21 Tanjung Teras SDN BHD v. Kerajaan Malaysia
21 Tanjung Teras SDN BHD v. Kerajaan Malaysia
CONTRACT: Payment for works done – Agreement – Sale of land and construction
of apartments (project) – Principle contractor and sub-contractor – Failure to
complete project within time frame – Termination of agreement with principle C
contractor – Whether sub-contractor could counterclaim for compensation for works
done – Quantum meruit – Whether conditions under s. 71 to be compensated for
works done satisfied – Whether trial judge erred in interpreting conditions –
Principle in Siow Yong Fatt v. Susur Rotan Mining – Whether applicable –
Contracts Act 1950, s. 71 D
The respondent (‘the plaintiff’) entered into a sale and purchase agreement
(‘the agreement’) with Jeram Permata (‘JP’). In consideration, JP agreed to
sell a piece of land and to construct 226 medium cost apartments on the said
land (‘the project’). A sum of RM16 million was paid to JP by the plaintiff
under the agreement, which included the price of the said land. The E
defendant was appointed by JP as its sub-contractor vide a letter of acceptance
(‘LOA’) dated 15 February 2007 to construct the super structure works under
the project. There was delay on the part of JP in completing the project and
in consequence, the plaintiff issued a letter of termination to JP on 13 July
2007. After the termination of the agreement, the defendant refused to leave F
the project site. The plaintiff gave notice to the defendant to vacate the project
site and further informed the defendant that the plaintiff would not be making
any payment to the defendant after the agreement was terminated on 13 July
2007. The defendant refused to vacate the site despite the notice. Therefore,
the plaintiff then filed an action against the defendant vide an originating G
summons (‘OS’) and sought, inter alia, for a declaration that it was the owner
of the land and was entitled to vacant possession of the land. In opposing the
plaintiff’s OS, the defendant contended, inter alia, that the termination of the
agreement between plaintiff and JP was wrongful on the ground that there
were representations made that extension of time would be granted to JP to
H
complete the project. It was further alleged by the defendant that the unlawful
termination of the agreement had resulted in loss and damage to the
defendant as it was not paid a single cent for the work done on the project.
The defendant submitted that payment for work done under the LOA was on
a back-to-back basis, ie, the defendant would be paid only if JP was paid.
Therefore, the defendant counterclaimed against the plaintiff for the amount I
of RM50 million. The High Court granted the prayers in the plaintiff’s OS.
The OS was also converted into a writ action so that the defendant’s
[2015] 9 CLJ Tanjung Teras Sdn Bhd v. Kerajaan Malaysia 1003
(2) The High Court Judge appeared to have given a very mechanical or A
narrow interpretation to the second condition. The factual scenario of
the present case is very different from the case of Seow Yong Fatt. At the
time the structure work was done by the defendant, it was in fact done
for the plaintiff as the ultimate owner of the project and the plaintiff was
the direct beneficiary of the project. The defendant had intended to be B
paid for carrying the works. The fact that the defendant would receive
payment from JP and not the plaintiff did not alter the fact that the
defendant never intended the work to be done gratuitously. Therefore,
the second condition ought to have been found in favour of the
defendant. (para 45) C
(3) The defendant was only appointed as a sub-contractor to construct the
super structure work while the construction of the entire project was the
responsibility of JP. The plaintiff had benefited from the super structure
work as the plaintiff had since revived the project and had appointed
new contractors to continue to build the apartments on the super D
structure work done by the defendant. There was no evidence to show
that the super structure work done by the defendant was defective and
or had to be demolished when the new contractor took over the project.
It would be unjust for the plaintiff to refuse to pay any compensation to
the defendant for the value of the structure work done. Based on the E
foregoing, the defendant had successfully proven, on a balance of
probabilities, its claim under s. 71 of the CA. (paras 48-53)
(4) The defendant’s claim for the sum of RM3,009,245.23 is premised on
the three interim certificates certified and issued by DW2, as part of its
progress payment claim under the terms of its LOA with the main F
contractor, JP. A sum certified for interim payment based on
contractual terms cannot form the basis of calculation of compensation
based on quantum meruit in a claim under s. 71 of the CA. However,
the court took note that in the three interim certificates, there was a sum
of RM1,241,022.56 certified as ‘actual physical work done’. The G
defendant was entitled to claim the said sum as reasonable compensation
for the super structure work done on the project site on a quantum meruit
basis. (paras 60-61)
(5) DW2 had in his testimony stated that the three interim certificates were
issued by him after the works were evaluated and verified by JP’s H
quantity surveyor (‘DW1’). Both DW1’s and DW2’s testimony was not
seriously challenged by the plaintiff during trial. Hence, it was not as if
the sum of RM1,241,022.56 for ‘actual physical work done’ was a figure
plucked from the air by the defendant as alleged by the plaintiff. It was
prepared by men skilled in their respective profession and the High I
Court could accept that they had acted professionally when quantifying
and certifying the various amounts stated in the certificate, including the
sum of RM1,241,022.56 for physical work done by the defendant.
