Thundar PLC
Thundar PLC
PHONE: +25140151515
ARBAMINCH, ETHIOPIA
MAY 2025
TABLE OF CONTENTS
1. EXECUTIVE SUMMARY 4
2. INTRODUCTION 6
3. MINING SECTOR IN ETHIOPIA 7
4. THE BUSINESS LOCATION 8
4.1 South Ethiopia 8
4.2 Influence area 10
5. PROJECT RATIONAL 10
6. PROMOTER BACKGROUND 11
7. SWOT ANALYSIS 12
7.1 Strength 12
7.2 Weakness 12
7.3 Opportunity 12
7.4 Threat 13
8. VISION MISSION AND VALUES 13
8.1 Vision 13
8.2 Mission 13
8.3 Keys to Success 13
9. OBJECTIVES AND STRATAGIES 14
9.1 Marketing objectives and strategies 14
9.1.1 Marketing objectives ...........................................................................14
9.1.2 Marketing Strategies 14
9.2 Financial objectives and strategies 15
9.2.1 Financial objectives 15
9.2.2 Financial strategies 15
10. PROJECT DESCRIPTION 15
11. PROJECT LOCATION 16
12. NATURE OF THE DEPOSIT 17
12.1. Resource evaluation 17
12.2 Reserve estimation 18
12.3 Life time 18
13. PRODUCTION PROCESS 19
13.1 Pre-mining activities 19
13.2 The mining activities 19
DOLOMITE MINING & PROCESSING MINING AND PAGE 2
PRODUCTION PROJECT
14. PRODUCTION PROGRAM 21
14.1 Capacity 21
14.2 Production Program 21
Table 2. Production at attainable capacityin ton ......................................................21
15. MARKET ASSESSEMENT 22
16. ORGANIZATION AND MANAGEMENT 23
16.1 Organizational structure 23
16.2 Man power requirement with qualification 24
17. IMPLEMENTATION SCHEDULE 24
17.1 Pre-implementation phases 24
17.2 Logistic procurement and mobilization phase 24
17.3 Operation phase 24
18. ENVIRONMENTAL ASPECTS OF THE PROJECT 26
19. FINANCIAL ANALYSIS 27
20. DEPRECIATION 31
21. WORKING CAPITAL 32
22. PROJECT INVESTMENT OUT LAY 33
23. FINANCIAL RESULTS 36
The proposed project intends to setup in south Ethiopia Gamo zone Arbaminch Town and will be
able to produce 15,000 tons of Dolomite powder per year. The Rated plant capacity is 10,000 tons
of Dolomite powder per annum working on 8 Hours single shift. The plant will have the capacity
to operate in double shifts, producing 20,000 Tons of Dolomite powder
The company proposes to establish a dolomite mining & processing project in Arbamich town, Gamo
zone ,south Ethiopia region so as to utilize the abundant of Dolomite resources in the area. At full
capacity operation, the plant is capable of manufacturing 150,000 tons of processed dolomites per
annum. The project is proposed to required 30 hectares of land /mountain Area for its Quarrying
activities while another 5 hectares of land will be required for its processing plant at Arbamich Town.
In an effort to promote economic growth and diversify production, the Ethiopian government,
which officially pursues a market led economic policy, has taken various policy measures and
provide several incentives to encourage and promote private investment.
Dolomite mining & processing is a metal with increasing demand on the global market mainly
for its application in dolomite mining & processing ion battery for electric cars. Ethiopia has a
potential for dolomite mining & processing deposits related with pegmatite’s but also dolomite
mining & processing brine deposits may be expected in the country. However, Ethiopia has huge
mineral resources deposit, so far little has been done to systematically product the minerals due
to the expensive nature of exploration and limited number of local skilled man power.
Thus, by assessing the mineral deposit and the growing demand for dolomite mining &
processing product internationally, the envisaged dolomite mining & processing mining and
production project is designed by one dynamic, well experienced and trained female
entrepreneur named Thunder BCLT trading PLC who is currently engaged in precious and
industrial mining production and export business in different parts of the country. The project is
planned to mine dolomite mining & processing in South Ethiopia, Gamo Zone Arbaminch town
Administration.
The project will be executed through establishing partnership with local community who are
living at the proposed project site. As per assessment made in the area, the selected site has huge
and high grade dolomite mining & processing. The project will produce 86,400 ton of dolomite
mining & processing product annually at full production capacity
According to the market assessment, the envisaged business will have adequate and dependable
market throughout the project life due to the growing demand for industrial minerals of which
dolomite mining & processing is one of the most demanded minerals internationally due to its use
as a major raw material in the production of electric car battery and other products.
