Document No: Date: 17-03-12: Method Statement For The Lifting of E & I Room

This 3 sentence summary provides the key details about lifting an E&I room from the document: The document outlines the method statement for lifting an E&I room using a crane, including preparing the work area, attaching rigging to lift the room from the trailer to the foundation, and ensuring safety measures are followed through each step of the lift under the supervision of a rigger-1. Important safety notes specify requirements like using outrigger pads for the crane, not allowing people under the hanging load, using certified rigging gear and communication devices, and referring to the attached risk assessment.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
281 views3 pages

Document No: Date: 17-03-12: Method Statement For The Lifting of E & I Room

This 3 sentence summary provides the key details about lifting an E&I room from the document: The document outlines the method statement for lifting an E&I room using a crane, including preparing the work area, attaching rigging to lift the room from the trailer to the foundation, and ensuring safety measures are followed through each step of the lift under the supervision of a rigger-1. Important safety notes specify requirements like using outrigger pads for the crane, not allowing people under the hanging load, using certified rigging gear and communication devices, and referring to the attached risk assessment.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

METHOD STATEMENT FOR THE LIFTING OF E & I ROOM Document No: Contract No: Date: Transmittal No:

17-03-12

Supplier :
Project : Subject : Introduction :

Rawabi Electric.

Maadin Aluminium Project.


Method Statement for the lifting of E & I Room. The following method covers typical procedure for lifting of E & I Room

Scope of work : Equipment

Lifting of E & I Room. Type Dimensions (Mts) L8.2 x W4.6 x H4.1 Weight (Tons)

E & I Room

Box Type

10 Approx.

Section A. i. Pre Lifting Activities :1. Ensure that necessary work permit is available prior to the commencement of work. 2. All personnel involved in the operation shall be familiar to the assigned specific task and shall consider the safety aspects at all times. A toolbox meeting shall be conducted prior to the job activity. Refer to Job Hazard Analysis RA-11-L-066002. 3. Ensure that all reference drawings and relevant documents pertaining to the task are available prior to the operation. 4. 5. Ensure that all materials and consumables confirming to the specifications are obtainable. Barricade (hard barricading) the working area to prevent the entry of unauthorized personnel and warning sign boards shall be displayed. 6. 7. Competent personnel shall be employed as in charge of the operation. The working area shall be leveled and protected by steel mats/plates to attain enough bearing capacity due to heavy lifting. 8. Ground shall be prepared to withstand the loading by utilizing steel plates above compacted surfaces wherever required.

ii.

Dependent Documents :1) Drawing No- L-11-066002 2) Risk Assessment - RA-11-L-066002

Page 1 of 3

METHOD STATEMENT FOR THE LIFTING OF E & I ROOM Document No: Contract No: Date: Transmittal No:

17-03-12

Section B.

i.

Lifting Of E &I Room From The Trailer

The crane shall be configured to Config-1 as described in Section A.iii. The crane shall be Step 1 positioned as shown in the dwg 11-066002. The radius and configurations shall follow the drawing.

Step 2

The area shall be prepared to withstand the load prior to the placement of the crane. Rigging tackles shall be attached to the crane. The outriggers of the crane shall be fully extended prior to the lifting of the load. The operator and Rigger-1

Step 3 shall check this before the lifting commences. The trailer shall be brought near to the crane and shall be stopped as instructed by the rigger-1. The rigger-1 is responsible to maintain the initial lifting radius as per the engineering study. The lifting end of the rigging gears shall be connected to the lifting trunnions of the cargo. The Rigger-1 shall Step 5 consistently check the position of the hook block and shall confirm that it is in the center of the load, above the CoG. Once the lifting gears are connected to the load securely, a final check up shall be performed by the rigger-1 Step 6 as well as the riggers to ensure that the connections are secure. The load shall be freed from the trailer when the Rigger-1 advices to do so. The Rigger-1 shall deliver the signal to lift the load and the lift shall be paused once the load is lifted to around Step 7 100mm from the trailer, in order to check the stability of the load, the rigging gears and the crane. Once the stability of the above are checked the crane shall lift the load further to clear the height of the Step 8 foundation edge or any hindrances. The crane shall swing to place the load over the foundation The load shall be completely transferred to the Step 9 foundation as per the instruction provided by the client representative present in the site.

Step 4

Page 2 of 3

METHOD STATEMENT FOR THE LIFTING OF E & I ROOM Document No: Contract No: Date: Transmittal No:

17-03-12

Once the entire load is transferred to the foundation the load freed from the rigging gears. Rigger-1 shall be Step 10 responsible for the entire lifting activity. Step 11 The crane shall be moved out from the site after retracting the boom and the outriggers.

ImportantNotes: 1. Craneoutriggerpadsshallbeutilizedasheavyloadsareappliedovertheground. 2. Atanypointoftheliftingactivityapersonissupposedtobeunderthehangingload. 3. ThecraneoperatorshallfollowonlythesignalsdeliveredbytheRigger1unlessanemergencystopsignal shownbyanyotherparties. 4. Onlyauthorizedpersonsareallowedinsidetheheavyliftingbarricadedarea. 5. ProperPPEshallbewornbyallthepersonspresentinthesite. 6. Proper tag lines [4nos] shall be used while the load is hanging. Tag lines shall not be tied around the hand/wrist. 7. Thecraneoperator,theriggerandtheRigger1shallpossessvalidSaudiAramcocertification. 8. OnlySaudiAramcoCertifiedrigginggearsshallbeutilizedforthelifting. 9. OnlyAramcopermittedcommunicationdevicesshallbeusedduringtheliftingactivity. 10. Formoresafetymeasurementspleaserefertotheattachedriskassessment. Prepared By
S .M

Checked by
R.N

Approved by
E.M
-

Revision
-

Page 3 of 3