22 - DPR Preparation - UP - Sanjay Gautam

The National Knowledge Workshop focuses on advancing safely managed sanitation in urban areas in Uttar Pradesh, highlighting the Swachh Bharat Mission (Urban) 2.0 launched in October 2021 with a goal of a Garbage Free India by 2026. Key features include wastewater management, setting up sewage treatment plants, and improving sewer networks, with significant financial allocations for urban local bodies. Challenges such as lack of technical manpower, funding, and public awareness are also addressed.

Uploaded by

yellowbellshotel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views17 pages

22 - DPR Preparation - UP - Sanjay Gautam

The National Knowledge Workshop focuses on advancing safely managed sanitation in urban areas in Uttar Pradesh, highlighting the Swachh Bharat Mission (Urban) 2.0 launched in October 2021 with a goal of a Garbage Free India by 2026. Key features include wastewater management, setting up sewage treatment plants, and improving sewer networks, with significant financial allocations for urban local bodies. Challenges such as lack of technical manpower, funding, and public awareness are also addressed.

Uploaded by

yellowbellshotel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 17

National Knowledge Workshop

on
Advancing Safely Managed Sanitation in Urban Areas

Planning and DPR Preparation in UWM


in Uttar Pradesh
by
Sanjay Gautam, Chief Engineer
Uttar Pradesh Jal Nigam (Urban),
Uttar Pradesh
Making Cities Garbage Free

Shri Narendra Modi


Prime Minister of India

2
Swachh Bharat Mission ( Urban) 2.0 – Introduction

• Launched during 75th anniversary of independence on 1st October 2021 by Hon.


Prime Minister of India, on the eve of Swachhata Divas with the ambitious vision of
Garbage Free India by 2026.
• Target to safe reuse of used water (Wastewater) i.e. its collection, conveyance,
treatment, reuse and final disposal.
• Adopt terminology that captures the notion safe and beneficial use of treated water.
• Mission has a reform agenda to enhance city water security, financial health of ULBs
and ease of living of citizens
• Mission period is till FY 2025-26
Swachh Bharat Mission ( Urban) 2.0 – Key features

❖ Used water management for towns less than 1.0 lakh population as a component of SBM-U-2.0

❖ Focus Areas under used water management

i. Setting up of STP- For 70% present population( year 2026)

ii. I&D Structures including pumping stations and pumping/gravity mains

iii. Procuring septic tank desludging equipment –where no Pvt. Operator exist

iv. Sewer network in core sanitation zone (CSZ) , where 50% city pop. reside in 20-30% area of the

city—to be financed by State/ULB /15th FC.


Status of UWM/Sewerage Project before SBM 2.0 for Uttar Pradesh

No. of ULBs Plans


Total No. of No of Project Sanctioned Cost
approved by
ULBs (in Cr)
Ministry
Completed Ongoing
762 60 28,691.19
177 80

• STP No:- 126


• Capacity:- 4074.1 MLD
• FSTP No:- 54
• Capacity:- 1.9MLD
• Cesspool tanker/Equipment:- 78

5
Swachh Bharat Mission ( Urban) 2.0 - Overview

Central Project STP Treatment Drains


Outlay Proposed Capacity Tapped
Assistance Sanctioned
5041 Cr. 670 1820 MLD 3442
2520 Cr. 670

DPR DPR Ongoing Population To


Prepared Approved Project be Benefitted

59 4 3 ~ 260 Lacs

**
Total 7 6 2 ULBs
6 7 0 – ULB plans sanctioned by GOI under S B M 2.0
6 0 - AMRUT Towns Covered under AMRUT .0
1 6 - ULBs proposed on other programmes with STP
1 6 - ULBs where City Sanitation Action Plan not prepared due to no existence of drains, scattered population or Ro c k y Strata 6
Approval Status of UWM under SBM(U) 2.0 for State
ULBs No. of ULBs
STP
Total No. of AMRUT Covered by Plans
Capacity in No of Drains
ULBs Towns other approved
MLD
Programs by GOI