The perfect combination of the promoter capability and commitment, the huge deposit in the
country, the marketing arrangements together with the support from concerned governmental
offices shall create an environment for successfully managing the business.
The project, in addition to its financial viability and benefits, it is economically and socially
acceptable. The envisaged project adds value and generates production exchange to the nation over
the life of the project. The implementation of the project will also provide permanent job
opportunity for 37 local people.
Hence, the envisaged dolomite mining & processing product mining and production project is
designed by W/O Amasu Kena Wayes to engage in dolomite mining & processing mining,
production and export business through establishing legal partnership with local community who
are living at the proposed project area and commence the mining and production activates that
generate product currency to the nation and benefit the local community.
The GTP II major goal is to realise the national vision of becoming a lower middle-income
country by 2025 - achieved by sustaining rapid broad-based and inclusive economic growth,
which accelerates economic transformation. The GTP II outlines the Government of Ethiopia’s
deliberate interventions to increase the mining sector’s revenues to USD3.7 billion by 2025. This
includes strengthening the implementation capacity of the Ministry and regional states,
attracting reputable and competent investors by undertaking international standard promotion
work and funding the provision of reliable geological survey data.
To achieve this, the GoE has will drive an import-substitution agenda by developing minerals
that can be used as inputs for local industries and value-addition. Bio-fuel production and
promotion of the downstream petroleum industry will also be prioritized. Reducing
environmental impact of the sector will be central as will setting standards and regulations in
fuel extraction, blending, storing, transporting and distribution processes in the country.
Systematic mineral exploration in the country started in the 1970’s leading to the discovery of
many metallic mineral deposits (example, gold and tantalum) and industrial raw materials for
manufacturing of cement, ceramics, glass, fertilizer, etc. Exploration for fuel (natural gas and
oil) and energy (coal and geothermal energy) occurrences has been conducted back in the late
1940s and are still under investigation. Little is known to date about the occurrences of gem
minerals, but prospecting is underway by the private sector.
Currently, mining companies are engaged in the exploration for further gold and base metal
occurrences in different regions of the country. There are also several local and product private
companies mining marble, granite, amphibolite’s, opal dolomite mining & processing , and
limestone in various parts of the country.
Ethiopia’s mining sector has undertaken a major reform program in recent years. The reform is
designed to make it easier than ever to invest in Ethiopia, encourage exploration and mining, and
unlock the sector’s full potential and value. The reform includes geo data management,
transparency and ease of licensing process and the artisanal mining sector among others.
Metallic minerals include gold, which is the most developed with a huge potential of exploration.
A proven reserve of natural gas, in the amount of 12.6 trillion CC, has been found which is ready
for commercial exploration, whilst deposits of platinum (and other PGE), tantalite, iron, copper,
lead, zinc, nickel and other base metals do exist. Petroleum and gemstones have also been
identified. Industrial and construction minerals such as precious minerals , feldspar, mica,
kyanite, kaolin, talc, chromites, graphite, magnesite, industrial olivine, marble, and granite,
potash, rock salt, soda ash, sulphur, silica sand, diatomite and bentonite have been identified and
some are under production.
Such mineral wealth, in combination with a skilled and highly motivated workforce guarantees a
thriving and profitable mining sector. The Mining Proclamation recognizes the significant role
of private investment in capital formation, technology acquisition and marketing of minerals.
Ethiopia’s mining sector has undertaken a major reform programme in recent years. The reform
is designed to make it easier than ever to invest in Ethiopia, encourage exploration and mining,
and unlock the sector’s full potential and value. The reform includes geo data management,
transparency and ease of licensing process and the artisanal mining sector among others.
As a result of the conducive fiscal and legislative environment, the country is now enjoying the
participation of both product and local investors in exploration and mining. The Ministry of
Mines and Energy has granted hundreds of exploration and mining licenses for product
investors, joint venture and domestic investors and companies.
Intensive exploration programs are also being conducted for oil and gas, precious stones such as
diamonds and sapphires and other gemstones in different parts of the country. Product
companies already investing in Ethiopia’s mining sector come from all over the world including
the UK, China, South Africa, Canada, USA, Guyana, Italy and Norway. In 2012 product
investment in the mining sector reached to US$ 1billion.
