The document outlines a project plan for establishing a 3/4 Star Hotel with 200 rooms, detailing activities, durations, and dependencies. The critical path includes phases from market research to hotel launch, with a total timeline that emphasizes the importance of planning, construction, and staffing. Each phase is broken down into specific activities, highlighting the necessary time and considerations for successful completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views5 pages

Project Management

The document outlines a project plan for establishing a 3/4 Star Hotel with 200 rooms, detailing activities, durations, and dependencies. The critical path includes phases from market research to hotel launch, with a total timeline that emphasizes the importance of planning, construction, and staffing. Each phase is broken down into specific activities, highlighting the necessary time and considerations for successful completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Project Planning and Management on To establish a 3/4 Star Hotel for 200 rooms.

Activity Activity Description Predecessor(s) Duration


ID (Days)

A Market Research & Feasibility - 30


Study
B Land Acquisition & Legal A 45
Clearances
C Design & Architectural Planning A 60

D Financing & Loan Approvals A 40

E Site Preparation & Groundwork B, C, D 50

F Foundation Construction E 70

G Structural Work (Floors & Walls) F 180

H Roofing & Exterior Finishing G 60

I Electrical & Plumbing Works G 75

J Interior Works & Furnishing H, I 90

K Landscape & Exterior Amenities H 40

L Staffing & Training J 45

M Testing, Inspection & Final Setup J, K 30

N Hotel Launch & Operations L, M 20


The Critical Path is highlighted in Red

A -> C -> E -> F -> G -> I -> J -> L -> N.


Explanation of how it will take the following days
Phase 1: Planning & Approvals

Activity Activity Description Duration Explanation


ID (Days)
A Market Research & 30 This involves demand analysis, competitor research, financial
Feasibility Study feasibility, and location selection. A month is reasonable as it
includes multiple consultations, surveys, and assessments.

B Land Acquisition & 45 Land purchase, obtaining zoning permits, and resolving legal
Legal Clearances documentation can be time-consuming due to bureaucratic
processes. Some delays in approvals are expected.

C Design & Architectural 60 Hiring architects, finalizing layout, structural drawings, and MEP
Planning (Mechanical, Electrical, and Plumbing) planning take time due to
multiple revisions and government approvals.

D Financing & Loan 40 Negotiating loans, securing investors, and financial structuring
Approvals require extensive paperwork and approvals from banks and funding
bodies.

Phase 2: Site Preparation & Core Construction


Activity ID Activity Description Duration (Days) Explanation
E Site Preparation & Groundwork 50 Land surveying, soil testing,
excavation, and leveling take
time depending on the land
condition, weather, and
machinery availability.
F Foundation Construction 70 The foundation is critical for
structural integrity. It involves
laying deep footings,
waterproofing, and setting
underground utilities, which
must be done with precision.
G Structural Work (Floors & Walls) 180 This is one of the longest
phases as it involves
constructing the hotel’s
framework, floors, concrete
slabs, walls, and staircases. The
complexity of a 200-room hotel
justifies this duration.
Phase 3: Structural Completion & Utility Installations

Activity Activity Description Duration Explanation


ID (Days)
H Roofing & Exterior Finishing 60 Installing roofing, facade, waterproofing, and
insulation requires skilled labor and careful
execution.

I Electrical & Plumbing Works 75 Laying electrical wiring, plumbing, HVAC


(Heating, Ventilation, Air Conditioning), and
fire safety systems requires specialized teams
and coordination.

Phase 4: Interiors & Landscaping

Activity Activity Description Duration Explanation


ID (Days)
J Interior Works & Furnishing 90 Installing flooring, wall finishes, ceilings,
lighting, doors, windows, furniture, and
decorative elements takes time, as multiple
contractors work simultaneously.
K Landscape & Exterior Amenities 40 Parking areas, gardens, pathways, signage,
and entrance designs are developed in this
phase. It runs parallel to interior work but still
requires a dedicated period.

Phase 5: Final Preparations & Launch

Activity Activity Description Duration Explanation


ID (Days)
L Staffing & Training 45 Hiring, onboarding, and training hotel staff in
hospitality, housekeeping, front desk
operations, and restaurant management
require extensive planning.
M Testing, Inspection & Final Setup 30 Fire safety, electrical checks, plumbing
tests, final equipment installations, and
government inspections must be completed
before opening.
N Hotel Launch & Operations 20 A soft launch, trial operations, marketing,
and grand opening preparations take about
three weeks to ensure a smooth start.