OperationsManagement Notes
OperationsManagement Notes
Immediate
Activity Predecessor
Activity
A -
B A
C, D B
E C
F D
G E, F
Solution
A
1 2
A B
1 2 3
247
4
C
B
2 3
C E
3 4 6
D F
3 5 6l
”
D F
3 5 6!
and
4
E
6
G 7
F
5
248
G is the last activity.
Putting all the pieces together, we obtain the following diagram the
project network:
C 4
Start event E End event
A B
1 2 3 G
6 7
D 5 F
C E
3 4 6
and
D F
3 5 6l
”
We took nodes 6 and 6l as one and the same. Instead, we can retain
them as different nodes. Then, in order to provide connectivity to the
network, we join nodes 6l and 6 by a dummy activity. Then we arrive at
the following diagram for the project network:
E
Start event C 4
6
G
1 2 3 dummy
A B
activity
7
D
F
5 6l
!
End event
249
Questions
Immediate
Activity Predecessor
Activity
A -
B -
C A
D B
E A
F C, D
G E
H E
I F, G
J H, I
****
250
Path In A Project
The path with the largest time is called the critical path and the
activities along this path are called the critical activities or bottleneck
activities. The activities are called critical because they cannot be delayed.
However, a non-critical activity may be delayed to a certain extent. Any
delay in a critical activity will delay the completion of the whole project.
However, a certain permissible delay in a non –critical activity will not
delay the completion of the whole project. It shall be noted that delay in a
non-critical activity beyond a limit would certainly delay the completion
the whole project. Sometimes, there may be several critical paths for a
project. A project manager shall pay special attention to critical activities.
Problem 1
Predecessor
Activity Duration (Weeks)
Activity
A - 3
B A 5
C A 7
D B 10
E C 5
F D,E 4
252
Determine the critical path, the critical activities and the project
completion time.
Solution
First let us construct the network diagram for the given project. We
mark the time estimates along the arrows representing the activities. We
obtain the following diagram:
Consider the paths, beginning with the start node and stopping
with the end node. There are two such paths for the given project. They are
as follows:
Path I
A B D F
1 2 3 5 6
3 5 10 4
Path II
A C E F
1 2 4 5 6
3 7 5 4
Compare the times for the two paths. Maximum of {22,19} = 22.
We see that path I has the maximum time of 22 weeks. Therefore, path
I is the critical path. The critical activities are A, B, D and F. The project
253
completion time is 22 weeks.
We notice that C and E are non- critical activities.
Time for path I - Time for path II = 22- 19 = 3 weeks.
Problem 2
Find out the completion time and the critical activities for the
following project:
D
5
2 20 1
G 8
A
8 E H 11 K 6
B 6 8 10
1 3
10 16
14
1 1
I L
7 5
C
J 9
F 10 1
7
4 25
Solution
Path I
A D G K
1 2 5 8 10
8 20 8 6
254
Path II
B E H K
1 3 6 8 10
10 16 11 6
Path III
B E I L
1 3 6 9 10
10 16 14 5
Path IV
C F J L
1 4 7 9 10
7 25 10 5
C F J L
1 4 7 9 10
7 25 10 5
255
Draw the network diagram and determine the critical path for the
following project:
1- 4 3
2 -5 5
3 -6 7
3 -7 10
4 -7 4
5 -8 2
6 -8 5
7 -9 6
8 -9 4
Solution
D 5
2
5 1
H
2
A
5
1 B E 6
I 8
K
3
6 7 1
3 1
4 9
1
10 J
3 C F
6
G 7
4
4
256
Solution
We assert that there are 4 paths, beginning with the start node of 1
and terminating at the end node of 9. They are as follows:
Path I
A D H K 9
1 2 5 8
5 5 2 4
Path II
B E I K 9
1 3 6 8
6 7 5 4
Path III
B F J
1 3 7 9
6 10 6
Path IV
C 4 5
1 4 7 9
3 4 6
Compare the times for the four paths. Maximum of {16, 22, 16, 13}
= 22. We see that the following path has the maximum time and so it is the
critical path:
257
D E I K
1 3 6 8 9
6 7 5 4
Questions
IMMEDIATE
time estimate
Activity Predecessor
(weeks)
Activity
A - 4
B - 7
C - 3
D A 6
E B 4
F B 7
G C 6
H E 10
I D 3
J F, G 4
K H, I 2
Draw the project network diagram. Determine the critical path and the
project completion time.
****
258
2
8−4 4
In the case of expert A, the variance = =
6 9
2
10 − 4
As regards expert B, the variance = =1
6
Problem 2
Find out the time required to complete the following project and
the critical activities:
Optimistic Most likely Pessimistic
Predecessor
Activity time estimate time estimate time estimate
Activity
(to days) (tm days) (tp days)
A - 2 4 6
B A 3 6 9
C A 8 10 12
D B 9 12 15
E C 8 9 10
F D, E 16 21 26
G D, E 19 22 25
H F 2 5 8
I G 1 3 5
Solution
262
Optimistic 4 x Most Pessimistic Time estimate
to+ 4tm
Activity time likely time time
+ tp to + 4 t m + t p
estimate (to) estimate estimate (tp) te =
6
A 2 16 6 24 4
B 3 24 9 36 6
C 8 40 12 60 10
D 9 48 15 72 12
E 8 36 10 54 9
F 16 84 26 126 21
G 19 88 25 132 22
H 2 20 8 30 5
I 1 12 5 18 3
3 F 6
B
12 21
A 6 5
1 2 5 I
4 8
10 E
22 3
9
4 7
Consider the paths, beginning with the start node and stopping
with the end node. There are four such paths for the given project. They
are as follows:
263
Path I
A B D F H
1 2 3 5 6 8
4 6 12 21 5
Path II
A B D G I
1 2 3 5 7 8
4 6 12 6 6 3
Path III
A C E F H
1 2 4 5 6 8
4 10 3 9 21 5
7
Path IV
A C E G I
1 2 4 5 7 8
4 10 9 6 6 3
Problem 3
Find out the time, variance and standard deviation of the project
with the following time estimates in weeks:
264