LOK SABHA
UNSTARRED QUESTION NO. 665
ANSWERED ON 13TH DECEMBER, 2018
(a) the details of current status of the East-West Corridor project in Assam, particularly in
the districts of Cachar and Dima Hasao;
(b) the year-wise funds allocated, funds released and funds utilised on the project from
2014 to 2018;
(c) whether there is any cost over-run for completion of the projects, if so, the details
thereof; and
ANSWER
Total Length
Sl. NH No. Total Length
Project District Scheme Completed Remarks
No (Old / New)
(Km) (Km)
State Assam (East -West Corridor Projects)
Date of Additi-
NH Cost of Revise
Sl. onal
Contract Pkg No. Length Commen Award d Cost During
N District Cost During During During Remarks
Stretch No. (Old/ (km) ce-ment Comp Comp (Rs in ( Rs in FY
o. ( Rs in FY FY FY
New) (as per (Org) (likely) Crore) Crore) 2017-
Crore) 14 -15 15-16 16-17
contract) 18
1 2 3 4 5 6 8 9 10 17 18 19 23 24 25 26 32
Four Laning of
WB Border
(Srirampur) to
The Contract
Kochugaon
18.10.05 17.04.08 - 218.38 218.38 0.00 3.22 0.00 0.19 0.00 was terminated
section from Km
on 29.03.2016
00.00 to Km
30.00
(Terminated)
31C /
1 Balance work of {AS-12} 30.000
27
four Laning of
Balance work
WB Border Kokrajhar
was Re-
(Srirampur) to (BTC)
awarded on
Kochugaon 05.10.17 04.04.20 - 129.19 129.19 0.00 0.00 0.00 0.00 0.00
31.07.2017 to
section from Km
M/s Simplex
00.00 to Km
infra Ltd..
30.00
(Reawarded)
Four Laning of
Kachugaon to Project
31C / Project
2 Karigaon section {AS-11} 29.715 06.10.05 05.04.08 Comple 199.41 220.20 20.79 24.38 38.00 21.22 29.45
27 Completed
from Km 30.00 to ted
Km 60.00
Four Laning of Bongaiga
Project
Karigaon to on & 31C Project
3 {AS-10} 32.671 06.10.05 05.04.08 Comple 248.69 281.78 33.09 56.46 63.93 37.26 15.58
Rakhaldobi Chirang /27 Completed
ted
section from Km (BTC)
Date of Additi-
NH Cost of Revise
Sl. onal
Contract Pkg No. Length Commen Award d Cost During
N District Cost During During During Remarks
Stretch No. (Old/ (km) ce-ment Comp Comp (Rs in ( Rs in FY
o. ( Rs in FY FY FY
New) (as per (Org) (likely) Crore) Crore) 2017-
Crore) 14 -15 15-16 16-17
contract) 18
1 2 3 4 5 6 8 9 10 17 18 19 23 24 25 26 32
60.00 to Km
93.00
(Old length 33.00
Km)
Four Laning of
Rakhaldobi to
Project
Patiladoha Bongaiga Project
4 {AS-9} 31 /27 21.500 03.11.05 02.05.08 Comple 131.23 151.91 20.68 9.14 0.00 0.00 2.38
section from Km on Completed
ted
961.50 to Km
983.00
Four Laning of
Patiladoha to Barpeta Project
31 / Project
5 Kaljhar section & Baska {AS-8} 30.000 03.11.05 02.05.08 Comple 187.08 204.00 16.92 10.31 5.26 0.00 0.00
27 Completed
from Km 983.00 (BTC) ted
to Km 1013.00
Four Laning of Show Caused
Kaljhar to Notice has
Patacharkuchi been issued to
section from Km 31 / 31.03.1 the contractor
6 Barpeta (AS-7) 27.30 19.10.05 19.04.08 207.17 230.00 22.84 7.81 5.37 22.47 0.66
1013.00 to Km 27 9 by the NHAI
1040.30 HQ under
clause 63.1 of
CoPA
Four Laning of 26.04.1
Patacharkuchi to Nalbari & 9 Project
31 /
7 Nalbari section Baska (AS-6) 24.700 10.11.05 10.07.08 (For full 182.48 193.26 10.78 4.16 4.31 6.00 2.88 Substantially
27
from Km 1040.30 (BTC) comple Completed
to Km 1065.00 tion)
Date of Additi-
NH Cost of Revise
Sl. onal
Contract Pkg No. Length Commen Award d Cost During
N District Cost During During During Remarks
Stretch No. (Old/ (km) ce-ment Comp Comp (Rs in ( Rs in FY
o. ( Rs in FY FY FY
New) (as per (Org) (likely) Crore) Crore) 2017-
Crore) 14 -15 15-16 16-17
contract) 18
1 2 3 4 5 6 8 9 10 17 18 19 23 24 25 26 32
Four Laning of
Nalbari to Nalbari & Project
31 / Project
8 Puthimari section Kamrup (AS-5) 28.000 02.12.05 01.06.08 Comple 192.87 236.75 43.88 53.64 12.91 0.00 6.31
27 Completed
from Km 1065.00 (Rural) ted
to Km 1093.00
Four Laning of
Puthimari to
Project
Amingaon Kamrup 31 / Project
9 (AS-4) 26.814 02.12.05 01.06.08 Comple 173.63 210.00 36.37 55.40 41.74 0.00 4.42
section from Km (Rural) 27 Completed
ted
1093.00 to Km
1119.814
Construction of Project
New Substantially
30.04.1
Brahamaputra Completed.
