0% found this document useful (0 votes)
16 views13 pages

Variations in Construction Contracts

Variations in construction contracts refer to changes in the original work plan that occur after the contract is signed, including additional work or design changes. Contracts must include variation clauses to prevent breaches and allow for legal adjustments without renegotiation. The handling of variations depends on the type of contract, with specific rules and tests to determine if changes qualify as variations and how they should be priced.

Uploaded by

Tejinder Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views13 pages

Variations in Construction Contracts

Variations in construction contracts refer to changes in the original work plan that occur after the contract is signed, including additional work or design changes. Contracts must include variation clauses to prevent breaches and allow for legal adjustments without renegotiation. The handling of variations depends on the type of contract, with specific rules and tests to determine if changes qualify as variations and how they should be priced.

Uploaded by

Tejinder Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

VARIATIONS IN

CONSTRUCTION
CONTRACTS
DEFINITION

“Work not contemplated at the time of


contract execution and not provided for.”

(Barter v Mayor of Melbourne, 1870)

Variations are changes to the original work


plan not included when the contract was
signed. They may include:

○ Additional work
○ Changes in design or quantity
○ Omissions or substitutions
A contract gives the contractor the right
to complete the work they were
promised. Taking away or changing that
work without agreement is a breach.”

(Abbey v PP Brickwork Ltd, 2003)

Contracts must include variation


clauses to prevent breach.

They let employers adapt the project to


clear rules to avoid arguments.

Also, They allow employers to adjust the


scope legally without renegotiating a
whole new contract.
To determine the position of the
additional work, we need to apply the
7-step test established in Watson v
Guennewig (1967):

1 .The extras were outside the scope of


the contract.

2. The extras were ordered by (or on


behalf of) the employer.

3. The employer agreed to pay more


money, either by words or conduct.

4. The extras were not provided


voluntarily by the contractor.
5. The extras were not necessary
because of the contractor’s default.

6. If the extras were ordered on behalf


of the employer, that agent was
authorised to issue that instruction.

7. Any condition precedent to payment


imposed by the contract has been
fulfilled.
Not a variation if:

○ It’s already in the contract, clearly


or implicitly.

○ It’s needed to finish the job (e.g,


Williams v Fitzmaurice, 1858).

○ It results from the contractor’s


fault.

○ The contractor upgrades materials


on their own.

○ The contractor adds work without


instructions.
The way changes are handled in
construction contracts depends
largely on the type of contract.

Lump Sum Contracts


Vs
Re-measurement, Cost-Plus, or
Target Cost Contracts.
Lump Sum Contracts:

• In a Lump Sum Contract, the contractor agrees


to complete a defined scope of work for a fixed
total price.
• Usually paid in stages, not all at once.
• Contractor gets the agreed amount, no matter
their costs.

·How Do Changes Work in Lump Sum Contracts?

• Lump sum contracts only work properly when


the scope of work is clearly defined and priced
at the start.
• However, if changes occur, those variations
must be evaluated carefully since the original
price was based on a fixed scope.
Re-measurement, Cost-Plus, or Target Cost
Contracts:

• These contracts do not lock in a final price


upfront.
• They set out a pricing method, and the final
cost depends on the actual quantities of work
completed.
• Payments are based on the actual work done.

·How Do Changes Work in These Contracts?

• In these types of contracts, the employer takes


the risk if quantities are underestimated, while
the contractor takes the risk that their unit
rates are sufficient.

• These styles of contracts handle risk and price


adjustments in very different ways. They
require different considerations when
evaluating variations.
Now, a variation has been agreed.

Yet, it doesn’t really matter why the


variation was needed.

what matters is how it's priced.

• Most contracts use the original bill of


quantities or a similar pricing structure.

• But what if the original rate was wrong or


too low?
Does it still apply?

Let’s see what the court said.


In Weldon v Commission for New Towns
(2001):

• The court made it clear that if a


contractor underprices something,
they’re usually stuck with that rate..

• Even if the rate is clearly too low, it


still counts because it’s what both
parties agreed to in the contract.

• Courts generally don’t care if the


actual cost turns out to be much
higher. The agreed rate wins.
Variations Are Normal, but they need careful handling.
To assess whether work is a variation:

• Know Your Contract: Fixed price or not, it shapes


the rules.

• Start with the contract scope: What’s expressly or


implicitly included?

• Apply the 7-Step Test for extras.

• Contractors should always double-check their


pricing before signing the contract and make sure
that their assumptions are clearly stated within
the contract documents.

• They should avoid under-pricing items tactically,


since they will likely be held to those prices later.

• Finally, contracts should clearly define when work


is considered “similar” to the original scope to
reduce future disputes.

You might also like