The document provides a detailed overview of resource capacity, project assignments, and estimation versus actual hours worked for various team members in a development and production support context. It includes information on capacity utilization for June and July, planned leaves, and remarks on project progress. Additionally, it lists user stories and tasks assigned to each team member along with their respective story points and descriptions.

Uploaded by

sadhiq1995
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views19 pages

SL C360 Team Capacity - Jul'24

The document provides a detailed overview of resource capacity, project assignments, and estimation versus actual hours worked for various team members in a development and production support context. It includes information on capacity utilization for June and July, planned leaves, and remarks on project progress. Additionally, it lists user stories and tasks assigned to each team member along with their respective story points and descriptions.

Uploaded by

sadhiq1995
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 19

Name Team Project Capacity Available June Capacity Utilised June Capacity Available July Capacity Actual July

Akanksha Rastogi Development 128 137 120 110


Jayalakshmi Ede Development 152 164 126 106
Jesus Sankaran Development 128 136 126 118
Karunakar Kukunoori Development 152 171 138 132
Santanu Dutta Development 96 108 138 122
Neha Saxena Development 144 156 132 56
Mohammed Sadhiq Vajeer Development 136 148 126 66
Robin Rana Prod Support 138 #N/A
Lavanya N Prod Support 138 #N/A
Anbarasan M Prod Support 138 #N/A
Deepak Kumar Development 0 0 24 24
Capacity Avilable Aug Capacity Planned Aug Planned Leaves - Jul Planned Leaves - Aug Remarks

160 0 3 1
168 0 2
160 0 2 1
168 0
168 0
168 0 1
168 0 2
168 0
144 0 3
168 0
168 0 0
Planned End Date - all -

Data
Name Sum of Estimation HoursSum of Actual Hrs
Akanksha 100 110
Deepak Kumar 24 24
Jayalakshmi, Ede 112 106
Jesus Arockia Sankaran S 88 118
Karunakar 128 132
Mohammed Sadhiq Vajeer 80 66
Santanu Dutta 88 122
Saxena, Neha 56 56
(empty) 0
Total Result 676 734

Row Labels Sum of Estimation Hours Sum of Actual Hrs


Akanksha Rastogi 100 110
Deepak Kumar 24 24
Jayalakshmi Ede 112 106
Jesus Sankaran 88 118
Karunakar Kukunoori 128 132
Mohammed Sadhiq Vajeer 80 66
Santanu Dutta 88 110
Neha Saxena 56 56
Name Project Name User Story Short Description Story Points
(Current / Planned)
Akanksha Extended View Cameras (Peripheral) VBG43960-279 Enhance SuperLibra APIs with DVR Details and Camera 5
Management (RHI)
Akanksha SL 2.0 SL360-2208 Government, Sourcewell or GSA fixed end date issue 3
SIT_IS_Credit card_CA wallet id field is not updated in the
Akanksha Rev Rec VZC42823-344 NA
contract account

Akanksha SL 2.0 Conflict fix - multiple services (order-servie/ order- NA


camunda-service/ sfdc-service)

Akanksha Extended View Cameras (Peripheral) SL360-2244 Implement Assign & Confirm for Extended View Cameras 2
Deepak Kumar Advanced Connect 360 VZC47353-495 Error banner is not matching for add flow 3
Job Amendments for Completed Tickets - ability to add
Jayalakshmi, Ede Advanced Connect 360 VZC47353-373 2
fees for Completed jobs and Partially Completed jobs

Jayalakshmi, Ede Advanced Connect 360 VZC47353-381 C360 Admin Tool : Service Fee (Installer/Customer) 2
Management screen
Jayalakshmi, Ede Advanced Connect 360 VZC47353-472 2
Jayalakshmi, Ede Advanced Connect 360 VZC47353-519 C360 ticket W000023940 is not generating SO 2
Update Vendor Management Admin screen to
Jayalakshmi, Ede Advanced Connect 360 VZC47353-419 show/manage International Vendors for Automatic 3
Scheduling - AUS
Update Vendor Management Admin screen to
Jayalakshmi, Ede Advanced Connect 360 VZC47353-432 show/manage International Vendors for Automatic 3
Scheduling - CAN
Jayalakshmi, Ede Advanced Connect 360 VZC47353-544 Auto Schedule throwing unexcepcted error for GBR 1
Jesus Arockia Sankaran S Advanced Connect 360 VZC47353-548 Case : Add Hardware : Create work ticket button not 2
enabled
Jesus Arockia Sankaran S Advanced Connect 360 VZC47353-545 Return Item dialog is closing while trying to select ESN 2
Jesus Arockia Sankaran S Advanced Connect 360 VZC47353-526 ESN's are getting deselected on closing the drop down- 2
Partial lost in transit flow

Jesus Arockia Sankaran S Common Task Reverse Merge Reverse merge conflicts has been resolved for July 15th N/A
relase.