9
Bridge Kamrup 31 / Under DLP
10 (AS-28) 4.700 22.10.06 25.04.10 (For full 238.14 360.84 122.70 56.61 50.32 49.39 5.15
(Amingaon to (Metrol) 27 Bridge has
comple
Jalukbari) from been
tion)
Km 1119.81 to inaugurated on
Km 1124.51 29.01.2017.
Four Laning of
Khanapara
(Guwahati) to Kamrup 37 / 31.12.1 Ongoing
11 {AS-3) 19.100 25.10.05 24.07.08 166.72 174.34 7.62 0.00 21.22 0.00 4.72
Sonapur section (Metrol) 27 8 Project
from Km 163.90
to Km 183.00
Four Laning of 28.02.1
Project
Sonapur to 9
Kamrup 37 / Substantially
12 Jagiroad section (AS-20) 22.000 21.12.05 20.06.08 (For full 137.75 167.98 30.23 0.00 4.13 6.11 13.27
(Metrol) 27 Completed.
from Km 183.00 comple
Under DLP
to Km 205.00 tion)
Date of Additi-
NH Cost of Revise
Sl. onal
Contract Pkg No. Length Commen Award d Cost During
N District Cost During During During Remarks
Stretch No. (Old/ (km) ce-ment Comp Comp (Rs in ( Rs in FY
o. ( Rs in FY FY FY
New) (as per (Org) (likely) Crore) Crore) 2017-
Crore) 14 -15 15-16 16-17
contract) 18
1 2 3 4 5 6 8 9 10 17 18 19 23 24 25 26 32
Four Laning of
Jagiroad to
Project
Dharamtul 37 / Project
13 Morigaon {AS-19} 25.500 25.11.05 30.06.08 Comple 173.14 284.27 111.13 40.46 24.80 1.76 8.19
section from Km 27 Completed
ted
205.00 to Km
230.50
Four Laning of
Dharamtul to Project
Morigaon 37 / Project
14 Raha section {AS-02} 24.500 25.11.05 30.06.08 Comple 273.80 372.91 99.11 5.73 13.51 22.86 24.01
& Nagaon 27 Completed
from Km 230.50 ted
to Km 255.00
Four Laning of
Raha to Nagaon
section from Km Project
37 / Project
15 255.00 to Km {AS-18} 23.663 16.11.05 15.05.08 Comple 238.72 301.21 62.49 0.00 0.00 0.00 0.00
27 Completed
262.725 & ted
15.943 Km of
Nagaon Bypass
Four Laning of
Nagaon to Project
Nagaon 36 / Project
16 Daboka section {AS-17} 30.362 25.11.05 01.07.08 Comple 202.18 309.83 107.65 0.00 0.00 0.00 0.00
27 Completed
from Km 5.500 to ted
Km 35.862
Four Laning of
Daboka to Lanka
Project
section from Km 54 / Project
17 {AS-16} 24.032 29.11.05 28.06.08 Comple 198.65 221.57 22.92 0.00 0.00 0.00 0.00
0.00 to Km 22.00 27 Completed
ted
& 4.14 Km of
Dakoka Bypass
Date of Additi-
NH Cost of Revise
Sl. onal
Contract Pkg No. Length Commen Award d Cost During
N District Cost During During During Remarks
Stretch No. (Old/ (km) ce-ment Comp Comp (Rs in ( Rs in FY
o. ( Rs in FY FY FY
New) (as per (Org) (likely) Crore) Crore) 2017-
Crore) 14 -15 15-16 16-17
contract) 18
1 2 3 4 5 6 8 9 10 17 18 19 23 24 25 26 32
Four Laning of
Lanka to Udali
Project
section from Km 54 / Project
18 {AS-15} 18.000 14.03.08 13.09.10 Comple 143.97 186.76 42.79 0.00 0.00 0.00 0.00
22.00 to Km 27 Completed
ted
40.00 including
Lanka Bypass
Four Laning of
Udali to 31.12.1
Project
Manderdisa 8
54 / Substantially
19 (Lumding) Hojai {AS-27} 20.250 15.10.06 14.04.09 (For full 198.68 229.40 30.72 46.98 31.49 28.35 24.33
