NEC4 Compensation Event and Delay Analysis
NEC4 Compensation Event and Delay Analysis
(a) Detailed Discussion of the Compensation Event Claim Mechanism under NEC4
ECC (Priced with Bills of Quantities)
Introduction
A Compensation Event (CE) under NEC4 Engineering and Construction Contract (ECC)
occurs when an event affects the cost or completion date, entitling the contractor to time
and/or cost compensation. Option B (Priced with Bill of Quantities) governs situations where
the contractor is paid based on quantities measured from the drawings.
Key Clauses:
Clause 60: Identifies Compensation Events.
Clause 61: Notification of the event.
Clause 62: Submission of quotations.
Clause 63: Assessment of compensation.
Clause 64: PM's assessment if the contractor fails to notify.
Clause 65: Agreement or revision of quotation.
Clause 66: Implementation of agreed CE.
Compensation Event Process:
1. Identification of the Event (Clause 60)
o Events that change the project scope or conditions, like weather, instructions
from the Project Manager (PM), or unexpected physical conditions.
2. Early Warning (Clause 15)
o The contractor must issue an Early Warning Notice as soon as they become
aware of a potential CE.
3. Notification of the CE (Clause 61)
o Either the PM or contractor may notify the event.
o Negotiation between parties until the final amount and time extension are
agreed upon.
7. Implementation of CE (Clause 66)
o Once agreed, the CE is formally implemented, adjusting the contract price and
Completion Date.
Flowchart Diagram:
Compensation Event Occurs
↓
Early Warning Notice (Clause 15)
↓
Notification of CE (Clause 61)
↓
Submission of Quotation (Clause 62)
↓
PM's Assessment (Clause 63)
↓
Agreement or Revision (Clause 65)
↓
Implementation (Clause 66)
Conclusion:
The Compensation Event mechanism ensures that contractors are fairly compensated for
unforeseen circumstances. Compliance with the notification and submission timeline is
crucial to avoid forfeiting entitlements.
(b) Methods to Determine the Amount of Delays
Introduction:
Construction delays can significantly impact project costs and timelines. Determining the
amount of delay requires accurate analysis techniques, particularly in complex projects.
Key Methods:
1. As-Planned vs. As-Built Analysis:
o Compares the original program (as-planned) with the actual completion record
(as-built).
o Identifies variances and causation.
4. Window Analysis:
o Breaks the project into smaller time frames (windows) and examines delays in
each window.
o Helps isolate specific periods of delay.
Conclusion:
Selecting the appropriate delay analysis technique depends on the project's complexity,
available records, and the type of delay (prospective or retrospective). Proper application of
these methods aids in accurate delay quantification and justifiable claims.
Question 5 (a): NEC4 Compensation Event Claim Mechanism (Priced with Bills of
Quantities - Option B)
(17 1/3 marks)
Detailed Discussion
The NEC4 Engineering and Construction Contract (ECC) is designed for proactive project
management, and its Compensation Event (CE) mechanism is central to managing change
and its consequences on time and cost. Under Main Option B (Priced contract with Bill of
Quantities), the CE process follows core clauses 60-65, with specific nuances for how cost is
assessed.
1. What is a Compensation Event?
Clause 60.1 lists events that, if they occur and are not due to the Contractor's fault, can lead to
changes in the Prices and/or the Completion Date/Key Dates. Examples include:
Project Manager (PM) giving an instruction changing the Scope (60.1(1)).
Employer not allowing access to the Site by the access date (60.1(2)).
PM or Supervisor not replying to a communication within the period required
(60.1(6)).
Physical conditions which are found to be significantly different from what an
experienced contractor would have expected (60.1(12)).
A weather measurement meeting conditions in Contract Data (60.1(13)).
Prevention events (60.1(19)).
2. Notification of Compensation Events:
Timely notification is crucial.
PM Notification (Clause 61.1): The PM notifies the Contractor of a CE if it arises
from the PM or Supervisor giving an instruction, changing an earlier decision, a
certificate, or a notification. The PM also instructs the Contractor to submit
quotations.
Contractor Notification (Clause 61.3): The Contractor notifies the PM of any other
event it believes is a CE, if the PM has not already done so. This notification must be
given within eight weeks of the Contractor becoming aware of the event. Failure
to do so means the Contractor is not entitled to a change in Prices, Completion Date,
or Key Dates, unless it was an event the PM should have notified under Clause 61.1
but did not. This eight-week rule is a critical time-bar.
Early Warning (Clause 15): While separate, matters raised in early warnings may
later become CEs.
3. PM's Response to Contractor's Notification (Clause 61.4):
Within one week of the Contractor's notification (or longer if agreed, but no longer than the
period for reply), the PM replies, stating:
If it is a CE (and instructing quotations).
If it is not a CE (with reasons).
If the event arises from the Contractor's fault.
If it is time-barred under Clause 61.3 (unless the PM should have notified it).
If the PM fails to reply as required, the Contractor may notify the PM of this failure.
If the failure continues for a further two weeks, the notified event is treated as a CE
and an instruction to submit quotations (Clause 61.6).
4. Quotations for Compensation Events (Clause 62):
Submission (Clause 62.3): The Contractor submits quotations for the CE within three
weeks of being instructed to do so by the PM (or an agreed longer period). The
quotation includes proposed changes to the Prices and any delays to the Completion
Date and Key Dates.
PM's Response to Quotation (Clause 62.3, 62.4): Within two weeks of the
Contractor's submission (or an agreed longer period), the PM replies by:
o Accepting the quotation.
o Notifying the Contractor that the quotation is not accepted (with reasons), and
stating the PM's assessment of the CE.
o Instructing the Contractor to submit a revised quotation.
