Valuing Variations in Accordance With The Principle Irish Standar
Valuing Variations in Accordance With The Principle Irish Standar
ARROW@TU Dublin
2017-10-14
Part of the Architectural Engineering Commons, and the Construction Engineering Commons
Recommended Citation
Cunningham, T. (2017)Valuing Variations in Accordance with the Principle Irish Standard Forms of
Building Contract – Worked Examples and Solutions,
This Other is brought to you for free and open access by the School of Surveying and Construction Management
(Former DIT) at ARROW@TU Dublin. It has been accepted for inclusion in Other Resources by an authorized
administrator of ARROW@TU Dublin. For more information, please contact [email protected],
[email protected], [email protected].
VALUING VARIATIONS IN ACCORDANCE WITH THE
PRINCIPLE IRISH STANDARD FORMS OF BUILDING
CONTRACT – WORKED EXAMPLES AND SOLUTIONS
Tony Cunningham
School of Surveying and Construction Management
Dublin Institute of Technology, Bolton Street, Dublin 1
Introduction
The general principles of contract law hold that once a contract has been entered into it
cannot be changed or varied without the agreement of all the parties. However, given the
nature of the construction process some change is almost inevitable. Standard forms of
contract, therefore, cater for such change by including provisions which permit variations
and alterations to the works.
Clause 2(a) of the Royal Institute of Architects in Ireland (RIAI) Contract authorises the
architect to issue instructions regarding ‘the modification of the design, quality or
quantity of the Works or the addition, omission or substitution of any work,’ that are
referred to as ‘variations’. In addition, clause 2(i) of the RIAI contract authorises the
architect to issue instructions on ‘any other matters appertaining to the proper execution
of the Contract’ (RIAI, 2012). Taken together, these provisions may broaden the scope of
variations to include both changes to the physical works and alterations to obligations
and restrictions imposed upon the contractor in other elements of the contract
documentation such as in the specification and/or bill of quantities.
The Public Works Contract Form PW-CF1 refers to variations as ‘change orders’. Clause
1.1, defines ‘Change Order’ as ‘an instruction of the Employer’s Representative to
change [including add to or omit from] the Works or to change [including impose or
remove] constraints in the Contract on how the Works are to be executed’ (Office of
Government Procurement, 2017).
Even simple changes can have significant implications and can give rise to costs such as:
1
Payment for aborted work and associated making good costs,
Cancellation of, or modifications to supply orders, loss of discount for large and
scheduled orders.
In isolation, variations are often dismissed as inconveniences and are commonly viewed
as one of the normal problem areas involved in construction. However, cumulatively or
where a series of interrelated or conflicting instructions arise, these may significantly
delay or disrupt the building programme, and result in the contractor expending
significant sums of money in reorganising and completing the contract. A common
difficulty faced by contractors is successfully negotiating the reimbursement of these
costs. The employer and consultants may think that the contractor is exaggerating the
problem or is being unreasonable, and may dispute the details of the contractor’s
variation account.
2
Forms of Contract - An Overview. http://arrow.dit.ie/beschreoth/28/. The rules
themselves, are set out in the Appendix to this study.
The RIAI Contract where quantities form part of the contract (Yellow Form)
The rules for valuing variations are set out in Clause 13 of the RIAI Standard Form of
Contract. In summary, valuations may be formulated:
2. Bill rates: Where the variation involves work of a similar character which is
carried out under similar conditions, then the valuation of the varied work is based
on bill rates.
3. Adjusted rates: Where the variation involves work which is not similar insofar as
it alters the specification, or involves working under different conditions, or
changes the quantities significantly, then the applicable contract rate(s) may be
adjusted in order to produce a ‘reasonable’ rate reflecting the additional or
reduced cost of executing the varied work.
4. Market rates: Where appropriate rates do not exist in the bill, a fair valuation of
the work should be made based on current rates for similar work in the locality.
These rates can normally be obtained from bills of quantities for similar works
and adjusted as appropriate. Price books such as Spons Irish Construction Price
Book (2008) may also be consulted as a general reference in agreeing these rates.
3
6. Omitted Work: In general omitted work is valued at contract rates. However, if the
omission is so extensive as to change the basic nature of the remaining work, then
a fair valuation shall be made of the remaining works.
Section 10.6 of the Public Works Contract Forms deals with the valuation rules
governing adjustments to the contract sum, these rules are included in the Appendix
below. The rules are similar to those contained in the RIAI contract, discussed above, but
there are subtle differences which reflect a greater emphasis on pre-costed contractor’s
proposals, and a more procedural approach to dealing with dayworks.