27 Completed.
section from Km comple
Under DLP
40.00 to Km tion)
60.50
Four Laning of
30.09.1
Manderdisa Project
8
(Lumding) to 54 / Substantially
20 {AS-26} 22.900 24.07.11 23.01.14 (For full 255.00 326.25 71.25 81.26 89.06 49.58 54.72
Hatikhali section 27 Completed.
comple
from Km 60.50 to Under DLP
tion)
Km 83.40
Four Laning of 31.03.1
Project
Hatikhali to Dima 9
54 / Substantially
21 Laining section Hasao {AS-25} 27.600 31.01.11 31.07.13 (For full 372.63 279.65 -92.98 67.89 41.06 48.35 50.26
27 Completed.
from Km 83.40 to comple
Under DLP
Km 111.00 tion)
Four Laning of
Lailing to Project
54 / Project
22 Maibong section {AS-24} 15.450 14.01.11 13.07.13 Comple 225.33 210.84 -14.49 27.81 32.22 14.19 24.92
27 Completed
from Km 111.00 ted
to Km 126.55
Date of Additi-
NH Cost of Revise
Sl. onal
Contract Pkg No. Length Commen Award d Cost During
N District Cost During During During Remarks
Stretch No. (Old/ (km) ce-ment Comp Comp (Rs in ( Rs in FY
o. ( Rs in FY FY FY
New) (as per (Org) (likely) Crore) Crore) 2017-
Crore) 14 -15 15-16 16-17
contract) 18
1 2 3 4 5 6 8 9 10 17 18 19 23 24 25 26 32
Four Laning of Project
Maibong to Substantially
31.12.1
Narimbanglo Completed.
8
section from Km 54 / Under DLP
23 {AS-23} 15.570 05.08.06 04.02.09 (For full 317.11 404.00 86.89 41.07 40.30 39.69 6.14
126.45 to Km 27 Affected by
comple
140.70 & Km landslide. 180m
tion)
164.08 to Km road has been
165.40 damaged.
Four Laning of Affected by
Narimbanglo to landslide.
Jatinga section 4 lane has
Foreclosed
from Km 140.70 been damaged
54 /
24 to Km 164.08 {AS-22} 23.380 03.11.11 02.05.14 318.69 612.90 294.21 64.96 71.52 104.24 118.76 in some areas
27
due to landslide
Dima & sinking.
Hasao Package
foreclosed
Four Laning of Contract
Jatinga to Terminated.
Harangajao 4 lane has
Contract Terminated.
section from Km been damaged
165.40 to Km due to landslide
190.59 & sinking.
54 /
25 {AS-21} 25.190 30.10.11 29.04.14 333.83 362.95 29.12 22.81 18.18 6.98 0.00 The
27
maintenance of
the existing NH
has been taken
up for the
benefits of the
road users and
Date of Additi-
NH Cost of Revise
Sl. onal
Contract Pkg No. Length Commen Award d Cost During
N District Cost During During During Remarks
Stretch No. (Old/ (km) ce-ment Comp Comp (Rs in ( Rs in FY
o. ( Rs in FY FY FY
New) (as per (Org) (likely) Crore) Crore) 2017-
Crore) 14 -15 15-16 16-17
contract) 18
1 2 3 4 5 6 8 9 10 17 18 19 23 24 25 26 32
the road is
being
maintained
now.
Four Laning of
Balachera to Project
54 /
26 Silchar section Cachar (AS-1) 25.760 17.09.04 16.09.07 Comple 115.86 151.60 35.74 14.26 0.17 11.45 0.00 Completed
27
from Km 275.00 ted
to Km 300.76
7032.7 1252.4
Grand Total 618.657 5780.32 694.36 609.50 470.09 396.15
7 5
Guwahati Bypass 18.000 Km
Total length of East - West Corridor 636.657 Km