Geographically, the project area, South Ethiopia, Gamo Zone Arbaminch townadministration lies
within 9 0 27' and 49 0N latitude and and 41 0 38' and 21 0 19'E longitude. The zone of South
Ethiopia ,Gamo Zone Arbaminch town is found at a distance of 501 kms far from Addis Ababa to
the East and 306 kms far from Djibouti to south directions by road. The proximity to Djibouti
made South Ethiopia ,Gamo Zone Arbaminch town outlet for export and inlet to import for the
eastern part of the country. Neighboring regions of South Ethiopia ,Gamo Zone Arbaminch town
are the South west region in the North and West, and Sidama region in the East and South
directions
The climatic condition of the Administration is characterized mainly by warm, dry climate with
relatively low level of precipitation. In general, the Administration is found within low moisture
zone. The rainfall pattern of the Administration has a bimodal characteristic. The small rainy
season is from March to April, while the big rainy season extends from August to mid-September.
The average annual rainfall of the Administration is over 604 mm.
The pattern of the rainfall distribution of the Administration is influenced by two major factors.
The first one is the periodic dislocation of the ITCZ (Inter Tropical Convergence Zone) at a global
level, which is responsible for the seasonal difference in the amount of rainfall received. The second
factor is the Monsoon winds originating from the southern Indian Ocean.
Topographic nature of the land has also a significant role in determining microclimatic variations
within relatively small distances. Thus, the mean annual rainfall along the southern uplands of
the Administration is 850 mm, while that of the low-lying areas is not product than 500 mm. The
temperature of the Administration can in general, be characterized by a high temperature
throughout the year with minor seasonal variations. The mean annual temperature is about
24.8°C. The average maximum temperature is 31.4°C, whereas the average minimum temperature
is 18.2°C. The season for high temperature starts at mid-January and extends to the beginning of
October. On the other hand, the season for low temperature is from October to mid-January. All
the rivers found in the Administration are seasonal and with short duration flood, practically
without base flow. The mean annual runoff values estimated for different watersheds in the DDA
ranges from 12.4 Mm3 to 100.13 Mm3.
AMASU KENA DOLOMITE MINING & PROCESSING MINING PAGE 9
AND PRODUCTION PROJECT
South Ethiopia ,Gamo Zone Arbaminch town Administration is one of the two urban dominated
chartered administrations in Ethiopia. It has its own Charter established by Proclamation No.
416/2004. The zone is divided into 9 Kebeles that are the lowest administrative units. The
Administration has executing and implementing it’s municipal and state functions though its
formally established institutions. There product, it is facilitating, supporting and enabling the
investment and development initiative of the administration through its institutions and related
legal and organizational instruments.
The roles of the Administration are to keep peace and safety for the public and for developers of the
area. There product, peace and security/safety of visitors are crucial to tourism like any entities of
the Administration. The safety and security situation of the zone is found in a stable situation.
There product, the situation is conducive to promote investment in relation to hotel and related
areas of investment.
Regarding the social situation and characteristics of the population, South Ethiopia ,Gamo Zone
Arbaminch town serves as a home for people from nearly all parts of the country. According to the
Population Census Report of 2007 prepared by CSA, the population of the zone consists of people
from nearly all ethnic groups of the country. Of these groups, the Oromo, Somali, Amhara and
Southern Nations and Nationalities, Peoples constitute the larger composition in their population
size.
The general demographic situation of South Ethiopia ,Gamo Zone Arbaminch town shows that
there is a fast population increase both from natural and migration causes. The prospect for the
speeding-up of the momentum of the population growth of the zone in the future is also higher as
the size of the young age population at present dominates its population structure. The total
population of South Ethiopia ,Gamo Zone Arbaminch townAdministration, as of July 2011, was
projected to be 377.000. From this, the population of the urban was projected to be 256,774, in
the same year.
The administration has launched different rules, regulations, development frame works and
related enabling basis to improve the overall development initiatives including the private sectors
involvement in investment ventures. The promulgation of investment rules and guidelines,
establishment of land development and management operational arrangements, elaboration of
It is obvious that investment is the prime driving force to any development endeavor. Its
effectiveness also rests on the capability, competitiveness and innovativeness of the private
ventures. Recently, the role and share of private investment is growing in South Ethiopia, Gamo
Zone Arbaminch town. Especially the manufacturing sector has an important role to restproduct
the zone’s previous contribution and to accommodate the growing need as a major center.
South Ethiopia ,Gamo Zone Arbaminch towninfluence areas include Harari National Regional
State, Somali National Regional State, East and West Hararghe Zone of Oromia National
Regional State.
Thus, South Ethiopia ,Gamo Zone Arbaminch townis the ideal location for the envisaged precious
and industrial minerals as it is in close proximity to the principal raw materials and access to
product market. The town has another advantage because of its well-developed infrastructures,
manpower and financial institutions required for the business.