(para 62)
[2015] 9 CLJ Tanjung Teras Sdn Bhd v. Kerajaan Malaysia 1005
A (2) Hakim Mahkamah Tinggi seolah-olah memberi satu tafsiran sempit atau
sangat mekanikal kepada syarat kedua. Fakta senario kes ini sangat
berbeza daripada kes Seow Yong Fatt. Semasa kerja-kerja struktur dibuat
oleh defendan, ia secara fakta telah dilakukan untuk plaintif sebagai
pemilik utama projek dan plaintif ialah benefisiari langsung projek.
B Defendan telah dimaksudkan untuk dibayar kerana menjalankan kerja-
kerja. Fakta bahawa defendan akan menerima bayaran daripada JP dan
bukan plaintif tidak mengubah fakta yang defendan tidak pernah berniat
agar kerja dibuat secara sukarela. Oleh itu, syarat kedua sepatutnya
diputuskan berpihak pada defendan.
C (3) Defendan hanya dilantik sebagai subkontraktor untuk membina kerja-
kerja struktur manakala pembinaan keseluruhan projek menjadi
tanggungjawab JP. Plaintif mendapat manfaat daripada kerja-kerja
struktur kerana plaintif telah menghidupkan semula projek itu dan
melantik kontraktor baru untuk terus membina pangsapuri bagi kerja-
D kerja struktur yang telah dilakukan oleh defendan. Tiada bukti yang
menunjukkan bahawa kerja-kerja struktur yang dilakukan oleh defendan
adalah cacat dan/atau terpaksa dirobohkan apabila kontraktor baru
mengambil alih projek tersebut. Tidak adil jika plaintif enggan
membayar apa-apa pampasan kepada defendan untuk nilai kerja struktur
E
yang dilakukan. Berdasarkan perkara di atas, defendan berjaya
membuktikan, atas imbangan kebarangkalian, tuntutan di bawah s. 71
AK.
(4) Tuntutan defendan untuk jumlah RM3,009,245.23 berdasarkan tiga sijil
sementara yang sah dan dikeluarkan oleh DW2, sebagai sebahagian
F daripada tuntutan bayaran di bawah syarat LOAnya dengan kontraktor
utama, JP. Satu jumlah disahkan untuk bayaran interim berdasarkan
terma kontrak tidak membentuk dasar pengiraan pampasan berdasarkan
quantum meruit dalam satu tuntutan di bawah s. 71 daripada AK. Walau
bagaimanapun, mahkamah mengambil kira bahawa dalam tiga sijil
G
sementara tersebut, terdapat satu jumlah RM1,241,022.56 yang
disahkan sebagai ‘kerja fizikal sebenar yang dibuat. Defendan berhak
menuntut jumlah tersebut sebagai pampasan berpatutan untuk kerja
struktur yang dijalankan di tapak projek atas dasar quantum meruit.
(5) Dalam testimoninya, DW2 menyatakan bahawa tiga sijil sementara
H telah dikeluarkan olehnya selepas segala-galanya dinilaikan dan
ditentusahkan oleh juruukur bahan (‘DW1’) JP. Kedua-dua keterangan
DW1 dan DW2 tidak dicabar dengan serius oleh plaintif semasa
perbicaraan. Oleh itu, jumlah RM1,241,022.56 bukanlah ‘kerja fizikal
sebenar yang dibuat’ untuk satu angka yang dipetik secara rawak oleh
I
defendan seperti yang didakwa oleh plaintif. Ia disediakan oleh orang
yang mahir dalam profesion masing-masing dan Mahkamah Tinggi
boleh menerima bahawa mereka bertindak profesional dalam
1008 Current Law Journal [2015] 9 CLJ
[Editor’s note: For the High Court judgment, please see Kerajaan Malaysia v. Tanjung I
Teras Sdn Bhd [2013] 10 CLJ 336.]
Reported by S Kahvitha
[2015] 9 CLJ Tanjung Teras Sdn Bhd v. Kerajaan Malaysia 1009
A JUDGMENT
Lim Yee Lan JCA:
Introduction
[1] This is an appeal by the appellant/defendant against the decision of the
B Kuala Lumpur High Court dated 28 February 2013 which dismissed the
appellant/defendant’s counterclaim for the sum of RM3,009,254.23 against
the respondent/plaintiff.
