Apqp Plan

This document outlines the timing plan for the APQP process for a new component called a "STAY FR NO PLATE" being developed for Hero Honda Motors Ltd. It lists 32 activities that must be completed, including developing process flow diagrams, identifying special characteristics, tool development plans, creating control plans, conducting design failure mode and effects analysis, and submitting prototype, pilot lot, and PPAP samples for customer approval. The document assigns responsibilities to various people and provides target dates for completing each step in the APQP process.

Uploaded by

anon-448387
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
1K views

Apqp Plan

This document outlines the timing plan for the APQP process for a new component called a "STAY FR NO PLATE" being developed for Hero Honda Motors Ltd. It lists 32 activities that must be completed, including developing process flow diagrams, identifying special characteristics, tool development plans, creating control plans, conducting design failure mode and effects analysis, and submitting prototype, pilot lot, and PPAP samples for customer approval. The document assigns responsibilities to various people and provides target dates for completing each step in the APQP process.

Uploaded by

anon-448387
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 3

Revision--- A

NEW SWAN COMPONENT (P) LTD.


Code: QF/PR/15
APQP TIMING PLAN Page:01 of 02
Component Name: STAY FR NO PLATE Customer: Hero Honda Motors Ltd.
Reference Drg. No.: 64315-KWA-9400
Sr.No Activity Responsibility Target Date Actual Date Remark
1 Drawing Study Mr Anil Pathak& Rakesh
Pandey
2 Process Flow Diagram.
Mr Rakesh Pandey
3 List of Special
Characterstics.(Customer
Specific) Mr Rakesh Pandey
4 List of Special Processes i.e
Heat Treatment/Surface
5 Coating.
List of IS/Customer
Standards.
6 List of Out Sourced
Process/B.O.P
7 List of Suppliers.

8 Prodn. Development Plan at


Supplier's end.
9 List of Tools.
Mr Anil Pathak
10 Tool Development Plan. Mr Anil Pathak& Rakesh
Pandey
11 List of Instruments & Gauge.
Mr Rakesh Pandey
12 Packing Specification.
Mr Rakesh Pandey
PROTOTYPE
13 PFMEA

14 Control Plans.

15 Sample Reports.(ISIR)

16 Target Date of Sample


Submission.
17 Feed Back For Sample &
Review Customer Reply/C/P
action.
PRELAUNCH TYPE
18 Review for Process Flow
Diagram.
19 Review PFMEA

20 List of Critical Parameters.

21 Tool Development Plan


Review.
Revision---A
NEW SWAN COMPONENT (P) LTD.
Code:QF/PR/15
APQP TIMING PLAN Page:02 of 02
Component Name: STAY FR NO PLATE Customer: Hero Honda Motors Ltd.
Reference Drg. No.: 64315-KWA-9400
Sr.No Activity Responsibility Target Date Actual Date Remark
22 Packing SpecificationReview.

23 Control Plans.

24 Prodn. Planning of Pilot Lot.

25 SPC Study.

26 MSA Study.

27 Pilot Lot Sample Report.

28 Target Date For Pilot Lot


Submission.
29 Feed Back & Review
Customer Report & C/P
30 action.
PPAP.

31 Master Sample

32 Feed Back from Costomer.