SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount
No Component Depth Volume Item of Works Rate
1 2 3 4 5 6 7 8 9 10 11 12 13
52. 5.05.01.02 RCC WORKS: 1:2:4 (measured on gross concrete section) cum RCC WORKS: 0.000 1.00 0.000
(f'c = 19 MPa, minimum f'cr = 26 MPa in nominal mix
1:2:4), with brick-chips (Sand of F.M. 1.2 and F.M. 2.2 in Gate Column 0.000 1.00 0.000
equal proportion) Reinforced cement concrete works with
minimum cement content relates to mix ratio 1:2:4 having Long Portion 5.525 0.800 0.250 1.105 2.00 2.210
maximum water cement ratio = 0.45 and minimum f'cr =
26 MPa, satisfying a specified compressive strength f'c= 19 Short Portion 5.525 0.500 0.250 0.691 2.00 1.382
MPa at 28 days on standard cylinders as per standard
practice of Code ACI/BNBC/ASTM, cement conforming to Mid Portion 5.525 0.600 0.150 0.497 2.00 0.994
BDS EN-197-1-CEM-I, 52.5N (52.5 MPa) / ASTM-C 150
Type – I, best quality sand [50% quantity of best local sand Top Long Portion 4.700 0.800 0.250 0.940 1.00 0.940
(F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand
of equivalent F.M. 2.2] and 20 mm down well graded picked Top Short Portion 4.700 0.500 0.250 0.588 1.00 0.588
jhama brick chips conforming to ASTM C-33 including
conducting necessary tests, breaking chips and screening, Top Mid Portion 4.700 0.600 0.150 0.423 1.00 0.423
making and placing shutter in position maintaining true to
plumb, making shutter water-tight properly, placing 6.537 10651.00 69625.59
reinforcement in position; mixing in standard mixer
machine with hopper fed by standard measuring boxes,
casting in forms, compacting by vibrator machine and
curing at least for 28 days, removing centering-shuttering
after specified time approved; including cost of water,
electricity, other charges etc. all complete, approved and
accepted by the Engineer-in-charge. (Rate is excluding
laboratory test fees, the cost of reinforcement and its
fabrication, placing, binding etc. and the cost of shuttering
& centering). (PWD 07.1)
Pedestal, column, column capital, lift wall and wall up to
ground floor (PWD 07.1.2)
53. 5.05.11.01 FORM WORK (Steel) :Centering and shuttering, including sqm FORM WORK (Steel): 0.000 1.00 0.000
strutting, propping etc. (The formwork must be rigid
enough both in and out of plane, to make the concrete Gate Footing 2.400 0.250 0.600 2.00 1.200
surface true to the designed shape and size by using
necessary MS sheets of minimum 16 BWG, angles of 1.200 582.00 698.40
minimum size 40 mm x 40 mm x 5 mm, flat bars etc.) and
removal of form for: (PWD 07.12)
Individual and combined footing (PWD 07.12.1)
54. 5.05.11.04 FORM WORK (Steel) :Centering and shuttering, including sqm FORM WORK (Steel): 0.000 1.00 0.000
strutting, propping etc. (The formwork must be rigid
enough both in and out of plane, to make the concrete Gate Column 0.000 1.00 0.000
surface true to the designed shape and size by using
necessary MS sheets of minimum 16 BWG, angles of Long Portion 1.975 2.100 4.148 2.00 8.296
minimum size 40 mm x 40 mm x 5 mm, flat bars etc.) and
removal of form for: (PWD 07.12) Short Portion 1.975 1.500 2.963 2.00 5.926
Pedestal, column, column capital, lift wall and wall up to
ground floor (PWD 07.12.4) Mid Portion 1.975 1.500 2.963 2.00 5.926
Top Long Portion 4.700 2.100 9.870 1.00 9.870
Top Short Portion 4.700 1.500 7.050 1.00 7.050
Top Mid Portion 4.700 1.500 7.050 1.00 7.050
44.118 522.00 23029.60
Package Code : Shibpur-2005; February 2023 Print Date/Time: 06-Feb-2025 04:35 PM Page 22