[2] We heard the appeal on 13 August 2014, after which we adjourned the
matter for consideration and decision. We now give our decision.
C
[3] In this judgment, the parties will be referred to as they were in the
High Court.
Background Facts
(xi) the defendant in its affidavit in reply opposed the plaintiff’s OS on the
ground that there were many disputes of facts which could be resolved
only through hearing the oral evidence of witnesses under a writ.
Amongst the disputed facts were whether the termination of the
G
agreement between plaintiff and JP was wrongful as there were
representations made by the plaintiff’s agents from JBPA and the
Ministry of Housing and Local Government to JP and the defendant
that extension of time would be granted to JP to complete the project;
whether there were representations made by the plaintiff’s agents from
JBPA and the Ministry of Housing and Local Government to the H
defendant that direct payment to the defendant would be made if the
defendant could procure JP’s architect’s certificate to certify the work
done. It was further alleged by the defendant that the unlawful
termination of the agreement had jeopardised the defendant in the sense
that payment to the defendant for work done under the LOA was on I
a back to back basis, ie, defendant would be paid only if JP is paid and
[2015] 9 CLJ Tanjung Teras Sdn Bhd v. Kerajaan Malaysia 1011
H [5] During the trial parties had agreed to the two following issues to be
tried:
(a) whether the plaintiff has an obligation under the law to pay the
defendant as a sub-contractor for the works that have been completed on
the said project;
I
(b) if the answer to the first issue is in the affirmative, what are the sums
due to the defendant?
1012 Current Law Journal [2015] 9 CLJ
[6] At the conclusion of the trial, the learned High Court Judge dismissed
the defendant’s counterclaim based on the following findings.
[7] In regard to the first issue, the learned trial judge accepted the
submission of learned counsel for the defendant that since there was no B
contractual relationship between the plaintiff and the defendant, the
defendant’s counterclaim was not a contractual claim but a claim premised
on s. 71 of the Contracts Act, which reads as follows:
Section 71 - obligation of person enjoying benefit of non-gratuitous act.
C
Where a person lawfully does anything for another, or delivers anything
to him, not intending to do so gratuitously, and such other person enjoys
the benefit thereof, the latter is bound to make compensation to the
former in respect of, or to restore, the thing so done or delivered.
[8] The Privy Council’s decision in the case of Siow Wong Fatt v. Susur
Rotan Mining Ltd & Anor [1967] 1 LNS 161; [1967] 2 MLJ 118 (“Siow D
Wong Fatt”) was referred to in which it was held that to succeed in a claim
under s. 71 of the Contracts Act, the following four conditions have to be
met:
The doing of the act or the delivery of the thing:
E
(a) must be lawful;
(b) must be done for another person;
(c) must not be intended to be done gratuitously;
(d) must be such that the other person enjoys the benefit of the act or F
the delivery.
(e) ...
[9] Based on the factual matrix of this case, the defendant had failed to
fulfil the second and fourth conditions set out in Siow Wong Fatt to
successfully establish a claim under s. 71. G
A (ii) the learned trial judge failed to appreciate that a claim under s. 71
is premised on the equitable principle of restitution to prevent unjust
enrichment to a party who had received goods or services from
another party who, at the time of delivering such goods or services,
did not intend it to be gratuitous (see: New Kok Ann Realty Sdn Bhd
B v. Development & Commercial Bank Ltd New Hebrides (In Liquidation)
[1986] 1 LNS 30; [1987] 2 MLJ 57 (SC), Aw Yong Wai Choo & Ors
v. Arief Trading Sdn Bhd & Anor [1991] 3 CLJ 2834; [1991] 2 CLJ
(Rep) 294; [1992] 1 MLJ 166 (HC) and Kumpulan Teknik Sdn Bhd v.
Murad Hashim Communication Sdn Bhd & Anor [2012] 6 CLJ 80;