If the PM fails to reply as required, the Contractor may notify the PM of this failure.
If the failure continues for a further two weeks, the quotation is treated as accepted
(Clause 62.6).
5. Assessment of Compensation Events (Clause 63):
Effect on Prices (Clause 63.1): The change to the Prices is assessed as the effect of
the CE upon:
o The actual Defined Cost of work already done.
Defined Cost (Option B - Clause 11.2(23)): Under Option B, Defined Cost is the
cost of components in the Short Schedule of Cost Components (SSCC) for work done
by the Contractor and its Subcontractors, less Disallowed Cost (Clause 11.2(26)).
BoQ and Option B (Clause 63.13): Changes to the Prices are assessed using Defined
Cost. If the CE means a quantity in the Bill of Quantities for work yet to be done is
incorrect, the Prices are reduced if the quantity is reduced, or the BoQ is treated as
ambiguous if the quantity is increased or the item is omitted. The PM corrects the
BoQ. The effect of the CE is the change in Defined Cost due to the corrected BoQ.
This means rates in the BoQ are not automatically used for valuing changes; Defined
Cost (SSCC) is the basis.
Effect on Time (Clause 63.5): Delay to the Completion Date is assessed as the length
of time that, due to the CE, planned Completion is later than planned Completion as
shown on the Accepted Program current at the dividing date (the date of the
instruction or notification that constitutes the CE).
Assumptions (Clause 63.10): Assessments assume the Contractor reacts competently
and promptly, and that any Defined Cost and time due to the Contractor's fault are not
included.
6. Project Manager's Assessment (Clause 64):
If the PM decides the Contractor has not assessed a CE correctly (e.g., incorrect quotation,
failure to submit), or if the Contractor has not submitted a quotation, the PM assesses the CE
themselves (Clause 64.1) using their own forecast of Defined Cost and impact on time.
Flowchart Diagram of NEC4 CE Claim Mechanism:
This mechanism aims for proactive and contemporaneous management of change, with clear
timelines and consequences for non-compliance, promoting collaboration while protecting
both parties' interests.
Bremer Handelgesellschaft
(Reiteration) Foundational for establishing and enforcing
mbH v Vanden Avenne-
CPs if clearly worded.
Izegem PVBA [1978]
Multiplex Constructions
6. Conditions (UK) Ltd v Honeywell If contract requires notice in a particular way, parties must
Precedent & Time- Control Systems Ltd (No 2) comply; actual knowledge may not be a substitute.
Bar Clauses [2007]
Carillion Construction Ltd v Adjudicators must do their best in limited time; complexity
Devonport Royal Dockyard or volume of material doesn't necessarily invalidate
Ltd [2005] decision if fair process followed.
7. ADR
Court can penalize a winning party on costs for
(Alternative Halsey v Milton Keynes
unreasonable refusal to engage in ADR (e.g., mediation).
Dispute Resolution) General NHS Trust [2004]
Outlined factors for "unreasonable."
1. NEC4 CE Definition & 60.1 (lists CEs like PMIs, access issues, physical
Compensation Examples conditions, weather, prevention)
Events
Early Warning 15.1 (duty to warn), 15.2 (register), 15.3 (meetings), 63.7
Obligations (assessment if no EW)
Assessment (Time 63.1 (Prices: Defined Cost + Fee), 63.5 (Time: delay to
& Cost) planned Completion), 63.10 (assumptions), 11.2(23)/(25)
(Defined Cost), Short/Schedule of Cost Components
4. Delay Contractual Basis 31.2, 31.3, 32.1 (Programme requirements, updates), 63.5
Analysis for Analysis (assessment against Accepted Programme)
Techniques
JCT 2016 EOT - Notice 2.27.1 (Ctr "forthwith" notice of likely delay), 2.27.2 (Ctr particulars
SBC Claim Requirements "as soon as practicable")
Process
EOT - Relevant Events 2.29 (lists Relevant Events, e.g., Variations, A/CA instructions,
exceptionally adverse weather, impediment by Employer, statutory
powers)
EOT - Entitlement & 2.28 (A/CA assesses EOT if Relevant Event causes delay beyond
Assessment Completion Date)
3. JCT Site Possession / 2.5 (Employer to give possession), 2.29.6 (Relevant Event:
Employer Deferment deferment of possession)
Risk Events
Variations (Employer 5.1 (Definition of Variation), 2.29.1 (Relevant Event: Variations),
Instruction) 4.24.1 (Relevant Matter: Variations)
A/CA Delayed 2.29.3 (Relevant Event: delay by A/CA in info), 4.24.5 (Relevant
Info/Instructions Matter: delay in receipt of info from A/CA)
4. Delay Contractual Basis for 2.28 (A/CA "fair and reasonable" EOT assessment)
Analysis Analysis
6. JCT Loss/Expense 4.23.1 ("provided always that... as soon as... apparent" - generally
Conditions Notice as CP held as CP)
Precedent &
JCT EOT Notice 2.27.1 ("forthwith" notice - generally not a strict CP barring all EOT
Time-Bars
(General Status) entitlement, but breach can have consequences)
7. ADR JCT Dispute Section 9 (as above: Negotiation, Adjudication, then Arbitration or
(Alternative Resolution Hierarchy Litigation as per Contract Particulars)
Dispute
Statutory Adjudication Housing Grants, Construction and Regeneration Act 1996 (HGCRA)
Resolution)
(Context) (as amended) - applies to "construction contracts" in UK.