Energy-System-Optimization-Modelling-through-PLEXOS-for-SAARC-member-states
Energy-System-Optimization-Modelling-through-PLEXOS-for-SAARC-member-states
Optimization
Modelling through
PLEXOS for SAARC
member states
Energy Exemplar
Why Energy Exemplar?
1. Market Leader since 1999. 350+ clients in 62+ countries
Clients by Region:
1 9 18 124
Clients by Segment:
Utilities: 97
Consultants: 44
Power Producers: 39
Researchers: 28
Regulators: 21
TSOs: 14
ISOs: 13
Traders: 5
Energy Analysts: 4
International Institutes: 3
Asia Pacific Customers
5
Why optimization?
Evaluate
Manage
Uncertainty
multiple
scenarios
Optimized
forecasting Foresight
accuracy
Minimize
costs
Fuel savings
8
How PLEXOS works?
.csv
Data read
Power system logic Engine Solver
Formulation & solution CPLEX, Xpress,
MIP and LP Gurobi, etc.
Solution interpretation
ENGINE
Reliability Evaluation
PSS®E AC OPF
PLEXOS Main Applications
Dispatch
Optimization
Reliability Hydro-thermal
Analysis Coordination
Generation
Energy and
and PLEXOS Reserves Co-
Transmission Functions optimization
Planning
Electricity and
Renewables
Gas Co-
Integration
optimization
Policy and
Strategy
Evaluation
10
Integrated Energy Model
Post-Fact Hour Ahead to Next Month Next Month to Next 5 Years Next 5 Years to Next 30+ Years
Market Market Analysis: Understanding market landscape, trends, effects and forecasting
When Where
P(x): Production Cost To build/retire To build/retire
x = Assets
MIP Objective: Minimize NPV of capital & production
Total
C(x) P(x)
Cost
14
Indicative Generation Capacity
Expansion Plan (IGCEP 2047)
Objectives:
Identify new generation requirements
by capacity, fuel technology and
commissioning dates on year-by-year
basis;
Satisfy the Loss of Load Probability
(LOLP) not more than 1% year to year;
Cater for the long-term load growth
forecast and reserve requirements; and
Provide a least cost optimal generation
expansion plan for development of
hydroelectric, thermal, nuclear and
renewable energy resources to meet the
expected load demand up to the year 2047
15
Load Forecasting
Base Load Profile Peak and Energy Forecast
Energy (TWh) Peak Load (MW)
7000 Historical Load 2017
6500 90.0 12,000
6000
5000 10,000
70.0
4500
4000 60.0
8,000
3500 50.0
40.0 6,000
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
16
Renewable Energy Integration
PLEXOS® Stochastic Optimization considers multiple renewable profiles
to deliver a single optimal build decision.
18
Medium Term Planning
LT Plan MT Schedule ST Schedule
Decompose inter-temporal
constraints that would otherwise
020 be too long for ST Schedule
500000
450000
Hydro Fuel
End Volume (1000 m3)
400000
350000 storage levels constraints
300000
250000 Inter-temporal
200000 Constraints
150000
100000 Generator
50000 technical Emission limits
0
limits
ST MT 20
System Security and Maintenance Planning
Projected Assessment of System Adequacy (PASA) is a simulation
phase that focuses on the balance of supply and demand in the
medium term. The functions of the PASA simulation phase are:
Reliability
EENS LOLP
• Compute reliability statistics such as: Reporting
LOLE
21
Hydro Optimization
Multiple phase
Ensures optimal use of storage down to
simulation chronological level
(Long – Medium – Short)
2000
1750 3) Ramping: High ramping
1500
1250 requirements with solar generation
1000
750
increase/decrease.
500
250
0
4) Hydro constraints: Highly complex
irrigation constraints.
Serie 1 Serie 2 Serie 3 Serie 4 Serie 5 Serie 6 23
Serie 7 Serie 8 Serie 9 Serie 10 Serie 11 Serie 12
Short Term Formulation
Minimise Operational Costs + Start−up/Shutdown Costs
How
How Much meet system
should each unit security
generate requirements
26
Dispatch Optimization
Over 300+ Unit
Mixed Integer Commitment
Constraints Resolution down
Programing properties modelling to 1-second
500
Generation (MW)
400
300
200
28
Cascading System Optimization
Time: t Inflow6
Total Generation = 1255 MW 272.1 m3/s
300 m3/s
• Generators flow water from their
Inflow1
117.2 m3/s
Inflow2
Gen8
Head Storage to their Tail
34.84 m3/s
25.1 MW
~ ~ Gen10
2 MW Storage or ‘to the sea’.
Leaks Lake Lake
1 2
Gen9
272.9 m3/s
~
89.6 726.7
Hm3 Hm3 6 MW
~
13.8 m3/s
Gen4 Hm3
53.5 MW
Gen12 loss of potential energy during
~ Gen15 Gen16
~
Gen14
37 MW
Irrigation Constraints
192.7 m3/s
29
Transmission Modelling
• Transmission operation
• Transmission Expansion Planning
• Security Constrained Economic
Dispatch (SCED)
• ‘N-x’ Contingency Analysis
• Congestion Costs
• Transmission aggregation and
Network reduction
• PSSE Power Flow Raw Data file
Importer Single Line Diagram (SLD) allow users to review
nodal connection
30
Battery Energy Storage System
Solar Generation and Battery Net Generation Solar Moquegua
Solar farm
800
220
Battery
BESS Moquegua
1
600
220
Battery discharging Battery
BESS ILO
2 220
Generation [MW]
400
200
0
0 6 12 18 24 30 36 42 48
-200 Hours
-400
Battery charging
33
Electricity and Gas Co-optimization
• Right-sizing for supply, storage, and transportation contracts
given gas and power demand
• Reliability requirements for delivering gas Gas Node 2
• Renewable generation impact studies to
serve both power and gas demand
• Storage injection and Gen_4
given both
power and gas demand Generator is
supplied with
PTG Fuel from the
Gas Node
Integrated Strategic Optimization
• High & low renewable penetration
scenarios impact on gas demand
• Impacts of nuclear & coal retirements to
the gas demand
• Increasing carbon price impact on merit
order between gas and coal
35
Concluding Remarks
Better knowledge
Accurate foresight
A confident direction
Optimal operation
36
Thank you for your kind attention
Do not hesitate to contact us if you have any question or want to know
more about our solutions.
Belen Leveroni
Business Development Executive
[email protected]
37
End