Advanced Protection
Advanced Protection
DIgSILENT PowerFactory *
Figure 1: Two machine network model to simulate stable and unstable power swings
Rev.2 2
ADVANCED PROTECTION APPLICATION EXAMPLE
The fault clearing time for a stable PS in this case is To create an unstable condition, a longer fault clearing
100 ms. After the short circuit is cleared by opening time of 300 ms is specified. This causes the genera-
both circuit breakers located at OHL2, the system re- tor to accelerate beyond its stability limit. The swing is
acts with a PS frequency oscillation of approximately no longer stable and cuts across the impedance char-
1 Hz. acteristic of the generator relay, entering the OOS 1
characteristic in the right half of the resistive plane,
Figure 4 shows the impedance trajectory in the R- crossing the imaginary axis within the OOS1 charac-
X plane for a simulation time of 1 s. The relay initially teristic and then exiting it in the left half of the imagi-
sees the fault on OHL2 in the reverse direction, af- nary plane (figure 5). Since the OOS 1 characteristic
ter the fault is cleared, the trajectory jumps between setting only allows one crossing of the characteristic,
the PS zones and swings back into Zone 1 before fi- the relay immediately trips.
nally swinging out of the PS zones. Figure 6 shows
binary signals from the PS blocking logic. The first
[pri.Ohm]
crossing of the two PS characteristics is nearly instan-
taneous but the second crossing has a duration of 0,12
sequently zone 1 does not trip. After the power swing 0,04
63,
Power Swing -0,06
Zone 2 -0,10
38,
Z1P
Zone 1
25, Figure 5: RX plot section of the generator distance
13,
relay with the impedance trajectory
13, 25, 38, 50, 63, 75, 88, 100, 113, 125, 138, [pri.Ohm]
-13,
-25,
-38,
-50,
Rev.2 3
ADVANCED PROTECTION APPLICATION EXAMPLE
2
Inner Zone
1 Outer Zone
0
2
Blocking Input Z1P
1 Blocking Input Z2P
0
20
10 Power Swing Starting
0
0 0,2 0,4 0,6 0,8 [s] 1
Rev.2 4
ADVANCED PROTECTION APPLICATION EXAMPLE
Rev.2 5
ADVANCED PROTECTION APPLICATION EXAMPLE
Four study cases are configured to demontrate the Right click on the Study Case “02a Unsuccessful 1-
ARC functionality. The first two cases study the oper- Phase Auto Reclosing” and activate it. A “Single
ation of ARC relays during a single phase to ground Phase to Ground Fault” short circuit event has been
fault and the remaining two cases during a three defined at 50% of the length of line NW-NE_L3.
phase fault:
Select the Simulation RMS/EMT Toolbox and run the
• 02a Unsuccessful 1-Phase Auto Reclosing configured dynamic simulation for 10 seconds. The
plots as shown in figure 8 represent the operation of
• 02b Successful 1-Phase Auto Reclosing the relays. When the fault is not cleared after the sec-
ond reclosure attempt, the relays reach the lockout
state.
• 02c Unsuccessful 3-Phase Auto Reclosing
The upper plot shows the three phase currents of the
• 02d Successful 3-Phase Auto Reclosing line during this simulation and the lower curve repre-
sents the states of both the breakers during the ARC
After executing each simulation, the stability of each operation of the relays. The fault occurres at t=0 and
generator should be verified based on the relative ro- at t=1.6 s both relays attempt to close the breakers.
tor angle between its own rotor angle and that of the Since the fault is still there, the breakers open and at
reference machine. t=1.7 s, and the relays reach the lockout state.
6
[kA]
4
2
0
0 0,5 1 1,5 [s] 2
1,5
0,5
0
0 0,5 1 1,5 [s] 2
2.2.2 Successful 1-Phase Auto Reclosing gle phase to ground fault at t=1 s. Run the dynamic
simulation for 10 seconds. The plots, as shown in fig-
ure 9, represent the operation of the relays. Since the
Right click on the Study Case “02b Successful 1- fault is cleared at t=1 s., the relays successfully close
Phase Auto Reclosing” and activate it. In this case, the breakers after the second reclosure attempt and
a second short circuit event is defined to clear the sin- the network continues in its normal operating state.
Rev.2 6
ADVANCED PROTECTION APPLICATION EXAMPLE
4
[kA]
2
0
0 0,5 1 1,5 [s] 2
1,5
0,5
0
0 0,5 1 1,5 [s] 2
2.2.3 Unsuccessful 3-Phase Auto Reclosing at 50% of the length of line NW-NE_L3. Run the dy-
namic simulation for 10 seconds. The plots, shown in
Right click on the Study Case “02c Unsuccessful 3- figure 10, represent the operation of the relays. When
Phase Auto Reclosing” and activate it. In this case, the fault is not cleared after the second reclosure at-
a “3-Phase Short-Circuit” short circuit event is defined tempt at t=0.5 s, the relays enter a lockout state.
[kA]
4
0
0 0,5 1 1,5 [s] 2
1,5
0,5
0
0 0,5 1 1,5 [s] 2
Rev.2 7
ADVANCED PROTECTION APPLICATION EXAMPLE
2.2.4 Successful 3-Phase Auto Reclosing phase fault. Run the dynamic simulation for 10 sec-
onds. The plots, shown in figure 11, represent the
operation of the relays. Since, the fault is cleared at
Right click on the Study Case “02d Successful 3- t=0.2 s, the relays close the breakers successfully af-
Phase Auto Reclosing” and activate it. In this case, a ter the second reclosure attempt and the network and
second short circuit event is defined to clear the three the network continues in its normal operating state.
6
[kA]
4
2
0
0 0,5 1 1,5 [s] 2
1,5
0,5
0
0 0,5 1 1,5 [s] 2
Rev.2 8
ADVANCED PROTECTION APPLICATION EXAMPLE
[1] Gerhard Zieger: “Numberical Distance Protec- [3] “Richtlinie für die Automatische Wiedereinschal-
tion - Principles and Applications”, Publicis Pub- tung in elektrischen Netzen”, VWEW Energiever-
lishing, 2011, ISBN 978-3-89578-381-4 lag GmbH, 2001