C
[2012] 8 MLJ 572 (HC), Mulamchand v. State of Madhya Pradesh, AIR
1968 SC 1218, Great Eastern Shipping Co Ltd v. Union of India AIR
1971 Cal 150 and Kotah Match Factory Kotah v State of Rajasthan, AIR
1970 Raj 118).
(iii) In Aw Yong Wai Choo, the plaintiffs were purchasers of houses
D developed by the first defendant under sale and purchase agreements
entered into between the plaintiffs and the first defendant. The first
defendant was unable to complete the project and the second
defendant had carried on and completed the same. The court held
that when the second defendant decided to take over the project and
E
built the houses according to more expensive specifications, it did so
in no way which could be conceivably unlawful. When it did so it
did not intend it to be gratuitous. The plaintiffs had all gained and
enjoyed the benefit of such specifications. Thus, the second defendant
was entitled to claim the additional costs of the expensive
specifications from the plaintiffs under s. 71 of the Contracts Act
F
1950;
(iv) in Kumpulan Teknik Sdn Bhd, the court held that a claim based on
quantum meruit can be made for work done where the contract is
terminated by breach. The party had obtained a benefit. The works
G
were not intended to be done gratuitously, it would therefore be
unjust for a party who has obtained a benefit to then refuse to make
payment;
(v) in this case, the learned judge had misconstrued the second condition
in s. 71 as laid down in Siow Wong Fatt;
H (vi) in Siow Wong Fatt, the PC held that although the road was built by
the first respondent (Susur Rotan), with the approval of the appellant
(Siow Wong Fatt), it was done for Susur Rotan’s own benefit because
under the chain of contracts Susur Rotan was the body that was going
to exploit the mineral land. This decision was not based on the fact
I of who ought to have paid Susur Rotan under the chain of contracts;
1016 Current Law Journal [2015] 9 CLJ
A (xii) what is more important is that the project was constructed for the
benefit of the plaintiff as staff quarters of its employees serving under
the JBDPA. While it is true the project was not completed by JP,
but it has since been revived and the new contractor had utilized the
superstructure work done to complete the project. In other words,
B the defendant had fulfilled all the conditions in s. 71 as set out in
Siow Wong Fatt to enable it to be paid a reasonable compensation for
the super structure work done;
(xiii) up to the date of the counterclaim, the defendant had not received a
single cent for the super structure work from JP. It was not denied
C that under the sub-contract the defendant was only entitled to receive
payment from JP on a back-to-back basis, ie, the defendant would
only be paid for work done if and after JP receives the payment for
the work from the plaintiff. In this case, the plaintiff had failed to
establish at the trial that JP had already been paid for the super
D structure work by the plaintiff through JP;
(xiv) in fact, the documents produced by the plaintiff during trial giving
the breakdown of the RM16 million allegedly paid to JP under the
project clearly showed that all the payments were made beginning
from 19 June 2003 until 2 February 2005. On the other hand, the
E defendant was appointed by JP as its sub-contractor only on
15 February 2007. In other words, the RM16 million paid to JP
could not have included payment for super structure work which was
yet to be done by the defendant;
(xv) hence, the learned judge made an erroneous finding of fact when, in
F
relation to the fourth condition, she found that “since the works were
performed for JP, it is JP who has benefited and not the plaintiff. In
consideration for the works done, the sum of RM50,548,000 will be
paid to JP, out of which it is undisputed a sum of RM16,444,072.19
has been paid”;
G
(xvi) with regard to the second issue relating to quantum, the defendant’s
claim against the plaintiff was for the sum of RM3,009,254.23 certified
under three interim certificates dated 2 August 2007, 10 August 2007
and 19 September 2007. The said sum of RM3,009,254.23 was made
up of RM2,708,328.81 which represents the value of work done and
H RM300,925.42 as refund of retention sum held under the sub-
contract;
(xvii) the three interim certificates were issued by JP’s architect (DW2)
after the works were evaluated and verified by JP’s quantity surveyor
(DW1) in accordance with the procedure laid down in the LOA
I
governing the payment of work done by the defendant. DW1’s and
DW2’s oral testimony was not subject to serious cross-examination
by the plaintiff;
1018 Current Law Journal [2015] 9 CLJ
(xviii) it was submitted that the defendant had therefore proven that the A
value of the work done by the defendant on the super structure work
was RM3,009,254.23;
(xix) the plaintiffs witnesses, SP1 and SP2, during cross-examination had
also not disputed the valuation and certification made by DW1 and
B
DW2. The amounts certified in the three interim certificates were
therefore binding on the plaintiff (see: Shen Yuan Pai v. Dato Wee
Hood Teck & Ors [1974] 1 LNS 153; [1976]1 MLJ 16, Teh Ah Khoon
Enterprise Sdn Bhd v. Puncakdana Sdn Bhd [2004] 1 LNS 558; [2004]
MLJU 630 and S&M Shopping Arcade Sdn Bhd v. Fui Lian-Kwong
Hing Sdn Bhd [2003] 3 CLJ 58; [2003] MLJU 203); C
(xx) it was further contended that the learned trial judge erred in law and
in fact when she acceded to the plaintiffs submission that it was
entitled to deduct from the total sum of RM3,009,254.23 claimed
by the defendant, the sums for (i) liquidated and ascertained damages
D
(LAD) (RM872,472.51) purportedly incurred by JP as the main
contractor for delay in the completion of the project; (ii) preliminaries
(RM1,354,184.50), variation order (RM205,412.90) and materials
on site (RM267,446.25) and (iii) retention sum (RM300,925.42),
which left a meager sum of RM8,812.65 due to the defendant;
E
(xxi) the learned judge failed to consider that the plaintiff’s submission was
an attempt to introduce evidence of a set - off or counterclaim which
was never pleaded in any of its affidavits in the OS and also defied
the learned trial judge’s own ruling on this issue at the commencement
of the trial;
F
(xxii) the defendant had invested considerable time, money and effort in
carrying out the super structure work for which it had not been paid
a single cent by JP and the plaintiff. JP could not pay the defendant
because the plaintiff had wrongly terminated the agreement and
refused to pay JP for the work done by the defendant; and
G
(xxiii) the plaintiff had benefited from the super structure work for which
neither JP nor the defendant had intended to be done gratuitously.