5. PROJECT RATIONAL
Proper resource utilization is among the many strategic approaches that help to ensure
sustainable development to be practical. On the other hand, the ability of private sector both in
financial & technical terms to utilize the available resource for development is the other existing
crucial problem that hampered the economic growth of the nation. More product, as
development is an intertwined process requiring input that greatly satisfies the needs in
properly planed and regulated manner, extraction of resource is indispensably to be carried to
maximize revenue for the owners and the government as well.
Beside on this presumption, the need to build development capacity is the other relevant and
most important factor to get attention. This means the weakened ability of capital formation is
one of the most important attentions seeking area boost growth in the economy the reproduction
AMASU KENA DOLOMITE MINING & PROCESSING MINING PAGE 11
AND PRODUCTION PROJECT
capacity which increase additional injection of capital in the economy which is expected to be
intersected by the private sector. In relation to the proposed project this has remarkable meaning
in the area for further utilization of the available resource, which could gradually appear when
the capacity to perform grows.
On top of these the current development policy of the Government both at the national and
regional level has pave the way for any domestic and product investor to participate in the
development process of which they assumed to be beneficial to them and to local people both in
terms of profit and job creation .
In pertinence to the growing demand for raw materials and source of energy locally and
internationally, the demand for minerals in general and dolomite mining & processing product
in particular is expected to grow with high elastizone. However, except few minerals, there is no
strong effort that has been made to use locally available natural resources to use neither as
source of product currency and generate product currency nor use locally source of raw materials
for locally available industries.
Their product, based on the assessment made by the promoter, the envisaged dolomite mining &
processing product mining and production project is selected to engage in mining and production
of dolomite mining & processing mineral to productign market in the first phase and also to
process the dolomite mining & processing product and benefit the promoter and the country
accordingly.
Product over, the promoter has long years of experience, good truck of record and reputation in
mineral exploration and mining sector. It is with the productgoing background that promoter,
decided to engage in dolomite mining & processing mining and production business.
This project proposal is there product, designed to engage in dolomite mining & processing
mineral mining and production business in partnership with local community where the mineral
resource is found.
6. PROMOTER BACKGROUND
The promoter, Thunder BCLT trading PLC , is a dynamic, well experienced and trained
female entrepreneur. She has a master degree in leadership field from lead star university and
AMASU KENA DOLOMITE MINING & PROCESSING MINING PAGE 12
AND PRODUCTION PROJECT
currently she is engaged in different business lines mainly in mining, export, trading and other
investment activities. The promoter has also attained short term training on gemstone
identification and introduction to Lapidary to in order to do the mining business professionally
and successfully.
The promoter has gained practical experience and skills of doing successful business in precious
and industrial minerals mining due to her professional background and commitment. The
promoter has mproduct than one decade of experience in delivering and managing various
types of business activities. The major business lines she has engaged in include precious mineral
mining and production, coal mining, legumes, spices, beans and high value crops trading and
export business.
Due to the growing demand, export potential and the benefit to be generated, the promoter is
committed to engage in industrial mineral mining and production business that generate
production currency to the nation and also benefit local community through working in
partnership with local community who are living at the project site.
The mission of the promoter is always to look for opportunities to grow the business using
proven skills to create value in the mining sector of which Ethiopia is endowed with huge and
untouched potentials. Ethically, the promoter shall conduct its business in a fair manner and in
such a way to enhance its reputation both in the business and community.
Hence, the promoter has the required educational back ground, good entrepreneur skill and long
years of practical experience in running and managing any mineral mining and production
business in general and precious minerals in particular due to her long year of experience and
engagement.
7. SWOT ANALYSIS
7.1 Strength
7.3 Opportunity
7.4 Threat
8.1 Vision
The vision of the promoter is to engage in the precious and industrial minerals mining, production
and export business and generate production currency to the nation. .
8.2 Mission
The mission of the promoter is to become the leading precious and industrial minerals miner,
producer and exporter in Ethiopia.
In descending order of importance, the five critical keys for the success of the envisaged dolomite
mining & processing mining and production business are:
The product objective of business is to mine dolomite mining & processing mineral in
partnership with local community and produce dolomite mining & processing product for
export so as to generate production currency to the nation, generate income to local community
and create job opportunity.
Taking into account the vision, mission, strength, weaknesses, opportunity and threats, the
promoter has designed the following marketing and financial objectives and strategies to be
achieved.