The pricing of variations often requires quantity surveyors to consider whether the varied
work is similar in character, conditions and quantity to that contained in the bill of
quantities or pricing document. Where this is not the case it usually becomes necessary to
adjust bill rates in order to calculate a ‘reasonable’ or ‘fair’ price for the work.
4
Example – An Introductory Exercise
A bill of quantities contains the following item:
What logic would be used by a quantity surveyor in determining appropriate rates for the
following variations?
3. The architect has instructed the contractor to repair defective plastering in the existing
building. The repairs were in small patches (typically not exceeding 1.0m2) and took
place from time to time over a six-month period. The areas involved totalled 25m2.
This variation is most readily valued by applying bill rates as the extra work is similar in
character and appears to be executed under similar conditions to those of the ‘parent’ rate
in the bill of quantities. The valuation therefore is 200m2 @ €18.00.
This variation is a different specification and therefore the work is of a different character
but it may be seen as being carried out under similar conditions to that of the plastering
rate in the bill. The originally billed and substituted work are, after all, both plastering
activities. The valuation may therefore be attempted by adjusting the billed plastering
rate. The revised rate could then be checked against current market rates or published
1
Spons Irish Construction Price Book (2008) published rates for 13mm two coat plaster at €17.80
(inclusive of 10% overhead and profit) comprising net costs of €13.05 for labour and €3.13 for materials –
a ratio approaching 80:20. Spons also reported net prices of €10.67 (€8.70:€1.97) and €16.08
(€13.05:€3.03) respectively for 12mm and 18mm thick cement and sand render. Although these rates are
nearly 10 years old, as a result of the effects of the recession prices are only now approaching those of
2008. It is considered therefore that a rate of €18.00 is indicative of current plastering rates. It is also
considered appropriate to use labour/materials ratios set out in Spons as the basis for carrying out this
exercise.
5
prices to assess whether it is ‘fair and reasonable’. The following example indicates how
a bill rate might be adapted as a basis of the valuation.
Step 1. Deduct the overheads and profit included in BQ rate. (Finding the net rate)
Assuming that the overheads are 13% and the profit is 7%,
2
The rates for materials published in Spons would indicate that the material content for 15mm cement and
sand render would be approximately €2.50. This is the same as that assumed in the analysis of the plaster
rate. No adjustment is necessary, therefore, for the relative differences in material cost between the two
specifications. An adjustment is, however, necessary for the differing thicknesses of the two specifications.
6
New net rate €18.75
Part 3. - Patching.
This is work of an ad-hoc nature and was work which was not included in the tender
documents. Although ‘patching’ rates contained on other refurbishment projects may be
tabled as a possible basis for agreement, it appears that dayworks would be the most
appropriate method for valuing this type of work.
Extensive omission of part of the work, fundamentally alters the basis on which the rates
for the particular work items were tendered. Economies of scale are lost on reduced scope
of works and fixed overheads associated with the work increase in proportion to the
extent of the reduced work. The omissions may also change the conditions under which
the work is carried out, for example, by losing continuity of work. In these instances the
remaining work is treated as if it, in itself, is a variation. An adjustment such as that
which follows may represent a fair valuation of the remaining works.
It should be noted that a quoted or an agreed valuation may be made for any or indeed all
of the illustrations.
7
Sample Questions
In answering the following questions assumptions should be stated which identify the
issues and potential outcome situations. Where appropriate, answers should contain
1. Due to design team error a reinforced concrete column has been cast in the wrong
position and the contractor has been instructed to remove and replace it.
2. A section of concrete slab must be cut out because tests show unsatisfactory strength.
3. A design change necessitates an increase in 215mm thick block walls on the ground
floor by one third.
4. Lift shaft walls on the roof of a tower block have been changed from reinforced
concrete to brickwork; rates are agreed for brickwork on the ground floor.
This situation is a change of the original design. It is therefore a variation, which will be
valued in accordance with the contract provisions. The contractor will be reimbursed for
the following:
The price of the original work at the rates contained in the bill of quantities /
pricing document.
The cost of demolishing the affected completed work and making good; as this is
unplanned work of an ‘ad-hoc’ nature the valuation will probably be based on
daywork accounts.
8
The cost of the remedial work. It is unlikely that the remedial work can be carried
out as originally planned (executed under similar conditions). The works are
likely to be out of sequence and will probably involve return visits of a number of
trades. The contractor is likely to seek a dayworks valuation for these works. It is
unlikely that an attempt to value the remedial work by adjusting bill rates to
reflect the reduced productivity would produce a ‘fair’ valuation in these
circumstances.