Jesus Arockia Sankaran S Advanced Connect 360 VZC47353-521 Disable Grid Search as Iterim Fix for scheduling Jobs - 2
(Emergency Release)
PROD - INC0222289 - Cannot select individual ESN when
Jesus Arockia Sankaran S Advanced Connect 360 VZC47353-506 2
processing LOST IN TRANSIT in C360
Jesus Arockia Sankaran S Advanced Connect 360 VZC47353-381 Disucussing and validating the UX design's feasibily. NA

Purchase Portal User Stories


SL360-2274 Purchase Portal - Create an API to Finalise
Payment Details
SL360-2274
SL360-2267 SL360-2267-Purchase Portal - Create an API to Generate
Karunakar SL 2.0 Payment Service Session Link 1
SL360-2273
SL360-2272 SL360-2273 Purchase Portal - Create an API to Submit
Payment Details
SL360-2272-Purchase Portal - Create an API to
Authenticate Payment Service
SL360-2298
Karunakar SL 2.0 SL360-2254 New Relic Issues 2
Karunakar SL2.0 SL360-2255
SL360-2425 Black Duck issues(fixed for 15 APIS) 2
DOIC
SL360-2387 Create an API to Generate Order Session Link-
SL360-2387 DOIC
Karunakar SL 2.0 SL360-2422 SL360-2422-Create an API to Regenerate Order Session 2
SL360-1413 Link
SL360-1413-DOIC : Create an API to validate address
information

Mohammed Sadhiq Vajeer Advanced Connect 360 VZC47353-430 UX - 4. MEA - Australia - Manage Existing Appointment 4
(Reschedule, Cancel, Expand BAU)
Mohammed Sadhiq Vajeer Advanced Connect 360 VZC47353-427 MEA - Australia - Appointment Scheduling 3
Mohammed Sadhiq Vajeer Advanced Connect 360 VZC47353-546 Installed Quantity - RHI not getting updated for installed 2
items on Case page
Mohammed Sadhiq Vajeer Adhoc Tasks NA
VZC48106-369 Resolving merge conflicts for release/240919 to QA 1
Santanu Dutta SL Legacy VZC48106-370 MIP isues 5
VZC48106-360 SIT:: Driver facing camera_inboundshipment failed in
Santanu Dutta SL Legacy ENVVC24-132 1
SL2.0
Santanu Dutta SL Legacy Prod Suppoer Working on two incident 1
Santanu Dutta Telogis Access Getting access for TElogis application support 2
Device status "shipped" is in lower case Incident
Santanu Dutta SL Legacy VZC47461-390 2
INC012132781
Santanu Dutta Adhoc Tasks Prod Support
Santanu Dutta Common Task
Saxena, Neha Advanced Connect 360 VZC47353-489 CSP/CASE : Not able to schedule job in workticket 3
Saxena, Neha Advanced Connect 360 VZC47353-491 Lost in Transit : Validate address button is not enabled on 1
updating the address
Lost in Transit : Not able to create work ticket with new
Saxena, Neha Advanced Connect 360 VZC47353-492 1
address
Saxena, Neha Advanced Connect 360 VZC47353-504 UI for Backend & UX -Service Fee , vendor Fee Flag 2
Estimation Hours Actual Hrs Planned Start Date Planned End Date Type of Work
(Config /Dev /Analysis / Data)
40 45 1-Jul-24 15-Jul-24 Dev
24 24 2-Jul-24 3-Jul-24 Analysis
16 16 3-Jul-24 5-Jul-24 Analysis

4 5 1-Jul-24 12-Jul-24 Dev

16 20 15-Jul-24 18-Jul-24 Dev


24 24 9-Jul-24 11-Jul-24 DEV
16 18 1-Jul-24 2-Jul-24 Dev

16 18 3-Jul-24 4-Jul-24 Analysis


16 18 5-Jul-24 8-Jul-24 Analysis
16 18 10-Jul-24 11-Jul-24 Config

16 10 9-Jul-24 11-Jul-24 Dev

24 16 15-Jul-24 17-Jul-24 Dev

8 8 15-Jul-24 15-Jul-24 Analysis


16 16 18-Jul-24 19-Jul-24 Dev
16 16 17-Jul-24 18-Jul-24 Dev
16 16 12-Jul-24 16-Jul-24 Dev