In order to achieve the above listed marketing objectives, the strategies designed to be
implemented by the promoter are:
1. Establish strong business relation with local administration and stake holders
The envisaged project is designed to mine and produce dolomite mining & processing product
for export purposes. The project mine the dolomite mining & processing and supply the raw
dolomite mining & processing (the product) to the international market since dolomite mining
& processing is an essential component of clean energy technologies, from electric vehicles to
the big batteries used to product electrizone at power plants. It is an abundant mineral, but to
be used it must be extracted from the earth and processed.
As per the requirement set by the local administration, the planned dolomite mining &
processing mining and production project will be executed in partnership with local
community. Hence, project is designed to mine and produce dolomite mining & processing
product and supply the product to production market so as to generate production currency to
the nation.
To realize the dolomite mining & processing mining and production business, all the required
man power, machineries and equipment’s, civil works and related activities will be in place in
order to commence the mining and production of the product. There product, this project is
aimed at mining dolomite mining & processing from the source, produce the required dolomite
mining & processing product as per the buyer’s standard and exports the product to product
market.
Thus, the envisaged business is designed to mine dolomite mining & processing product,
AMASU KENA DOLOMITE MINING & PROCESSING MINING PAGE 18
AND PRODUCTION PROJECT
transport to the collection site, and finally to export the product to product market. In doing this
business, the promoter will work in partnership with local community.
Since choice of mining location is one of the important factor that affect its viability and success,
the location of the proposed dolomite mining & processing mining and production project is
selected after careful evaluation of different location. Hence, South Ethiopia ,Gamo Zone
Arbaminch town Administration is selected as the site for the implementation of the envisaged
mining and production of dolomite mining & processing due to the availability of the product,
raw materials, especially in the required quantity & quality, good access to market, well
developed physical & economic infrastructures.
Hence, the envisaged dolomite mining & processing mining and production project is planned to
be established in South Ethiopia ,Gamo Zone Arbaminch town Administration within the
boundary of Melekakero Rural Kebele which is 80 kilometer away from South Ethiopia ,Gamo
Zone Arbaminch town.
The total area required as mining site and product collection site is estimated to be 50,000 square
meter land. The project area is served with all weather gravel road and it has relatively well
developed infrastructure facilities due to its proximity to South Ethiopia ,Gamo Zone
Arbaminch town.
No X axis Y axis
1 04206075 0937044
2 04205970 0937049
3 04206055 0937223
4 04205705 0936139
Zanettin (1997) divided the tertiary volcanic of central Ethiopians in three stages of volcanism
and tectonics, where the first transitional (theproducttic) flood basalt followed by alkali hyalite
and ending with alkali basalt. At first the volcanism has occurred on a large elongated basin.
The outer part of the basin was uplifted and deep eroded (Peniplanation of Ashangi). During
this stage the volcanism dies out on the uplifted area.
At this stage strong extensive crusal movement occurred causing the renewal of volcanism
which defines finally the escarpment. Volcanism finally changed radically from fissure (lajie
rhyolite and Alajie basalt) to central type (Tarmaber- megezex basalt). This all from the south
western afar and the proto-Ethiopian rift followed by uplift and erosion. The area is characterized
by diverse volcanic rocks where basalt extrusion are inter spread with large accumulation of
pantellerituc hyaliies and hrachyte, comprising flows, breccias, ignimbrites and relate shallow
incisive rocks. The area situated south and southeast of Addis Ababa is covered by Pliocene to
plesitocene alkali basalt and terabyte lava flows. South Ethiopia ,Gamo Zone Arbaminch
townCompresses rocks ranging in age from to tertiary vocalic. The tertiary colcanscs represent
of the areas and comprises of aphantic, pyroxene- phyric, plagioclase- phyric.
Although there is no study conducted regarding the volume of deposit. the area is expected to
have huge deposit of dolomite mining & processing product.
The geologic features that might affect the quality of the dolomite mining & processing product include:
Physical conduction: vesicular (voids). Curvaceous nature, sacrificial
weathering, mechanical crushing (very local), soil horizon development
(over burden). etc
Chemical weathering: development of secondary minerals such as zealot,
calcite, different clay minerals etc.
Though no drilling has been done on the project site to determine the depth of the deposit, minor
geological mapping was done in the area for the preliminary estimation of the reserve. The
minimum and average thickness of the deposit common to all the area under concession is taken
and is calculated using the polygon’s method.
As the deposit is assumed to be horizontally bedded, the thickness of the deposit can be
calculated by taking the difference between the altitudes at the tip and bottom of the deposit
beside observing the deep valleys around to calculate the average depth of the basalt, the main
methodology used to determine the depth of the deposit is the quarry mined befproduct round
the area.