Loss and expense suffered by the contractor should the remedial works delay
completion of the contract or disrupt other site operations. Delay costs are usually
valued as a prolongation claim based on the time-related items included in the
contract preliminaries. Disruption claims must be proved and consequent costs are
likely to be based on daywork accounts. On public works contracts the use of the
Programme Contingency would be applied in these circumstances.
This work is not in accordance with the contract documents and therefore is not a
variation. This work must be cut out and replaced by the contractor at his own expense.
In addition, the contract must be completed within the original contract period.
On the face of it, this instruction is for additional work which is of a similar character and
is executed under similar conditions to that described in the contract, i.e. the description
of the additional work, measured in accordance with ARM4, is the same as that described
in the bill of quantities. The variation would, therefore, be valued at contract rates. (Note,
the word similar does not mean identical and it is a matter of judgement to assess whether
the conditions are, in fact, similar).
The extent of the change, however, begs the question, when do the characteristics and/or
conditions under which the works are executed cease to be ‘similar’ to those described in
the contract? If the blockwork is confined to the ground floor, it may be argued that the
9
instruction brings about a substantial increase in the scope of the works. ‘Boundary
disputes’ are common in many areas of life and a consultant QS might argue that the
variation should result in savings in the blockwork rates due to increased economies of
scale, while a contractor may argue that the increased work scope has implications for
preliminaries costs which should be reimbursed. Each situation must be judged
individually on the particular facts.
This instruction is for substituted work which is not executed under similar conditions to
those envisaged in the contract and should therefore be valued at a fair/reasonable rate
using the rates for the ground floor brickwork as the basis of the valuation.
The concrete construction is omitted at bill rates. The rates for the brickwork should take
account of the changed conditions affecting its execution. This involves work on the
tower block roof rather than ground floor and involves additional time to get labour and
materials to and from the work station. The work is also confined and in a small area
rather than the probable large areas at ground level. Similarly the work is executed out of
sequence and will probably require a return set up on site. The work is exposed at height
to the elements and may require special scaffolding.
10
Example 2 Variations under the RIAI Contract.
Explain how the following changes are valued under the RIAI Standard Form of Contract
(assume a 65 week contract).
a) The tiles for the kitchen and toilet areas are to be supplied by a nominated
supplier. They are ordered for delivery to site during week 58 and are programmed to be
fixed during weeks 61 and 62. Upon delivery, the tiles are found to be have been
incorrectly dispatched by the nominated supplier, and can only be replaced during week
63.
b) The contract is on programme at week 58 with all the internal doors fixed. The
Architect issues an instruction to remove a number of the corridor doors and frames and
replace them with acoustic door sets. Delivery of these units is quoted as 14 weeks.
In this case there is no variation. The materials delivered are, in fact, not in accordance
with the contract specification (clause 8). The architect can insist on the correct tiles and
issue an instruction ordering the wrong tiles to be removed from site and to be replaced
with the correct tiles (clause 2). In this event, the contractor must comply with the
instruction and suffer any extra costs incurred in resupplying the tiles. The contractor is
also responsible if this problem delays handover of the works. There is no provision in
the RIAI contract to extend the completion period for delay by nominated subcontractors
or suppliers. The employer may become entitled to deduct liquidated damages should the
contractor fail to complete on time. The contractor will have to recover any losses from
the nominated supplier who is ultimately responsible for the additional costs caused by
this blunder.
A more pragmatic solution however would be to approve the tiles which although
incorrect may be ‘suitable’. In this case the architect may exercise his discretion to
11
approve the tiles. Alternatively, the contractor may propose another type of tile which
satisfies the architect. This has the practical advantage of allowing the works to be
completed on time. It does, however, constitute a variation because it modifies the works.
It is likely for a credit to be sought where the substitute tile is accepted as being
‘expedient’ in order to compensate the client for possible loss of amenity. Where the
contractor proposes a superior tile specification, however, the client would not expect to
be charged extra, as the substitute tile has been proposed in order to solve the contractor’s
own difficulties.
This is a substitution of the contract works and is a variation under clause 2 of the RIAI
contract and is consequently valued under the provisions of clause 13 of the contract. The
evaluation of the variation presents a number of issues:
Abortive work. The contractor will be paid for doorsets which have already been
fixed on site at bill rates. This valuation would include other associated works
such as fixings, ironmongery, glazing and painting.
