.00 Temple Kharhar Azad chock
16 110+500 LHS 4.00 Temple Gidwaas
17 110+650 LHS 15.00 Mosque Gidwaas
18 110+900 LHS 13.00 Temple Gidwaas
19 112+800 LHS 5.00 Temple Hansaa
Side
S. Ex. Distance Religious
LH RHS Name of Village
No. Chainage C/L Mtr Structure
S
20 113+500 RHS 8.50 Temple Hansaa
21 113+700 LHS 8.70 Temple Hansaa
22 114+600 LHS 7.70 Temple Kamalpur
23 124+400 LHS 5.00 Temple Marhua
24 125+500 RHS 8.10 Temple Bhanulalpatti
25 130+350 LHS 5.20 temple Jamuaan
26 132+400 LHS 6.70 Temple Khojdi
27 135+300 RHS 11.70 Temple Khojdi
District Supaul
28 135+600 LHS 11.00 Temple JBC Canal
29 136+850 RHS 15.50 Mosque Mughalghat
30 138+100 RHS 22.00 Temple Pandey Patti
31 138+250 RHS 11.50 Temple Pandey Patti
32 144+350 LHS 7.50 Temple Bhageli sunder chock
33 146+550 LHS 15.50 Temple Rajeshwari
34 148+400 RHS 4.50 Temple Murliganj road Jadia
35 148+500 RHS 16.70 Temple Jadia
36 149+600 LHS 4.00 Temple Jadia
37 150+300 LHS 25.00 Temple Jadia
38 152+700 RHS 6.50 Temple Kamkulha
39 154+550 LHS 8.00 Temple Laxminea
40 156+330 LHS 7.70 Temple Laxminea Chock
Maa Champa
41 160+150 LHS 11.70 Daparkha
temple
42 162+200 RHS 7.50 Temple Tirveniganj
43 165+150 LHS 15.70 Temple Tirveniganj
44 165+220 LHS 13.50 Temple Tirveniganj
45 168+800 LHS 10.35 Temple Bhuraa
46 168+820 RHS 15.25 Temple Bhuraa
47 169+200 LHS 8.90 Temple Gajhar rahtaa
48 170+235 LHS 4.70 Temple Gajhar rahtaa
49 170+700 LHS 7.70 Temple Gambhirpur
50 170+740 LHS 8.20 Temple Gambhirpur
51 170+850 LHS 19.70 Temple Gambhirpur
52 171+500 RHS 9.00 Temple Gambhirpur
53 174+500 RHS 23.00 Temple Parmana river
Side
S. Ex. Distance Religious
LH RHS Name of Village
No. Chainage C/L Mtr Structure
S
54 175+200 LHS 15.00 Temple Dinaptti
55 175+900 RHS 7.00 Temple Dinaptti
56 177+300 RHS 8.10 Hanuman Temple Leetmadhi
57 178+220 RHS 20.70 Shiv ji Temple Thumha
58 179+000 LHS 11.50 Hanuman Temple Thumha
59 180+800 LHS 7.20 Hanuman Temple Katheagaon
60 181+020 LHS 6.90 Laxmi Temple Katheagaon
61 181+550 RHS 13.60 Shani dev temple Katia Chock
62 182+380 RHS 6.75 Hanuman Temple Katia
63 182+400 RHS 11.70 Temple katia
64 184+500 LHS 5.00 Laxmi Temple Nirmali
65 184+500 RHS 4.85 Hanuman Temple Nirmali
66 184+850 LHS 8.10 Hanuman Temple Nirmali
67 185+400 RHS 8.00 Temple Nirmali river
68 185+500 LHS 15.10 Temple Nirmali river
69 185+700 RHS 13.20 Mosque Nirmali
70 187+150 LHS 6.60 Shiv ji Temple Pathra
71 187+165 LHS 7.30 Hanuman Temple Pathra Choti Chok
72 187+550 RHS 6.90 Temple Pathra
73 187+800 LHS 9.40 Kabristan Pathra
74 188+750 RHS 8.00 Temple Pathra
75 189+300 RHS 4.50 Temple Badi Chock
76 189+600 RHS 8.00 Temple Goravgadh
77 190+750 LHS 15.50 Sai temple Goravgadh
78 191+450 LHS 8.00 Temple Goravgadh
79 197+800 RHS 13.00 Samadhi Supaul Belahi
80 198+700 LHS 3.90 Temple Karanpur Chok
81 199+350 LHS 5.10 Temple Brahman tola
82 200+450 RHS 7.20 Kali maa Temple Malhani
83 200+700 LHS 7.60 Temple Thakurwadi
Eid gaha &
84 201+000 RHS 14.50 Malhani
Kabristan
85 201+600 RHS 15.65 Temple Malhani
86 202+350 LHS 13.2 Temple Thalha Chok
There are 7 no. Major Bridges & about 35 no. minor bridges in addition to 20 no. Box
culvert, 38 no. Slab culvert and 67 no. Pipe culvert along the project road.