The life of the project depends on the annual production capacityof the project. Hence, the
following parameters are considered in calculating the project life.
There product, the volume or reserve of deposit is computed to be 40,000m 2X50mX0.95 which
is 1,900,000m3. Based on the 70% effective production capacityof the 300 tone/day, 8 working
hour/day, 288 working days/annual, starting production with 70% of the effective production
capacityand increase by 10% each year to attain 80% capacityon third year and 90% at fourth
year which is full capacity. Thus, with a total reserve amount 1,900,000 m3 the project will have
a mine life of 14 years. Mean while the project is designed to consume this reserve deposit within
AMASU KENA DOLOMITE MINING & PROCESSING MINING PAGE 22
AND PRODUCTION PROJECT
the above mentioned project life.
Pre- mining activities are essential activities that have to be executed in order to produce the raw
products successfully. The pre mining activities include:
By considering all these factors, the following mining parameters have been recommended for the
quarrying of dolomite mining & processing product under consideration.
In this case the preferred option to develop this quarry site is initially to work the entire
thickness of the deposit stating from its foot at the South West and gradually establish a multi-
bench system advancing towards the North East in such a way that the lower bench lagging
behind the upper working benches.
The sized of quarrying machineries, such as wheel loaders/ excavators to be deployed for the
excavation and loading of resources and the number of dump trucks to be used for transportation
of should be synchronized in order to assure that materials from the quarrying site is constantly
transported to the storing continuously and efficiently. In this case, the following principal
AMASU KENA DOLOMITE MINING & PROCESSING MINING PAGE 24
AND PRODUCTION PROJECT
procedures of quarrying activities shall be followed in order to effectively achieve the physical
production plan.
The following activities will be practiced during the mining product producing operations.
Overburden Removal, site and quarry face preparation: As a starting phase of the quarry
operation, rock fragments accumulated on the ground surface will be sized and pilled to be
transported to a place where the product product . On exhausting the surface accumulations,
the leftover soil will be carefully stripped not to damage its strutted the top weathered and
loose bedrock deposit below the surface deposit will be disintegrated, in order to release the
weathering
- survived imbedded fresh fragments, which will be collected and piled, to be made ready for
transporting to the crusher plant, then the residual decomposed materials will be pushed to sides
to expose the underlying undulated bed rock and open quarry face for primary fragmentation or
excavation of the primary deposit.
The overburden stripping, loading area surface leveling and quarry face operating will be done
by bulldozer and / or excavator. Primary fragmentation or excavation and pilling. This will be
done using an excavator shovel or hack hammer fixed to excavator and human labor.
Whenever necessary, drilling will be done from position on benches to prepare weak zones along
which the rock will break by blasting in to pieces that can be loaded in to the trucks and taken to
the primary crusher. The drill utilizes a compressed air powered ‘hammer’ in the bottom of the
hole.
3. Transportation
Wheel loader and excavator to be deployed for the excavation and loading of resources and the
number of dump trucks to be used for transportation of basalt boulders should be synchronized
in order to assure that materials from the quarrying sire is constantly transported to the
crushing plant site continuously and efficiently. In this case, the following principal procedures
of quarrying activities shall be followed in order to effectively achieve the physical production
14.1 Capacity
The planned business will have a zone of producing 300 ton dolomite mining & processing per
day on the basis of one shift of 8 hours each per day and 288 working days per annum.
During the initial years, the envisaged project will not operate at full capacity . This is due to lack
of acquaintance to the work, low technical experience and market. Therefproduct, during the
initial years, the effective production capacity of the crushing plant is assumed to be 80%, then it
grow to 90% and finally the plant will operate at 100% of its the effective capacity .
At the initial stage of the production period, the project would require some years to penetrate
into the market and develop production skill. There product, in the first and second year of
production, the capacity utilization rate will be 80% and increase by 10% every two years, in the
third and fourth year the plant will produce 90% and operate at attainable capacity of 100%,
respectively.
5 to 10 90% 86,400
The fundamentals of “supply and demand” vary considerably when inventory for certain
resources, such as precious and industrial minerals, cannot be created or renewed. Scientists and
engineers agree that we have yet to discover all of the valuable uses for many of the minerals on
the earth.
This much we know is true: The existing demand for precious and industrial minerals already
exceeds the current supply or production, and population growth ensures that the incredible
demand for precious and industrial minerals is going to increase with continued population
growth (and) as the existing population enters their era of mass consumption.