8 6 16-Jul-24 16-Jul-24 Post-release activity

16 16 12-Jul-24 15-Jul-24 Dev

16 16 11-Jul-24 12-Jul-24 Dev


N/A 32 1-Jul-24 10-Jul-24 Analysis

32 36 1-Jul-24 12-Jul-24 DEV

32 30 10-Jul-24 19-Jul-24 DEV/ANALYSIS


32 30 CONFIG
32 36 21-Jul-24 26-Jul-24 DEV

32 34 1-Jul-24 4-Jul-24 Dev


24 16 5-Jul-24 8-Jul-24 Dev
16 8 9-Jul-24 10-Jul-24 Dev
8 8 11-Jul-24 11-Jul-24 Dev
40 45 9-Jul-24 18-Jul-24 Analysis
8 10 12-Jul-24 16-Jul-24 Analysis
8 15 16-Jul-24 18-Jul-24 Prod
16 20 1-Jul-24 30-Jul-24 Config
16 20 17-Jul-24 22-Aug-24 Analysis
0 8
0 4
24 24 1-Jul-24 3-Jul-24 Dev
8 8 4-Jul-24 4-Jul-24 Dev

8 8 5-Jul-24 5-Jul-24 Dev


16 16 9-Jul-24 10-Jul-24 Dev
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Comments

Analysis the issue in env, resolved with code merge to qa for SIT bug
Analysis the issue blocked to test with other milestone failure.

Code merge qa to dev (order-servie/ order-camunda-service/ sfdc-service)

Development delyed due to test data


Code merged to qa
Need to complete by 28-jun it self but extended to Jul-2nd due to Inputs pending from bussiness.

Did Analysis and worked with Balaji to complete DB changes.

Waiting for Configuration to updated by Backend team.

Waiting for Configuration to updated by Backend team.

Then and there I was working on this requirement gathering and grooming.
Resolved Merge conflicts between release branch and QA.
1-May-24 30-Sep-24
Data
Resource Sum of Available Hrs Sum of Utilised / Actual Worked Hrs
Akanksha 128 137
Jayalakshmi, Ede 152 164
Jesus Arockia Sankaran 128 136
Karunakar Kukunoori 152 171
Praveen Reddy 120 120
Sahithi S 120 140
Santanu Dutta 96 108
Saxena, Neha 144 156
Vajeer, Mohammed Sadhiq 136 148
Total Result 1176 1280
Resource Project No. of Working Days in June/ Available Hrs
Total Story points for Project
Jesus Arockia Sankaran Advanced Connect 360 10 80
Jesus Arockia Sankaran SL 2.0 3 24
Jesus Arockia Sankaran Adhoc Tasks (Prod Sup, Security, Tech Debt, Data Cleanup, Deployement) 3 24
Jayalakshmi, Ede Advanced Connect 360 16 128
Jayalakshmi, Ede Adhoc Tasks (Prod Sup, Security, Tech Debt, Data Cleanup, Deployement) 3 24
Saxena, Neha Advanced Connect 360 18 144
Vajeer, Mohammed Sadhiq Advanced Connect 360 17 136
Karunakar Kukunoori SL 2.0 19 152
Praveen Reddy SL 2.0 15 120
Sahithi S Adhoc Tasks (Prod Sup, Security, Tech Debt, Data Cleanup, Deployement) 10 80
Sahithi S Advanced Connect 360 5 40
Akanksha Extended View Cameras (Peripheral) 3 24
Akanksha Rev Rec 3 24
Akanksha SL 2.0 10 80
Santanu Dutta Digital Self Serve (VCCP / MIP) 5 40
Santanu Dutta Run The Business 1 8
Santanu Dutta Adhoc Tasks (Prod Sup, Security, Tech Debt, Data Cleanup, Deployement) 4 32
Santanu Dutta Contract Flex 2024 / Capex Cancellation 2 16
Utilised / Actual
Worked Hrs Remarks, If Any

88
24
24
136
28
156
148
171
120
100
40
25
26
86
45
8
35
20