The existing road in most of the project section is of 2 lanes without paved shoulder
configuration and carries heavily loaded commercial traffic. To cater that heavy traffic and
future requirements, it is proposed that the project highway to be developed as 4 lane
carriageway.
The Alignment Options have been studied for the proposed road corridor from Parsarma
to Araria section of NH-327E. Details of these options are as follows:
Greenfield Option.
Improvements in existing road including geometric and structure improvement have been
explored for upgradation to 4 lane configuration. Bypass options have been explored for
major built up areas i.e Parsarma, Supaul, Thumha, Pipra, Tribeniganj, Jadia, Bhargama,
Raniganj, Araria having poor geometrics and constrained RoW. Such locations/towns are
identified and are listed below. Alignment plan showing these improvements are shown in
Figure 8.1 below.
The Existing Road is a 2-lane highway without paved shoulder and passes through Parsarma Town from km 205.900 to km 202.500. The
stretch passing through Parsarma town has poor geometry and dense habitation. NH-527A joins the project road in the middle of the town and
is being upgraded through Bharatmala Pariyojana. Existing road has constrained ROW and hence four lane section cannot be developed
without substantial demolition of structure. Alternative options of bypasses for Parsarma town has been explored and discussed below.
Based on the detail techno-economical comparison above alternatives, Option-I (LHS) seems to be the best suitable option. Widening on
existing road results in high demolition drive due to dense habitation and hence is not feasible. Option-I (LHS) requires acquisition of land
which is generally vacant with isolated buildings. This option also connects with NH-527A and helps avoid traffic to enter the town when not
required. Hence habitat affected will be minimum and highway traffic movement will be better managed.
The Existing Road is a two lane highway and passes through Supaul Town from km 199.150 to km 188.750. The section is completely
built - up and high density of local traffic is observed while reconnaissance survey. The stretch has poor geometry with many substandard
curves. An ROB is under construction on the project road within town section. Alternative bypass options for Supaul town is being explored
towards LHS & RHS. An option of elevated structure along existing road is also explored. Details of these options with comparison is shown
below: -
The Existing Road is a two lane highway and passes through Thumha Town from km 179.800 to km 177.500. The stretch passes through
habitation of Thumha town where ROW is constrained. Additional LA in this section induces demolition of buildings within busy market place.
Bypass options have been explored towards LHS and RHS and one existing road improvement. Comparison of these options is shown below: -
Based on the detail techno-economical comparison above alternatives, Option-I (RHS) will be best suitable option to avoid R&R issues.
This option requires acquisition of land which is generally vacant with isolated buildings. Hence habitat affected will be minimum and reducing
R & R cost and efforts.
The Existing Road is a two lane highway and passes through Pipra Town from km 174.850 to km 169.800. A new railway line is under
construction on the RHS side of the existing alignment. The stretch passing through Pipra town has generally poor geometry and dense
habitation so four lane section cannot be developed without substantial demolition of structure. Alternative options for Pipra town has been
explored towards LHS and RHS and one existing road improvement. Details of these options with comparison is shown below: -
S.No
Particulars Existing Alignment Option-I (LHS) Option-II (RHS)
.