762 60 32** 670 1820 3442

Mission Allocation for UWM=Rs. 5041 Cr

Central Share approved = Rs. 2520.60

**
1 6 - ULBs proposed on other programmes with STP
7
1 6 - ULBs where City Sanitation Action Plan not prepared due to no existence of drains, scattered population or R o c k y Strata
SBM 2.0 of
Status – DPR Status
SBM 2.0, DPR

67 No of ULB having Population more than 50,000

Under preparation/Scrutiny Prepared


Approved
(No. of projects) (No. of projects)

51 16 3

603 No of ULB having Population less than 50,000

Under preparation/Scrutiny Prepared


Approved
(No. of projects) (No. of projects)

576 ( 280 + 296 )


27 1
280 : pop < 25000
23C : pop b/w 25000 - 50000
SBM 2.0 of
Status – Action
SBM 2.0, Plan
DPR for grounding of Projects

❖ ULB’s with Population less than 25000 : 280 (DPR to be prepared by ULB )

❖ ULB’s with Population greater than 25,000 : 3G0 (DPR to be prepared by UP Jal Nigam(Urban)

❑ Phase 1 : ULB with Population 50,000 to 100,000 - ( 67 Nos. )

❑ Phase 2 : ULB with Population 25,000 to 50,000 – ( 323 Nos.)


Household Coverage Summary – Sewerage

Total No of Households including S l u m s – 8 1 Lacs

Households Covered with Sewer Connections before AMRUT 2.0 : 2 2 . 9 0 Lacs

Sewer Coverage Before AMRUT 2 . 0 : 28% ( For 60 AMRUT Towns)

New House sewer connections Proposed Under AMRUT 2.0( Tranche 1,2&3) : 5 Lacs

Total Households covered with house sewer connections after AMRUT2.0 : 2 7 . 9 0 Lacs

Water Su p pl y Coverage after AMRUT 2 . 0 : 3 5 % ( For 60 AMRUT Towns)

10
100% W/S Coverage Status – Post implementation of Tranche 1, 2 & 3
Total No. ULBs – 762
100% Coverage before AMRUT2.0 -3
100% Coverage In Tranche 1 - 71
100% Coverage In Tranche 2 - 146
100% Coverage In Tranche 3 - 94
Total Saturated ULBs – 314

11
Coverage Status ( Post implementation of Tranche 1,2 and 3 )
Total no of ULBs - 762

No of ULBs saturated After AMRUT 2.0 (Tranche 1 ,2 and 3 ) – 314

• Out of 75 District Headquarter, 64 District headquarter will be saturated after Tranche 3

• Out of 17 Nagar Nigams, 6 Nagar Nigams will be saturated after Tranche 3

• All 54 ULBs under 8 Aspirational Districts will be saturated after Tranche 3

• All 72 UL Bs under the Bundel K h a n d Region along with Mirzapur, Chandauli and Sonbhadra will
be saturated after Tranche 3

12
Household Coverage Summary – Water Supply

Total No of Households including S l u m s – 1 4 0 Lacs

Households Covered with water tap Connections before AMRUT 2.0 : 5 2 . 8 7 Lacs

Water S u p p l y Coverage Before AMRUT 2 . 0 : 3 7 %

New House Connections Proposed Under AMRUT 2.0( Tranche 1,2&3) : 4 3 . 0 4 Lacs

Total Households covered with water tap Connections after AMRUT2.0 : 9 5 . 9 1 Lacs

Water Su p p l y Coverage after AMRUT 2 . 0 : 6 8 %

13
Completed Project

Aligarh Sewerage Scheme (Smart City Area Based Development)


14
Completed Project

Hapur Sewerage Scheme Part-I Phase-I district- Hapur


15
Challenges
Challenges:

• No Technical Manpower at ULB for Operation & Maintenance


• Lack of Fund with ULB for ULB Share & Operation & Maintenance of projects.
• Awareness of ULB/Public w.r.t pollution
• Availability of Suitable Land
Thank You !!