Unit 3- Asset Depreciation and Project Evaluation
Unit 3- Asset Depreciation and Project Evaluation
Related Concepts:
Methods of Depreciation
There are several methods of accounting depreciation fund.
These are as follows:
1. Straight line method of depreciation
2. Declining balance method of depreciation
3. Sum of the years—digits method of depreciation
4. Sinking-fund method of depreciation
5. Service output method of depreciation
Example 1
A company has purchased an asset whose first cost is ₹ 1,00,000 with an estimated life of eight
years. The estimated salvage value of the asset at the end of its lifetime is ₹ 20,000. Determine the
depreciation charge and book value at the end of various years using the straight line method of
depreciation.
P = ₹ 1,00,000
F = ₹ 20,000
n = 8 years
Dt = (P – F)/n = (1,00,000 – 20,000)/8
= ₹ 10,000
In this method of depreciation, the value of Dt is the same for all the years. The calculations
pertaining to Bt for different values of t are summarized in Table.
Table Dt and Bt Values under Straight line Method of Depreciation
End of year Depreciation Book Value
(t) (Dt) (Bt = Bt–1 – Dt)
0 1,00,000
1 10,000 90,000
2 10,000 80,000
3 10,000 70,000
4 10,000 60,000
5 10,000 50,000
6 10,000 40,000
7 10,000 30,000
8 10,000 20,000
If we are interested in computing Dt and Bt for a specific period (t), the formulae can be used. In
this approach, it should be noted that the depreciation is the same for all the periods.
Example 2
Consider Example and compute the depreciation and the book value for period 5.
P = Rs. 1,00,000
F = Rs. 20,000 n = 8 years
D5 = (P – F)/n = (1,00,000 – 20,000)/8
= Rs. 10,000 (This is independent of the time period.)
Bt = P – t (P – F)/n
B5 = 1,00,000 – 5 (1,00,000 – 20,000)/8
= Rs. 50,000
Declining Balance Method of Depreciation
In this method of depreciation, a constant percentage of the book value of the previous period of
the asset will be charged as the depreciation amount for the current period.
This approach is a more realistic approach, since the depreciation charge decreases with the life of
the asset which matches with the earning potential of the asset.
The book value at the end of the life of the asset may not be exactly equal to the salvage value of
the asset. This is a major limitation of this approach.
Let
P = first cost of the asset,
F = salvage value of the asset,
n = life of the asset,
Bt = book value of the asset at the end of the period t,
K = a fixed percentage, and
Dt = depreciation amount at the end of the period t.
The formulae for depreciation and book value are as follows:
Dt = K Bt-1
Bt = Bt–1 – Dt
= Bt–1 – K Bt–1
= (1 – K) Bt–1
The formulae for depreciation and book value in terms of P are as follows:
Dt = K (1 – K) t–1
P Bt = (1 – K) t P
While availing income-tax exception for the depreciation amount paid in each year, the rate K is
limited to at the most 2/n. If this rate is used, then the corresponding approach is called the double
declining balance method of depreciation.
EXAMPLE 3
Consider Example 1 and demonstrate the calculations of the declining balance method of
depreciation by assuming 0.2 for K.
Solution
P = Rs. 1,00,000
F = Rs. 20,000
n = 8 years
K = 0.2
The calculations pertaining to Dt and Bt for different values of t are summarized in Table 9.2 using
the following formulae:
Dt = K Bt-1
Bt = Bt–1 – Dt
Table Dt and Bt according to Declining Balance Method of Depreciation
End of year Depreciation Book Value
(n) (Dt) (Bt = Bt–1 – Dt)
0 1,00,000.00
1 20,000.00 80,000.00
2 16,000.00 64,000.00
3 12,800.00 51,200.00
4 10,240.00 40,960.00
5 8,192.00 32,768.00
6 6,553.60 26,214.40
7 5,242.88 20,971.52
8 4,194.30 16,777.22
If we are interested in computing Dt and Bt for a specific period t, the respective formulae can be
used.