It was thus inequitable and unjust for the plaintiff to refuse to pay the
defendant for the work done. The plaintiff is therefore liable in law
to pay the defendant the sum of RM3,009,254.23 pursuant to s. 71 H
of the Contracts Act 1950.
[14] Learned Senior Federal Counsel (SFC), on the other hand, in her
submission, contended that no error either of fact or law had been committed
by the learned High Court Judge to warrant any appellate intervention of this
court, for the following reasons. I
[2015] 9 CLJ Tanjung Teras Sdn Bhd v. Kerajaan Malaysia 1019
A [15] Firstly, the plaintiff maintained its position that there was no
contractual relationship between the plaintiff and the defendant to impose
any obligation in law on the plaintiff to pay for the work done by the
defendant.
[16] The contractual relationship under the agreement on the project was
B
between JP and the plaintiff and any claim for payment for work done, if
any, under the project was to be made by JP and not by the defendant.
[17] The defendant was appointed by JP without the approval or
knowledge of the plaintiff and way after the contractual period under the
C
agreement had expired, as admitted by DW3.
[18] The plaintiff had lawfully terminated the agreement after JP breached
its contractual obligation to the plaintiff under the agreement for failing to
complete the project within the contractual period.
[19] The plaintiff’s witnesses, SP1 and SP2 had in their testimony denied
D the defendant’s allegation that representation had been made to the defendant
that the plaintiff would make direct payment to the defendant if it could
procure the architect of JP to certify the work done by the defendant.
[20] Thus, the factual scenario in this case does not fall under the purview
of s. 71 of the Contracts Act to allow the defendant to make a claim under
E
that section. However, if this court is of the view that the defendant’s claim
falls to be governed by s. 71 of the Contracts Act 1950, the plaintiff submits
that the learned High Court Judge was right in holding that based on the PC’s
decision in Siow Wong Fatt, the defendant had failed to satisfy the second and
fourth conditions in s. 71 to successfully establish a claim under that section.
F
[21] In particular, in regard to the second condition, the learned High
Court Judge was right in holding that whether the work was done for the
benefit of the plaintiff had to be considered at the time the work was done.
It was submitted that in this case at the time the work was done it was for
the benefit of JP. This is because the defendant was the sub-contractor of JP
G
and would receive payment from JP. The work was not done for the plaintiff
but for the benefit of JP.
[22] In regard to the fourth condition, it was submitted that the learned trial
judge was again correct in holding that the plaintiff has not benefited from
H the super structure work done by the defendant as the project was not
completed and the plaintiff had to appoint new contractors to complete the
project.
[23] In regard to the second issue on quantum, since the learned High Court
Judge had decided the first issue in the negative, this issue did not therefore
I arise for consideration.
1020 Current Law Journal [2015] 9 CLJ
[24] Be that as it may, it was submitted that the learned High Court Judge A
was right to hold that the defendant failed to prove the quantum of its claim.
This is because during the trial the defendant merely produced three interim
certificates certified by JP’s architect (DW2) as proof of the amount claimed.
[25] It was observed that no documentary evidence was adduced by DW2,
B
the architect, to explain and support each item certified by him. What the
court had before it were the bare figures stated in the three certificates.
[26] The learned trial judge had in fact earlier agreed with the plaintiff’s
submission and found that the defendant had failed to particularise the works
done by the defendant and the particulars of the claim in respect of the same. C
In other words, the learned judge found that the defendant had completely
failed to discharge its legal burden to prove the quantum of its claim. The
learned trial judge ought therefore to have dismissed the defendant’s claim
on this ground alone, which unfortunately she failed to do so.