Removal of abortive work. The contractor will be reimbursed for the cost of
removing the doors and frames and making good any finishes on a dayworks
basis. Although unlikely, the ‘redundant’ doorsets may have some value to the
contractor and some credit could be obtained. Otherwise, they must be disposed
of and the contractor will be reimbursed for the disposal costs.
Substituted work. Acoustic doors cost considerably more than standard flush
doors. It is assumed there are no acoustic doors required elsewhere on the project
and, therefore, there are no rates for them in the bill of quantities. There may be a
temptation to attempt to value this instruction on the basis of interpolating rates
for acoustic doors on other projects. This may present problems, as acoustic doors
are not required on many projects, and therefore, the QS may not have an
adequate database on which to base a reliable valuation. In addition, acoustic
12
doors are often installed by firms specialising in this type of work, and it may be
that the architect may insist on a specialist to carry out the work.
Given the specialist nature and the urgency of these works it is likely that a price,
based on a specialist’s quotation would be negotiated and agreed. This may well
be on the basis of dayworks if no agreement can be reached beforehand. If it is
decided to appoint a nominated subcontractor to carry out the work, the contractor
will be entitled to add for profit, and the cost of any additional special attendance
provided to the nominated sub-contractor.
Programme effects. The delivery period for the acoustic doorsets is 14 weeks
meaning that they will be delivered in week 72, seven weeks after the scheduled
contract completion. This will delay handover by at least these seven weeks plus
the additional time taken to install the replacement doors and complete any
follow-on and tidy-up activities. The architect and contractor will, no doubt, urge
the nominated sub-contractor to prioritise the work in order to minimise the
eventual delay.
13
following handover of the building. This approach would, however, require a new
contract to be negotiated and the original bill rates would no longer apply.
The scope of the works would include removing the original doorsets and
ancillary works, making good, and replacing with the acoustic doorsets. These
works could be done while the building is operational, in accordance with an
agreed programme, perhaps over weekends or at night to minimise disruption.
Despite the premium which is likely to be paid for this arrangement, it may
nevertheless, be a more economic option than reimbursing the contractor’s
prolongation / disruption claim for being prevented from completing on time.
This work must be carried out before the project is handed over for safety reasons! The
instruction brings about a variation under clause 2 which is to be valued in accordance
with clause 13. The scenario indicates an emergency situation where there will be no time
to ‘shop around’ before making an appointment. As the work is of a specialist nature, the
architect would typically nominate a particular subcontractor to carry out these works.
The contractor may propose suitable firms in making this appointment.
The valuation of this variation will be by agreement, as there are no applicable rates
included in the bill, nor is it likely that reliable rates could be interpolated from rates on
‘local’ projects. Ideally the price will be agreed before the work commences, but given
the ad-hoc scenario this is more likely to be agreed on completion of the works on the
basis of dayworks. Emergency works by specialists can be expected to cost considerably
more than routine operations. The contractor will be entitled to add for profit and any
additional special attendance on the nominated subcontractor’s work.
The fire protection work will, no doubt, delay the handover of the building. The
contractor will therefore become entitled to an extension of time for the delay caused by
this instruction. The contractor will be entitled to claim prolongation costs arising as a
result of the extended duration on site. There may also be disruption costs associated with
the works.
14
Example 3. Variations under the Public Works Contract
Explain the provisions of the Public Works Contract PW-CF 1 to value the following
change orders: (assume an 80 week-contract)
a. A significant part of the softwood skirting and architraves have been fixed when
the Employer’s Representative issues an instruction to omit softwood skirting and
substitute these with hardwood.
b. The contract is on programme at week 74. The internal plastering has been
completed when the Employer’s Representative issues an instruction to take out
the double glazed aluminium windows to the west elevation and substitute them
with triple glazed units. Delivery of these units is quoted as 10 weeks
c. Add sound deadening quilt above the suspended ceilings of the ground floor.
Instruction issued during week 78.
Part a, is a variation and will be the subject of a change order issued by the employer’s
representative. The contractor will be paid for the softwood skirting and architraves
which have already been fixed in position at rates contained in the pricing document. It is
assumed that the skirting has not been painted at this stage and that architraves will not
need to be taken down. This change order requires the accurate measurement of the
quantity of softwood skirting fixed on site in order to agree the quantum involved with
the contractor.