EXAMPLE 4
Consider Example 9.1 and calculate the depreciation and the book value for period 5 using the
declining balance method of depreciation by assuming 0.2 for K.
Solution
P = Rs. 1,00,000
F = Rs. 20,000
n = 8 years
K = 0.2
Dt = K (1 – K) t–1 P
D5 = 0.2(1 – 0.2)4 1,00,000
= Rs. 8,192
Bt = Bt–1 – Dt P
B5 = = (1 – 0.2) 5 1,00,000
= Rs. 32,768
Project Evaluation Techniques: Present Worth Method, Future Worth Method
Present Worth Method
When evaluating investment projects or asset, selecting the best option requires comparing their
financial benefits or costs. The Present Worth (PW) Comparison Method provides a consistent
basis for this decision-making by translating future cash flows to a single reference point in time
known as “present worth” for a clear comparison. These comparisons are particularly essential
when the alternatives are mutually exclusive, meaning only one project can be selected.
Use of Present Worth
• Consistent Valuation: Currency values fluctuate over time, meaning that cash flows from
different periods aren’t directly comparable. For example, an investment of ₹1,000,000 in
2014 does not hold the same value as an equivalent amount in 2024 due to inflation and
time value differences.
• Decision Standardization: By converting all cash flows to a common point in time,
projects can be evaluated based on their economic value today, enabling standardized and
accurate comparisons across alternatives.
The Present Worth Method translates future cash flows of a project back to “time zero” (typically
the base period or current year) using a discount rate (rate of interest). By comparing these present
values, one can identify the project with the least cost or the highest return.
Key Decision Factors in Present Worth Comparisons:
1. Minimization of Costs: If the goal is to choose the most cost-effective option, select the
alternative with the lowest present worth.
2. Maximization of Profit: If the aim is to maximize returns, choose the project with the
highest present worth.
Assumptions in Present Worth Comparisons:
All cash flows (both inflows and outflows) are known.
• The period and rate of interest are given.
• The value of money remains constant over the time period.
• Calculations are based on pre-tax cash flows.
• Intangible factors are not considered in the decision.
• Fund availability is not a limiting factor in project selection.
If the benefit cost ratio is greater than 1 (i.e., the benefits are greater than the costs), then the
project should be accepted. If it is less than 1, then the project should be rejected.
2. Profitability Index
The profitability index (PI) for a project is slightly different from the cost benefit ratio, since it
considers costs and benefits on an annual basis and incorporates the capital investment cost of
project separately. Again, the costs and benefits associated with the project must all be considered
at their present values.
As with the benefit cost ratio, if the PI is greater than 1, the project should be accepted. Otherwise,
the project should be rejected.
Comparing Multiple Projects
In case of performing cost benefit analyses to find the best alternative for the expansion of an
existing airport. Five alternatives were considered, which returned benefit cost ratios of 1.2, 0.8,
1.15, 1.3, and 0.95. One might assume that the alternative with the 1.3 benefit-cost ratio is the best
alternative, since it has the highest ratio. However, the best approach in this situation is to use an
incremental analysis technique, consisting of the following steps:
1. Eliminate any alternatives with benefit-cost ratios less than 1.
2. Arrange the remaining alternatives from lowest cost to highest cost.
3. Compute the incremental differences from the paired alternatives.
4. Compute the benefit cost ratio again based on the incremental benefits and costs.
5. Compare the chosen alternative to the next alternative.
This technique is best demonstrated using an example. Let’s look at the airport expansion example
from above, but in greater detail. Using the data provided below, let’s walk through the steps of
this analysis.
Initial Benefit/Cost
Alternative Benefits Costs
Investment Ratio
A ₹10,00,000 ₹48,000 ₹40,000 1.2
B ₹15,00,000 ₹48,000 ₹60,000 0.8
C ₹8,00,000 ₹40,250 ₹35,000 1.15
D ₹12,50,000 ₹58,500 ₹45,000 1.3
E ₹7,50,000 ₹33,250 ₹35,000 0.95