Cap_Bud_II
Cap_Bud_II
1. NPV Steps
- Use Cashflows - Find the cashflows(Initial, Operating, Terminal)
Connection points
- IRR and Payback are going to use same formula
- NPV and PI require same inputs
- ROI is unique
IRR using manual method
Initial outlfow Uniform Cash inflows rate = 8%
Yr 0 1 2 3 NPV 1540
-50000 20000 20000 20000
- @ IRR, NPV = 0
so 20000 of annuity is multiplied by a PV factor such that PV is 50000
PV factor 2.5 - Cashoutflow/Uniform cash inflow
Period is 3 yrs
From the chart, we can find that IRR is between 9% and 10%
If you are using real cashflows for capital budgeting, the discount rate should be adjusted for inflation ie no inflation in the dis
If you are using nominal cashflows for capital budgeting, discount rate should not be adjusted for Inflation ie Inflation should b
We should be able to do below 4
1. Convert nominal to real cashflows. -----> Divide nominal cashflows by (1+Inflation rate)
2. Convert real to nominal cashflows. ------> Multiply by (1+Inflation rate)
3. Convert nominal to real rate of return
4. Convert real to nominal rate of return
Mutually exclusive projects Only one of the available options can be chosen
Always prefer NPV
These projects are dependent - If one is chosen, other cannot be chosen
Independent Projects
Unrelated projects
Scenarios
Change more than 1 independent variable to get different scenarios
Simulation
Model of real time environment where actual behavioral changes can be studied
- Run the simulation for 10 times and plot NPV in a frequency distribution graph
- Statistical models to evaluate different results
- Monte Carlo Simulation
Discount rate
Certainty equivalent Risk free rate
Remove risks for cashflows and use risk-free rate to find NPV Nominal rate
Only 2 steps differ from normal NPV Real rate
1. Multiplying cashflows by certainty factors
2. Discounting by rf which is my risk free rate
Question 2
1 2 3 4 5
Outflow -200000 -200000 -200000 -200000 -200000
Tax Savings 80000 80000 80000 80000 80000
Net outflow -120000 -120000 -120000 -120000 -120000
PV(10%, 5 yyrs) 3.790787 3.791
PV of outflows -454894 -454920
Question 9
0 1 2 3 4 5
Initial inv -1000000
Units sold 92000 92000 92000 92000 92000
Prof Margin /unit 5 5 5 5 5
Profits 460000 460000 460000 460000 460000
PAT 276000 276000 276000 276000 276000
Depreciation 200000 200000 200000 200000 200000
DTS 80000 80000 80000 80000 80000
NPV 5024
WACC 10%
Proj X Proj Y
PV factor 3.790787 0.620921
PV of inflows 178167 173858
NPV 28166.98 23857.97
ows = PV of outflows
ws = 40000000
ws = PV factor * Annuity
= PV Of inflows/Annuity
= 40000000/6000000 6.666667
yyears and PV factor = 6.66 10%
WACC Tax
12% 40%
Rf 4%
0.961538
0.924556
0.888996
0.854804
0.821927
Alternative 1
0 2007 2008 2009 2010
Sale proceeds from plant 3000000
Tax saved on CL(inflow) = 240000
NPV = 3240000
Alternative 2
0 2007 2008 2009 2010
Lease Payments 1020000 1020000 1020000 1020000
Lease income after tax 612000 612000 612000 612000
Depreciation 900000 900000 900000 900000
DTS 360000 360000 360000 360000
MV of asset(end of life) 600000
Tax on CG/CL = 0
Final CFs = 972000 972000 972000 1572000
NPV = 3051206
Alternative 3
0 2007 2008 2009 2010
Sales 4200000 4200000 4200000
Annual cash outlay 2250000 2250000 2250000
Profit -2250000 1950000 1950000 4200000
Profit after tax -1350000 1170000 1170000 2520000
Depreciation 900000 900000 900000 900000
DTS 360000 360000 360000 360000
MV of asset(end of life) 600000
Tax on CG/CL = 0
Final Cash Flow -990000 1530000 1530000 3480000
NPV = 3185770
BV of plant as of 1-1-07 = 4200000
Sales value of plant = 3000000
Capital Loss = 1200000
Tax saved on CL(inflow) = 240000
EV of Sales 5200000
BV of Asset at end of 2010 600000
MV at end of 2010 = 600000
CG or CL = 0
Hurdle Rate or Cost of Capital = 10%
Project A
0 1 2 3 4 5
-155000 43000 43000 43000 43000 43000
IRR = 12.00%
Project B
0 1 2 3 4 5
-240000 60000 60000 60000 60000 60000
IRR = 7.93%
By Manual Method
PV Factor Proj A = 3.605 IRR of Proj A = 12% Greater than Cost of Capital, hence ACCEPT
PV Factor Proj B = 4 IRR of Proj B = 8% less than Cost of Capital, hence REJECT
Payback Method
Payback for A 3.605 yrs ACCEPT because this is < 4yrs
Payback for B 4.000 yrs ACCEPT because this is = 4yrs which Company requirement
BV Market ValueCG/CL Tax paid/saved
Land 500000 700000 200000 -80000
Building 1000000 800000 -200000 80000
Equipment 0 120000 120000 -48000
Tax rate 40% Revenues 1500000
Discount rate 6%
0 1 2 3 4 5
Land -500000
Building -2000000
Equipment -3000000
ICF -5500000
Revenues 1500000 1500000 1500000 1500000 1500000
Cash expenses 300000 300000 300000 300000 300000
Pretax profit 1200000 1200000 1200000 1200000 1200000
After tax profit 720000 720000 720000 720000 720000
Depreciation of Building 200000 200000 200000 200000 200000
Depreciation of Equipment 600000 600000 600000 600000 600000
Total Depreciation 800000 800000 800000 800000 800000
DTS 320000 320000 320000 320000 320000
OCF 1040000 1040000 1040000 1040000 1040000
NPV
ABC 950
ABD 980
ACD 880
BCD 730
Volvo 0 1 2
NPV 2 mn
0 1 2
2 mn
Total NPV 3.594
Benz 0 1 2 3 4
NPV 3.5 mn
Proj A 0 1 2 3 4 5 6
-1000 1000 1000 1000
1321.63
Proj B 0 1 2 3 4 5 6
-1000 0 0 0 1500 1500 1500
1350.55
Project A
Year Exp. cashfl CE factor Discount Factor @ 3% Certain cashPV
1 1,500 0.9 0.971 1350 1310.85
2 1,200 0.85 0.943 1020 961.86
3 900 0.7 0.915 630 576.45
4 600 0.6 0.888 360 319.68
Initial Investment - 3,000; Risk free rate 3%; Calculate Project’s NPV
NPV 168.84
Proj B 0 1 2 3 4 5 6
-1000 0.0 0.0 0.0 1500 1500 1500
We can solve this
problem without
finding NPV at all OR
Proj B 0 1 2 3 4 5 6
-1000 1012.5 1012.5 1012.5