This document outlines the timing plan for the APQP process for a new component called a "STAY FR NO PLATE" being developed for Hero Honda Motors Ltd. It lists 32 activities that must be completed, including developing process flow diagrams, identifying special characteristics, tool development plans, creating control plans, conducting design failure mode and effects analysis, and submitting prototype, pilot lot, and PPAP samples for customer approval. The document assigns responsibilities to various people and provides target dates for completing each step in the APQP process.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
50%(2)50% found this document useful (2 votes)
1K views
Apqp Plan
This document outlines the timing plan for the APQP process for a new component called a "STAY FR NO PLATE" being developed for Hero Honda Motors Ltd. It lists 32 activities that must be completed, including developing process flow diagrams, identifying special characteristics, tool development plans, creating control plans, conducting design failure mode and effects analysis, and submitting prototype, pilot lot, and PPAP samples for customer approval. The document assigns responsibilities to various people and provides target dates for completing each step in the APQP process.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 3
Revision--- A
NEW SWAN COMPONENT (P) LTD.
Code: QF/PR/15 APQP TIMING PLAN Page:01 of 02 Component Name: STAY FR NO PLATE Customer: Hero Honda Motors Ltd. Reference Drg. No.: 64315-KWA-9400 Sr.No Activity Responsibility Target Date Actual Date Remark 1 Drawing Study Mr Anil Pathak& Rakesh Pandey 2 Process Flow Diagram. Mr Rakesh Pandey 3 List of Special Characterstics.(Customer Specific) Mr Rakesh Pandey 4 List of Special Processes i.e Heat Treatment/Surface 5 Coating. List of IS/Customer Standards. 6 List of Out Sourced Process/B.O.P 7 List of Suppliers.
8 Prodn. Development Plan at
Supplier's end. 9 List of Tools. Mr Anil Pathak 10 Tool Development Plan. Mr Anil Pathak& Rakesh Pandey 11 List of Instruments & Gauge. Mr Rakesh Pandey 12 Packing Specification. Mr Rakesh Pandey PROTOTYPE 13 PFMEA
14 Control Plans.
15 Sample Reports.(ISIR)
16 Target Date of Sample
Submission. 17 Feed Back For Sample & Review Customer Reply/C/P action. PRELAUNCH TYPE 18 Review for Process Flow Diagram. 19 Review PFMEA
20 List of Critical Parameters.
21 Tool Development Plan
Review. Revision---A NEW SWAN COMPONENT (P) LTD. Code:QF/PR/15 APQP TIMING PLAN Page:02 of 02 Component Name: STAY FR NO PLATE Customer: Hero Honda Motors Ltd. Reference Drg. No.: 64315-KWA-9400 Sr.No Activity Responsibility Target Date Actual Date Remark 22 Packing SpecificationReview.