1 Total Length (in Km) 6.2 6.2 5.0 km Bypass & 0.9km Existing Carriageway
2 Terrain Plain Plain Plain
3 Existing ROW(m) 16-24 0 16-24m ROW on Existing Carriageway
60m at Service road section, 60m at Service road section, 45m at other
4 Proposed ROW(m) 45
45m at other sections sections
S.No
Particulars Existing Alignment Option-I (LHS) Option-II (RHS)
.
5 Geometry of Road Sub Standard Standard Standard
6 Major Bridge (Nos.) 2 Nos. 2 Nos. 1 Nos.
7 Minor Bridge (Nos.) 1 Nos. 1 Nos. 3 Nos.
8 Railway Crossing/ROB Nil Nil Nil
NH-131, NH-131, NH-131,
9 Cross Road
5 Nos. Village Road 6 Nos. Village Road 4 Nos. Village Road
10 Grade Separator 2 Nos. VUP/LVUP 3 Nos. VUP/LVUP 3 Nos. VUP/LVUP
11 Design Speed 40-80kmph 100kmph 100kmph
12 Shifting of Utility Moderate Minimal Minimal
13 Land Use Dense Built-Up Agriculture Agriculture
14 Habitation Affected High Nil Low
15 Land Acquisition Required 20Ha 36Ha 29.25Ha
16 LA Cost (in Cr.) 13.84 24.91 20.24
17 Civil Cost (in Cr.) 117.63 150.68 145.92
Based on the detail techno-economical comparison above alternatives, Option-I (LHS) will be best suitable option to avoid substantial
R&R issues and to avoid under construction railway track. This option requires acquisition of land which is generally vacant with isolated
buildings. Hence habitat affected will be minimum and reducing R & R cost and efforts.
The Existing Road is a two lane highway and passes through Tribeniganj Town from km 164.800 to km 159.000. A railway line is under
construction on the right side of the town passing through semi built up area. The road stretch passing through Tribeniganj town has dense
habitation so four lane section cannot be developed without substantial demolition of structure. Alternative options for Tribeniganj town has
been explored towards LHS and RHS and one existing road improvement. Details of these options with comparison is shown below-
S.
Particulars Existing Alignment Option-I (LHS) Option-II (RHS)
No.
1 Total Length (in Km) 5.80 6.20 7.4 Bypass & 0.8km Existing Carriageway
2 Terrain Plain Plain Plain
3 Existing ROW(m) 16-24 0 16-24m ROW on Existing Carriageway
60m at Service road section, 60m at Service road section, 45m at other
4 Proposed ROW(m) 45
45m at other sections sections
5 Geometry of Road Sub Standard Standard Standard
6 Major Bridge (Nos.) 2 Nos. 2 Nos. 2 Nos.
7 Minor Bridge (Nos.) 4 Nos. 5 Nos. 4 Nos.
8 Railway Crossing/ROB Nil Nil Nil
9 Cross Road 4 Nos. Village Road 5 Nos. Village Road 4 Nos. Village Road
10 Grade Separator 1 Nos. VUP 2 Nos. VUP/LVUP 2 Nos. VUP/LVUP
11 Design Speed 80 kmph 100kmph 100kmph
12 Shifting of Utility Moderate Minimal Minimal
13 Land Use Dense Built-Up Agriculture Agriculture
14 Habitation Affected High Low Nil
15 Land Acquisition Required 16.75 Ha. 32.40 Ha. 41.40 Ha.
16 LA Cost (in Cr.) 8.28 16.01 20.46
Based on the detail techno-economical comparison above alternatives, Option-I (LHS) will be best suitable compared to other options. Habitat
affected will be minimum in this option and it will reduce R & R cost and efforts. This option also avoids crossing of new railway line and
requirement of railway crossing structures.
