0% found this document useful (0 votes)
15 views2 pages

Request For Backhoe Equipment

The Rizal Waterworks Office is requesting a backhoe with operator and fuel for scheduled water system improvements in various locations from April to June 2025. The activities include clearing road access, earth excavation, and relocation of mainline pipes. The request is prepared by Engr. Kenneth P. Apgao and noted by Engr. Nelson R. Avanceña, with approval from Municipal Mayor Norman S. Ong.

Uploaded by

Kenneth
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views2 pages

Request For Backhoe Equipment

The Rizal Waterworks Office is requesting a backhoe with operator and fuel for scheduled water system improvements in various locations from April to June 2025. The activities include clearing road access, earth excavation, and relocation of mainline pipes. The request is prepared by Engr. Kenneth P. Apgao and noted by Engr. Nelson R. Avanceña, with approval from Municipal Mayor Norman S. Ong.

Uploaded by

Kenneth
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Republic of the Philippines

Province of Palawan
Municipality of Dr. Jose P. Rizal
MUNICIPAL ECONOMIC ENTERPRISE DEVELOPMENT OFFICE

RIZAL WATERWORKS OFFICE

April 24, 2025

ENGR. RODEL B. LOBATON


MUNICIPAL ENGINEER
RIZAL, PALAWAN

Sir:

Good day!
We humbly request from your good office a Backhoe Equipment with operator and
fuel for the following schedule of Rectifications and Mainline Pipe Expansions for the
Improvement on Water Systems Operation of Rizalwaterworks, with the following details:

SCHEDULE/ LOCATION ACTIVITY


DATE
April 29 & 30 Sitio Luntab, Bgy. Taburi Clearing of Road Access for
Drilling Equipment
May 13-15 Sitio Ararab, Bgy. Iraan & Rancho I Earth Excavation and Backfill for
& II Bgy. Punta Baja the Mainline Pipe Expansion
May 27-29 Purok Nagsambat, Bgy. Bunog Repair of Road Access &
Relocation of Exposed Mainline
Pipe
June 10 & 11 Sitio Calupisan, Bgy. Punta Baja Earth Excavation & Embankment
for the Rectification of Mainline
Pipe
June 17 & 18 Purok Tatabyunan, Bgy. Campong Earth Excavation and
Uay Embankment for the Relocation
of Mainline Pipe

Anticipating your support and approval, Thank you and more power!

Prepared by:

Engr. Kenneth P. Apgao


Admin. Officer I / Waterworks Supervisor

Noted by: Approved by:


Republic of the Philippines
Province of Palawan
Municipality of Dr. Jose P. Rizal
MUNICIPAL ECONOMIC ENTERPRISE DEVELOPMENT OFFICE

Engr. Nelson R. Avanceña Norman S. Ong

MGDH I (Meedo) / Waterworks Manager Municipal Mayor

You might also like