Brief Note 19.05.2025

The document outlines the construction details for a Sub District Hospital in Bagidora, including financial and physical progress, with a total project cost of approximately Rs. 40.93 crore. The project is currently 85% physically complete but faces delays primarily due to pending forest clearance and issues with tender allotments for HVAC and MGPS works. Additional delays are also attributed to pending deviation approvals, affecting the overall timeline and site finalization.

Uploaded by

max000007
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views2 pages

Brief Note 19.05.2025

The document outlines the construction details for a Sub District Hospital in Bagidora, including financial and physical progress, with a total project cost of approximately Rs. 40.93 crore. The project is currently 85% physically complete but faces delays primarily due to pending forest clearance and issues with tender allotments for HVAC and MGPS works. Additional delays are also attributed to pending deviation approvals, affecting the overall timeline and site finalization.

Uploaded by

max000007
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

BRIEF NOTE

S.No. Item Details


Construction of Sub District Hospital at
1 Name of work :- Bagidora Distt.- Banswara ( Including
Internal Electric Work )

2 Scheme :- RMSCL LOAN


3 A&F Sanction Amount :- Rs.- 40,93,34,672,36 /-
4 Name of Agency :- M/s Girraj Construction Company, Jaipur
5 Work order Amount with TP :- Rs.- 30,83,33,819.52 /-
6 Date of Commencement :- 10-10-2023 / 24-04-2024
7 Date of Completion 09-01-2025 / 23-09-2025
8 Likely Date of Completion :- 31-07-2025
9 Physical Progress in % :- 85%
10 Financial Progress in % :- 72.00%
11 Excess Item :-
Sr. BSR/Non
Item Amount Reason
No. BSR
Due to hilly terrain in some areas and
level differences of up to 6-10 meters
1 Earth Work 1520923.00 BSR
from the existing main road, cutting is
required for leveling.
Due to an increase in plinth area from
3,712 sqm at the time of estimation to
5,450 sqm as per the final drawings
2 Karanja/PCC 2105242.00 BSR
provided by the NHM Technical
Committee the total plinth area has
increased by 1,738 sqm.

Due to the increase in plinth area as per


the final approved drawings by the NHM
Technical Committee, and because the
structural drawings were not ready at
the time of estimate preparation. And
3 Steel Reinforcement 3850000.00 BSR
Variations in footing size have occurred
because the codal requirements for
hospital buildings are much more
stringent than for normal buildings,
necessitating these adjustments

Increased as per the final approved


drawings from the NHM Technical
4 Aluminium Work 2357972.00 BSR Committee, considering the doors and
windows specified in the elevation and
final working drawings.
Enhanced in accordance with the NHM
Technical Committee's final approved
5 False Ceiling Work 3323378.00 BSR drawing and AC ducting work in the
building; false ceiling requirements for
the Mostly building area
Increased as per Final Approved
Outer Road & Drawing of NHM Technical Committee,
6 1435999.00 BSR
Development Work Road Mention In the Plan Variation in
Road Area
Increased as per Final Approved
7 Electrical Work 2134671.00 BSR Drawing of Assistant Engineer
(Electrical) /NHM Technical Committee
12 Extra Item
Sr. BSR/Non
Item Amount Reason
No. BSR
1 PVC Storage Tank 1600970.00 BSR Due to Item Not taken In Estimate
Require for Covering the Ramp, Lift,
Roof Covering With Fibre
2 476975.00 BSR Shaft Area for Future Extension
Sheet
provision instead of RCC Structure

1. *Forest Clearance*:
The primary reason for the delay is the pending forest
clearance. Due to the lack of necessary approvals for
tree removal, the land required for the project has not
13 Reason for Delay of Work :- been made available. Consequently, no construction
or related activities can be initiated at this stage.
As of now, the total delay attributable to departmental
issues stands at 195 days. ( From 10.10.2023 to
24.04.2024 )

14 Date of Approval by District Committee :-


15 Date of Approval by Pre EC Committee :-
16 GPS Photo of Work :-

1. *Pending Tender and Agency Allotment*:


The tender for HVAC (Air Conditioning Work) and
MGPS Works has not yet been published, and no
executing agency has been appointed. Due to this,
we are unable to proceed with false Ceiling, Internal
Electrical and Other Internal finishing works. These
17 Any Other Issue :- activities are Interdependent, and without their
completion, the site cannot be finalised.
2.*Pending Deviation Approval*:
The deviation proposal is still under review and has
not been approved. Without formal approval, we are
unable to proceed with the related scope of work,
which is causing additional delays.