The Existing Road is a two lane highway and passes through Jadia Town from km 151.700 to km 147.250. The stretch passing through Jadia
town has poor geometry along with substantial ribbon development is observed along the existing road section. Hence the section direly
needs geometric improvements to improve safety and comfort for the road users. The proposed options include left bypass option and one
existing road improvement. Details of these options with comparison is shown below-
S.
Particulars Existing Alignment Option-I (LHS)
No.
1 Total Length (in Km) 4.40 4.50
2 Terrain Plain Plain
3 Existing ROW(m) 20 0
4 Proposed ROW(m) 45 60m at Service road section, 45m at other sections
5 Geometry of Road Sub Standard Standard
6 Major Bridge (Nos.) Nil Nil
7 Minor Bridge (Nos.) 2 Nos. (Total Length 40m) 2 Nos. (Total Length 40m)
8 Railway Crossing/ROB Nil Nil
Based on the detail techno-economical comparison above alternatives, Option-I (LHS) will be best suitable option. This option requires
acquisition of land which is generally vacant with isolated buildings. Hence habitat affected will be minimum and reducing R & R cost and
efforts.
The Existing Road is a two lane highway and passes through Bhargama Town from km 133.350 to km 129.050. The stretch passing through
Bhargama town has very poor geometry along with hair pin bend (being plain terrain) and average habitation. Hence the section direly needs
geometric improvements to improve safety and comfort for the road users. Also substantial ribbon development is observed along the existing
road section. The proposed options include two bypass options and one existing road improvement. Details of these options with comparison
is shown below-
Based on the detail techno-economical comparison above alternatives, Option-I (LHS) will be best suitable option as it eliminates all
substandard curves and improve geometric deficiencies in road alignment. This option requires acquisition of land which is generally
vacant with isolated buildings. Hence habitat affected will be minimum and reducing R & R cost and efforts.
The Existing Road is a two lane highway and passes through Raniganj Town from Km 125.850 to Km 119.250. The stretch passing through
Raniganj town has very poor geometry and dense habitation. Hence section cannot be developed within the existing road section. The
proposed options include two bypasses and one existing road improvement. Details of these options with comparison is shown below-
Based on the detail techno-economical comparison above alternatives, Option-I (LHS) will be best suitable option to avoid substantial
R&R issues and improve the geometry according to codal provisions. This option requires acquisition of land which is generally vacant
with isolated buildings. Hence habitat affected will be minimum and reducing R & R cost and efforts.
The Project Road of NH-327E road presently ends at Junction with NH-27 at Km. 257.000 of NH-27 within the town of Araria. The stretch of
NH-327 E continues towards Galgalia from other junction with NH-27 at Km 254.650 of NH-27. The bypass options have been proposed for
Existing Road section from Km 101.500 to Km 94.000 and comparison with existing road is shown below-
Based on the detail techno-economical comparison above alternatives, Option-I (RHS) seems to be best suitable option. This option
requires acquisition of land which is generally vacant with isolated buildings. Also habitat affected will be minimum and reducing R & R cost
and efforts for 4-lane highway construction.
There are numerous locations where existing road has substandard geometry in rural
areas as well. These curves need to be improved for efficient development and safety of
road user. There are few locations where minor realignments are required to avoid R & R
of buildings that exist as a result of ribbon development. Few such improvements are
suggested below.
List of deficient curves where improvements have been proposed, is shown below-
S. Existing Km Deficient
Remarks
No. From To Curve Nos.
S. Existing Km Deficient
Remarks
No. From To Curve Nos.
Considering the substantial bypasses length (More than 50%) and required geometric improvements, a complete green field alignment option
has been explored. In greenfield option the alignment starts from NH-527A at Parsarma village and ends at NH-27 at Araria Village. This
option traverses through green field areas and passes through Gamaharia, Behrari, Ramnagar Mahesh, Chiraiya, Parshahat, Mohni,
Bangama villages areas. The tentative length of this alignment option is 98.500 km.
Note-Detailed LA cost is given in Annexure 8.1 for greenfield alignment option-1 and Annexure 8.2 for option-2 and Annexure 8.3 for existing
alignment.