[27] It was submitted that even assuming that the amounts certified in the D
three interim certificates were binding on the plaintiff, the plaintiff fully
agrees with the learned High Court Judge that there must be deducted from
those amounts the five items stated in para. 18 of the learned judge’s judgment
and for the reasons stated in the said paragraph.
[28] In conclusion, for the above reasons, the plaintiff urged this court to E
dismiss the defendant’s appeal with costs.
Our Decision
[29] Having read the written submissions and heard oral arguments of
learned counsel for both parties, and having perused the appeal records, we F
are of the view that this appeal ought to be allowed on account of errors of
fact and law on the part of the learned High Court Judge in arriving at her
decision. We set out the reasons for our decision.
On The First Issue Of Liability
G
[30] The defendant’s counterclaim against the plaintiff is for the sum of
RM3,009,254.23 as the value of the super structure work done by the
defendant under the project. The claim is premised on s. 71 of the Contracts
Act 1950.
Juristic Basis Behind S. 71 H
[31] Section 71 is the statutory embodiment of the common law principle
of quantum meruit, which provides for a just compensation as the measure of
the work done as opposed to contractual damages (see: Siow Wong Fatt,
Craven-Ellis v. Cannons Ltd [1936] 2 KB 403, Delpuri-Harl Corp JV Sdn Bhd v.
Perbadanan Kemajuan Negeri Selangor [2014] 1 LNS 1075; Spatial Ventures Sdn I
Bhd v. Twintech Holdings Sdn Bhd [2013] 1 LNS 729; [2014] 8 MLJ 14).
[2015] 9 CLJ Tanjung Teras Sdn Bhd v. Kerajaan Malaysia 1021
A [32] Liability under s. 71 is not based on any existing contract between the
parties. Rather it is based on the equitable principle of conscionable conduct
and restitution to prevent unjust enrichment by one party at the expense of
another party (see: Ramkrishna Shankarrao v. Rangoobai and anr AIR 1959
Bom 519; (1958) 60 BOMLR 459, Abu Mohammed v. Mohammed Kunju Lebba
B (1995) DMC 316 and Pallonjee Eduljee and Sons v. the Lonavala City
Municipality AIR 1937 Bom 417; (1937) 39 BOMLR 835).
[33] In Craven-Ellis v. Cannons Ltd, it was held that:
The obligation to pay reasonable remuneration for the work done when
there is no binding contract between the parties is imposed by a rule of
C law and not by an inference of fact from the acceptance of service.
[34] In Ramkrishna Shankarrao v. Rangoobai, it was held as follows:
From a bare reading of the section it is clear that even if there is no
contract for the performance of certain work and if the Plaintiff has done
D that work, without intending to do that work gratuitously, and the
Defendant has enjoyed the benefits thereof, then the Defendant is bound
to compensate the Plaintiff in respect of such work. The equitable principle
underlying Section 70 of the Contract Act is that there should be no
undue enrichment of one party at the cost of another. It is based on the
principle of restitution which prevents unjust enrichment by one party.
E The learned Counsel for the Appellant invited my attention to some
reported decisions on this point.
In: [1968] 3 SCR 214, Mulachand v. State of MP, it was held that the
contract in that case was not a valid one. However, the relief was granted
by invoking Section 70 of the Indian Contract Act. It was pointed out that
under Section 70 of the Contract Act the juristic basis of the principle
F
under this section is not founded on any contract or tort but it is based
on quasi-contract.
In: [1970] 3 SCR 415, P Dhunji Shaw v. Poona Municipality the plaintiff was
supplying goods to the Municipality for which there was no contract but
it was held that under Section 70 of Contract Act when a person lawfully
G delivers to another and not intending to do so gratuitously is entitled to
return of the goods or the payment of the value of the goods. Similarly
in: [1978] 3 SCR 571, Md Ishaq v. Iqbal & Md Ali & Company it was also
a case of Plaintiff’s supplying some goods to the Defendants and there
was no contract. The court spelt out an implied contract by conduct of
the parties. That means there was supply of goods by the Plaintiff and its
H
acceptance by the Defendants. Even in the present case, the Plaintiff has
done some additional work and the Defendant has accepted and enjoyed
the benefits of the same.
Similarly in: [1980] 3 SCR 893 Union of India v. JK Gas Plant the Supreme
Court applied the principle underlying Section 70 of the Contract Act and
I granted the relief even though there was no valid contract. It was held
that since the Defendant has enjoyed the benefit of the work done by the
Plaintiff, he is bound to pay the full value of the goods.
