Brief Note 19.05.2025
Brief Note 19.05.2025
1. *Forest Clearance*:
The primary reason for the delay is the pending forest
clearance. Due to the lack of necessary approvals for
tree removal, the land required for the project has not
13 Reason for Delay of Work :- been made available. Consequently, no construction
or related activities can be initiated at this stage.
As of now, the total delay attributable to departmental
issues stands at 195 days. ( From 10.10.2023 to
24.04.2024 )