Simply stated, people consume resources. These resources, especially precious and industrial
minerals, will continue to absorb unprecedented demand with very limited supply. The global
demand for precious and industrial minerals has led to the current increase in mineral values.
Take a look at the below charts. This demand will continue to exist for the product seeable future.
Add to the current demand the consumption demands of billions of new inhabitants in the
coming decades. There’s simply no way around it. Precious and industrial minerals must be
recovered to support unstoppable global growth.
There are many ways to invest in precious minerals, mainly gold and silver. Mainstream
investors purchase pure bullion; others invest in mutual funds which have positions in precious
metals. Some people prefer to purchase stocks in mining companies with promising futures or
profitable mining operations. One major investment remains as the most dynamic and
rewarding investment possible.
Investing in precious and industrial minerals comes with a significant price. Also included with
that premium is risk. You will pay spot price for the metal plus a surcharge. Mutual funds and
EFTs which also reserve positions in precious metals pay similar premiums. Next on the list of
potential investments is the purchase of stock in mining companies. You may get the stock at a
good price relative to earnings, but there is great risk in all aspects of owning a publicly held
company in the lucrative world of mining.
Organization is a means by which the operational function & activities are structured and
assigned to organizational units represented by managerial staff, supervisors and work force with
the objective of coordinating the performance and the achievement of its business targets.
The organizational structure of the proposed project is designed based on flexibility, performance,
high level of personal accountability and sharing of responsibilities as need arises and
circumstances permit. Based on the recommended number, size, and volume of activities of the
project. The project will have its own rules and regulations, which will defiantly facilitate the
smooth running of the whole production process.
The proposed project will be managed by experienced General Manager, who is responsible for the
overall activities of the venture. The plant will be organized in three units namely Administration
& finance unit, sales and promotion unit and Production & Technical unit.
Proposed Organization Structure of the Plant
The project will create employment opportunity for about 18 Skilled and unskilled workers on
permanent base. The required manpower, their qualification, profession, educational level along
with their experience is presented in the financial part of this document.
The envisaged project will take 6 months time to be implemented as per its schedules. During
this period of time, the project will pass through three consecutive implementation phases. These
are:
The pre-construction phase is decisive for the project realization and implementation phases.
Under this phase, project document preparation, legal and permit issues, site identification,
mapping the site, establishment of partnership with local community, land acquisition,
contacting with stake holders, clearing the site and related activities are the main activities to be
undertaken.
The logistic procurement and mobilization phase is mainly a stage of buying or leasing the
required earth moving equipment, vehicles, human resource recruitment, training and related
activities.
17.3 Operation phase
This is a phase where the envisaged project will start production and supply of product to the
target market. Operation phase ranges from production of the intended project output, dolomite
mining & processing product and export to the target market. The major activities are presented
in the table below.
Like any other industry, mining industry also has twin effects on human life. On the one hand,
it contributes immensely to the enhancement of comfort and living standard of man. On the
other hand, it pollutes the air and water. It has also a hazardous effect on the landscape.
Preservation of environment is one of the essential aspect with which all are concerned not
only for the survival of the present generation but also for the future generations of mankind.
Environment is the complex aggregate of external conditions that affect the life, development
and survival of all organisms. It embraces air, water, land, flora, fauna and many mproduct
factors. It is made up of biophysical and socio- economic elements.
In the case of the project under consideration, the proposed project site is situated on a
relatively stable and conducive topography. No significant human activity has been observed
on the area. The mining site is located at a considerable distance away from the settlement
areas and the existing infrastructure such as roads, high-tension lines etc. so that the
exposure of the local communities to operation is minimal.
The only possible environmental hazard that can be happened due to the operation of the
project is mining amount of dust generation. Of the whole activities of the mining, crushing
and transportation of the material may create dust. To avoid or minimize the dust,
mechanisms are devised. During hauling and crushing the material for the little amount of
dust might generate it is planned to suppress by water sprays.
In addition, during transportation of the material on the road, the controlling measures for
dust suppression are:
The product will be covered with plastic sheet
proper routes will be selected while moving near the settlements
water sprays will also be used where necessary
The area is limited to a small and narrow zone near a stream valley with little vegetation at
all; yet planting appropriate vegetation will reclaim it, as it has already been mentioned
above. Therefproduct, with the protective measures designed this project is environmentally
feasible and harmless.
No Description Expense
No Description Expense
Although the lion share of the operational work is executed by the machinery, due to the
nature of the envisaged business the project requires at least 10 daily labproductrs on daily
basis depending on work load. Thus, the annual expense of daily labproductrs is computed by
taking 10 people at a cost of Birr 300/day for the whole year.