1022 Current Law Journal [2015] 9 CLJ
[35] In Abu Mohammed v. Mohammed Kunju Lebba the court held as follows: A
A [37] Section 70 of the Indian Contract Act referred to in the three Indian
cases is in pari materia with s. 71 of our Contracts Act.
[38] In the light of the decided authorities cited above on the jurisdic basis
behind s. 71 of our Contracts Act, it is thus clear that the learned SFC’s
submission that there is no obligation on the part of the plaintiff to pay the
B
defendant for the super structure work done because there was no privity of
contract between the parties does not hold any water.
Conditions To Be Fulfilled In A Claim Under s. 71
[39] As rightly pointed out by the learned High Court Judge, in a claim
C under s. 71, the defendant is required to fulfil four conditions as set out in
the Privy Council’s decision in Siow Wong Fatt as set out above.
[40] The learned High Court Judge, having evaluated the factual matrix
before her, came to the conclusion that the second and fourth conditions had
not been met by the defendant to entitle it to make a claim under s. 71. We
D had earlier set out in detail the reasons for her findings on these two
conditions.
[41] To understand the decision of the Privy Council in Siow Wong Fatt,
it is pertinent to appreciate the facts in that case.
E [42] The brief facts in Siow Wong Fatt as appeared in the headnotes read
as follows:
The appellant (Siow) made discoveries of a few hundred acres of land
which gave promise of bearing iron ore. In November 1959 he obtained
a prospectors licence and a mining lease was granted to him in September
F 1961. He then formed a company called the Kota Mining Co Ltd
(hereinafter called “Kota”) and transferred all the benefits and burdens
vested in him to the company. By an agreement dated September 19, 1960
Kota transferred its right under the earlier agreements to the first
respondent (Susur Rotan) in consideration of $40,000 and a further
$40,000 was to be paid at a later stage (which was never paid) with a
G tribute of $2 for every ton raised. Thus by a train of sub-contracts Susur
Rotan became entitled as a matter of substance to the benefit of the
prospectors licence and a right to a mining sub-lease of the mineral land.
Susur Rotan then as a commercial owners of the mining rights
constructed a road eight or nine miles long leading to the mineral land.
But despite that Susur Rotan never started to mine the land as it appeared
H that Kota did not carry out their part of the contract. Susur Rotan then
sued Kota for specific performance of the agreement dated September 19,
1960 and they joined Siow as a defendant against whom they made a
claim for specific performance of an alleged oral agreement. When the
case came up before Azmi J, as he then was, counsel for Susur Rotan
announced that the action between his client and Kota had been settled
I so that the action proceeded between Susur Rotan and Siow, and Azmi
1024 Current Law Journal [2015] 9 CLJ
J held that there was no oral agreement as alleged and dismissed the A
action. Susur Rotan then appealed to the Federal Court who found
against Susur Rotan upon the alleged oral agreement but in its favour
under section 71 of the then Contracts (Malay States) Ordinance and
directed an inquiry as to the sum to which Susur Rotan was thereby
entitled ([1965] 2 MLJ 45). On appeal to the Privy Council the sole
question before their Lordships was whether the Federal Court were B
right in holding that Susur Rotan had a valid claim against Siow under
section 71 of the said Ordinance in respect of their expenditure upon the
road.
[43] The PC had answered the sole question in the negative. Having set out
the four conditions which must be fulfilled in order to establish a claim under C
s. 71, the PC went on to hold that based on the facts, Susur Rotan had failed
to fulfil the second condition of the section. This is what the PC said in regard
to this condition:
It is the second point which in their lordships’ judgment is decisive of this
case. As a matter of phraseology the section seems clear upon it. To bring D
the section into play the person when doing the act or delivering the thing
must do the act “for another person” or deliver something “to him”. So
that his then present intention must be to do the act or to deliver the
thing for or to another.
[44] Relying on the words that the work must be done “for another person” E
or to “deliver something to him” and that intention must be gathered at the
time the work was done or delivered, the learned High Court Judge went on
to hold that since “DW3 had stated that the works were performed by the
defendant for JP and in consideration thereof, the defendant will be paid by
JP, hence the works were not done for the plaintiff but for JP”, the second F
condition was not satisfied.
