Design of Chenab Bridge
Design of Chenab Bridge
○ IS (Indian Standards)
● The main reference code for design and construction is BS:5400 (British Standard).
🔷 3. Key Design Parameters
● Design speed for trains on the bridge: 100 km/h
● Fatigue analysis (checking how the bridge resists repeated stress over time) is done
per BS:5400 Part 10.
○ Ensures safety under extreme conditions like heavy loading and earthquakes
In an arch bridge, this downward force gets spread out to the ends of the arch — called
abutments (the strong supports at the bottom ends).
Because the bridge is not moving, the abutments push back with equal force to hold
everything up.
● The main arch crossing the Chenab River is 469 meters long.
● On both sides, there will be viaducts (bridge sections connecting to the main span).
● The arch is made from steel trusses, which are filled with concrete inside sealed steel
box sections — this improves strength and reduces vibrations.
● Other smaller parts are kept circular to make their connections simpler.
○ Strength
○ Stability
● There are expansion joints at both abutments and at a pier called S70 — this allows
movement due to temperature or load.
● At S70, the deck height changes, marking the transition between the main arch span
and the approach bridge.
● The center of the arch is the point of longitudinal fixity — meaning it's the most stable
point where forces are balanced and movement is minimal.
● The closed deck prevents water from getting inside, keeping the space below dry.
● Wind noses are added to the deck to help deflect wind safely in the arch section.
● For the first time in Indian Railways, the End Launching Method was used to build
the curved viaduct — where the bridge is pushed out from one end during construction.
🔷 15. Quality control:
● A NABL-accredited lab was set up right at the site.
● This lab checks the quality of welds (important for safety and strength) during
construction.
● The platforms (temporary supports) for assembling this arch are built on-site.
● 4 workshops and nearby paint shops were set up on both sides of the valley.
● Most steel materials arrive as flat steel sheets, which are then cut and assembled on
site.
● A cable crane was built to transport steel across the valley — moving between tall
towers on either side.
● A derrick crane (a stronger type) is also used — it can lift up to 100 tons.
✅ Fun Fact: For the first time in Indian Railways, a continuous welded plate
girder is being used in this railway bridge.
🔷 19. Foundations:
● Building in such a difficult hilly terrain requires large-scale excavation.
○ Rock bolts (metal rods) of lengths 4m, 8.5m, and 11.5m are drilled into the
ground.
○ Perforated pipes are installed to drain water, reducing water pressure inside
the slope.
○ The slope is also sprayed with concrete (called guniting) and reinforced with
steel mesh.
🔷 21. Deck and Arch Construction Process:
● Long steel segments are assembled, and the deck (where trains run) is pushed over
them.
● The derrick is used to build the arch by lifting arch segments up from deck level.
● Both the deck and the arch are built at the same time, cantilevering out up to 48
meters.
○ A new arch pier (dock) is built at the free end to support the next segment.
● The last segment of the arch is also lifted using the cable crane, and the final closure
is done using the derrick crane.
○ There was no proper road access to the site, so 5 km of new roads had to be
built just to reach the foundation area.
○ Transporting heavy construction machinery was very hard due to the poor
infrastructure and hilly terrain.
○ Engineers had to anchor the arch with many forestay and backstay cables at
specific joints (called nodal points) to reduce bending or movement.
○ If wind speed exceeds 50 km/h, all erection work must stop for safety.
○ Since work is being done at great heights, safety nets are fixed underneath to
catch any falling tools or materials and prevent injuries.
🔷 24. Conclusions:
● Designing the main arch bridge was extremely complex and had to account for:
○ Fatigue (effect of repeated loads over time)
● The design had to ensure the same level of reliability for all possible load cases (like
train weight, wind, earthquake, etc.).
● The Chenab Bridge will be the highest, longest-span railway arch bridge in the world
once completed.
🔷 26. Timeline:
● Construction was stopped in 2008 due to alignment and security concerns.