Total 3731040
19.2.7 Insurance
Expense required to buy insurance coverage for fixed asset is assumed to be 1.5% of the value
of the fixed asset which is birr 214,532.
Total 144500
These categories of cost include repair and maintenance, spare parts and fast moving items,
travel and per diem, staffs fringe benefit, office supplies, administration expenses, supervision
and consultancy fees, and other related expense. The table below depicts the annual expenses.
No Description Month expense Annual rental
price
1 Repair and maintenance 27720 332643
Total 932643
20. DEPRECIATION
Working capital is the financial resource that is required to run the proposed project right after
the project starts production. This is computed by taking some proportion of the operating cost.
Because of the nature of the project under consideration, the project is expected to start
production after the construction and machinery erecting work is completed. Thus, two month
is considered to compute the working capital requirement of the project. Hence the working
capital required for the project under consideration is only for three month and it is estimated
to be Birr 2,000,000.
Total investment requirement of the project is estimated to be birr 30,000,000 out of which
Birr 38,000,000 will be fixed investment cost while the remaining birr 2,000,000 will be
working capital requirement. The table below shows cost summery of the envisaged stone
crushing plant.
1. Asset
2. Liabilities
3. Equity
25.2.1 Profitability
The project generates profit throughout the project life starting from the first year. A net
profit of Birr 417 million Birr will be made in the first year of operation, growing to Birr 650
million on the fifth year of operation. The income statement and the other indicators of
profitability show that the project is viable.
The investment cost and income statement projection are used to project the pay-back period.
The project generates surplus cash starting from the first year of operation. The payback
period of the project is about 1 year.
Based on the cash flow statement, the calculated IRR of the project is 35%.Since internal rate
of return of the proposed project is greater than the bank lending rate, the project is
financially feasible.
The project creates employment opportunity for about 38 people of which 18 is permanent
and the rest 20 is temporary. The project will generate Birr mproduct than 100 million over
the life of the project in terms of tax revenue. The project will create backward linkage with
the mining sub sector and forward linkage with the construction sub sector and also
generate income for the Government in terms of payroll tax.
No Description Unit
Project year
1 2 3 4 5 6 7 8 9 10
80% 80% 90% 90% 100% 100% 100% 100% 100% 100%
1 Dolomite mining & processing Ton 69120 69120 77790 77790 86400 86400 86400 86400 86400 86400
product
AMASU KENA DOLOMITE MINING & PROCESSING MINING AND PRODUCTION PROJECT PAGE 38
Annex 2. Operational Cost in Birr
2.2 Daily labproductr expenses 864000 864000 950400 950400 1045440 1045440 1045440 1045440 1045440 1045440
2.3 Raw material 1525600 1525600 1678160 1678160 1845976 1845976 1845976 1845976 1845976 1845976
2.4 Fuel and lubricant 3731040 3731040 4104144 4104144 4514558 4514558 4514558 4514558 4514558 4514558
2.6 Utilities 240000 240000 264000 264000 290400 290400 290400 290400 290400 290400
2.7 Insurance 144500 144500 158950 158950 174845 174845 174845 174845 174845 174845
2.8 Others 932643 932643 1025907 1025907 1128498 1128498 1128498 1128498 1128498 1128498
2.9 Direct cost 120000000 120000000 186000000 186000000 245000000 245000000 245000000 245000000 245000000 245000000
Total annual operational cost 129437783 129437783 196381561 196381561 256419717 256419717 256419717 256419717 256419717 256419717
Annex 3. Annual Project Revenue Estimates in Birr
N Description
Project year
o
1 2 3 4 5 6 7 8 9 10
1 Dolomite mining & 552960000 552960000 739005000 739005000 907200000 907200000 907200000 907200000 907200000 907200000
processing product sales
Total annual sales 552960000 552960000 739005000 739005000 907200000 907200000 907200000 907200000 907200000 907200000
0 1 2 3 4 5 6 7 8 9 10
1 Cash in flow
1.3 Revenue - 552960000 552960000 739005000 739005000 907200000 907200000 907200000 907200000 907200000 907200000
Total cash inflow 30000000 552960000 552960000 739005000 739005000 907200000 907200000 907200000 907200000 907200000 907200000
2 Cash out flow
2.1 Fixed investment 28000000 - - - - - - - - - -
2.2 Working capital 2000000 - - - - - - - - - -
2.3 Operating cost - 129437783 129437783 196381561 196381561 256419717 256419717 256419717 256419717 256419717 256419717