[45] We are unable to agree with the learned High Court Judge’s reasoning
on the second condition. She would appear to have given a very mechanical
or narrow interpretation to the second condition. She had overlooked the
observation made by the PC, in regard to the second condition, that at the G
time of the construction of the road, Susur Rotan was not doing it for the
benefit of Siow but for its own benefit under the chain of contracts because
it was the body that was going to exploit the mineral land. It was also clear
from the facts that at the time of the construction, Susur Rotan was not
looking to Siow or any one else for reimbursement of the costs involved. H
[46] Coming back to the case before us, the factual scenario is very
different from Siow Wong Fatt. The facts here were that (1) the project was
built for and on behalf of the plaintiff to be used as the staff quarters of
JBDPAN; (2) the project was undertaken by JP for the plaintiff under the
agreement for which JP had expected to be paid under the agreement; (3) the I
super structure work was part of the works under the project; (4) JP had
appointed the defendant as its sub-contractor to construct the super structure
work; (5) the defendant had certainly expected to be paid for the super
structure work by JP on a back-to-back basis.
[2015] 9 CLJ Tanjung Teras Sdn Bhd v. Kerajaan Malaysia 1025
[55] She had agreed with the plaintiff’s submission that the defendant had A
merely relied on the three interim certificates issued by DW2 and had failed
to particularise the works done by the defendant and the particulars of claim
in respect of the same.
[56] The learned judge went on to hold that even if the defendant had
B
proven its claim for the sum of RM3,009,254.23, the plaintiff was entitled
to set-off the items mentioned in (i) to (v) totaling RM3,000,441.58 from
RM3,009,254.23, leaving a balance of RM8,812.65 due to the defendant.
[57] The question is whether the learned High Court Judge had applied the
correct principle in assessing a claim under s. 71 of the Contracts Act. As C
we had stated earlier, s. 71 of our Contracts Act is the statutory embodiment
of the common law principle of quantum meruit, which provides for just
compensation as the measure of the work done as opposed to contractual
damages (see: Siow Wong Fatt, Craven-Ellis v. Cannons Ltd (supra), Delpuri-Harl
Corp JV Sdn Bhd v. Perbadanan Kemajuan Negeri Selangor (supra); Spatial
D
Ventures Sdn Bhd v. Twintech Holdings Sdn Bhd (supra)).
[58] In Siow Wong Fatt this was stated so by the PC at p. 121 para. D-E
of its judgment as follows:
If the other conditions of the section are satisfied then compensation
must be paid for that act if the person sued has enjoyed that benefit. E
That compensation must prima facie be measured by the worth of the act
done. Whether or not it ought to be modified by an assessment of the
benefit enjoyed is not a matter which their lordships propose to discuss
in this judgment.
The words “compensation must be measured by the worth of the work done” F
implies a quantum meruit formula.
[59] In Spatial Ventures Sdn Bhd, the plaintiff’s claim to be paid professional
fees based on the scale costs in the letters of appointment was rejected by
Nallini Pathmanathan J (now JCA), on the ground that reference to the scale
G
in the contract or on the contract price of the project is not a tenable basis
on which to assess or award damages on a quantum meruit basis. The learned
High Court Judge gave the following rationale for her findings as appeared
in paragraphs of her judgment:
The Law on Quantum Meruit
H
[24] The position in law is that an assessment for restitution on the basis
of quantum meruit is in reality a measure of the costs of the work done,
a matter which does not depend upon the contract and therefore will not
be trammeled or limited by the contract rate. This gives the plaintiff, not
contractual damages, but restitution for the work done.
I
[25] It follows from the foregoing that the Plaintiff cannot seek to recover
damages on quantum meruit basis by reference to the scale in the contract
or on the contract price. Therefore the Plaintiff’s claim premised on the
[2015] 9 CLJ Tanjung Teras Sdn Bhd v. Kerajaan Malaysia 1027
[63] In the circumstances of this case, this court takes the view that on a A
balance of probabilities and in the interest of justice, the sum RM1,241,022.56
certified in the three interim certificates under the component of “actual
physical work done” should be accepted as the value of work done by the
defendant on a quantum meruit basis.
B
[64] In allowing the defendant’s appeal on quantum, we have also accepted
the defendant’s contention that although a sum of RM16 million had
purportedly been paid by the plaintiff to JP under the agreement, it did not
include the super structure work carried out by the defendant on the project
site. Indeed, the documentary evidence adduced by the plaintiff itself showed
that the RM16 million was paid to JP between the period 19 June 2003 to C
2 February 2005 whilst the defendant was appointed by JP as its sub-
contractor only on 15 February 2007. In other words, the RM16 million
paid to JP could not have included payment for super structure work which
was yet to be done by the defendant at the relevant time.
D
[65] In conclusion, based on the foregoing findings and conclusion, we
hereby allow this appeal with costs and set aside the decision of the High
Court Judge. The defendant is awarded the sum of RM1,241,022.56 as
reasonable compensation for the super structure work carried out on the
project site. The sum awarded to carry interest at the rate of 5% from the date
of this judgment until the date of full realisation. E