The contractor will also be paid the cost of removing the original skirting, plus the cost of
any consequential making good of finishes. It is very unlikely that there will be rates
covering this type of work in the pricing document and it would be considered
inappropriate to use tendered rates on other (refurbishment) projects as the basis of for
valuing this unplanned work. The cost of the work involved in removing and disposing of
the skirting should, therefore, be valued on the basis of invoiced dayworks.
15
Regarding unfixed softwood skirting, the contractor should immediately cancel any
outstanding deliveries. Any unfixed skirting included in previous certificates has already
been paid for, and is now the client’s property. It is possible, however that further
deliveries of softwood skirting have been made since the previous certificate; the
employer’s representative has the discretion to pay for these unfixed materials but is not
obliged to include them in the next interim certificate. The contractor will, nevertheless,
be instructed to remove the unfixed softwood skirting from site and is expected to use
best efforts in order to minimise the additional expense involved. The contractor may be
able to return them to the supplier, but this will probably incur restocking charges. There
is also a slight possibility that the contractor may be able to use the materials on other
sites, and if so, the consultant QS will seek to ensure that any credit from restocking or
their use on other sites is passed on to the client.
The extra cost of the hardwood over and above that of the softwood. This
involves subtracting the basic cost of the softwood from hardwood.
The additional labour required to fit hardwood in lieu of softwood. This involves
comparing the labour constants for fixing hardwood and softwood. This is then
multiplied by the all-in rate per hour for carpenters.
It is assumed in this instance that this variation can be completed without delaying
completion of any critical activities and that the preliminaries costs are not
impacted.
It should be noted that P.C. Sums are not accommodated on public works contracts and
that ‘reserved specialists’ are employed by the contractor on a ‘domestic’ basis. The
16
contractor will be paid for the work properly carried out at the date of the employer’s
representative’s instruction.
Abortive work. It is assumed that original double glazed window frames cannot
accommodate the extra thickness of the triple glazing and, therefore, will
effectively become scrap. Any credit which can be obtained for these will be
taken into account. The cost of removing and disposing of the windows and
making good any structural work or finishes will be the subject of a daywork
account as in part (a) above.
17
There will be additional delays associated with the window installation and
consequent finishing up process. The contractor will be entitled to apply for the
use of the Programme Contingency or to seek an extension of time where the
Contingency has been exhausted.
The contractor will not be paid any delay costs until the first threshold of the
Programme Contingency has been exhausted. The contractor will be paid half of
his tendered daily rate for delay where the delay exceeds the first, but not the
second threshold of the Programme Contingency. When the Programme
Contingency has been entirely exhausted, the contractor will be paid his full daily
rates tendered for the remaining period of the delay.
The contractor must comply with all notice and information required by the
contract and demonstrate the effects of the instruction by reference to the
programme. As the contractors have included daily rates for delays in their
tenders, these rates will form the basis for calculating damages should the delay(s)
exceed the Programme Contingency first and second thresholds.
There is little doubt that some (considerable) pressure will be exerted on the
contractor and window subcontractor to prioritise the delivery of the windows in
order to enable the project to be completed within the original schedule and to
avoid the need for retrofitting works. The client may agree to pay for accelerating
the contractor’s progress in this instance. The additional cost of overtime, shift
work and the increased subcontract charges involved will need to be carefully
recorded in order to evaluate this instruction.
This instruction has been ordered very late in the contract programme and is targeted at
corridors areas that are likely to be very busy during this crucial period immediately
preceding handover. The proposed work therefore has the potential to be highly
disruptive and, as such, is likely to cost (significantly) more than similar work carried out
as part of a planned programme of works.
18
Installation of the insulation will require the lifting and/or removal of some or all of the
ceiling panels/sheeting and its supporting framework. The cost of carrying out this
unplanned preparatory work and replacing it on completion will be valued on a daywork
basis.
Although no rates for the sound deadening quilt are contained in the bill of quantities, it
is an item which is included in many commercial and educational projects. In normal
circumstances it would be appropriate to value these works by agreeing a ‘fair rate’ based
on rates for similar work in the locality. However, in the current ‘emergency’ scenario, it
is clear that ‘normally tendered’ rates for insulation are unlikely to form the basis of an
agreed settlement, particularly if the work has been carried out at night or over weekends.
The valuation of the insulation, therefore, is also likely to be claimed, and most probably
settled, based on dayworks.
As noted above, the instruction may cause (considerable) disruption of the contractor’s
completion activities. It may also delay handover of the building. In the event of delay,
the contractor will be entitled to seek a use of the Programme Contingency or to seek an
extension of time if the Contingency has been exhausted. Additional costs arising from
the disruption of the contractor’s work, however, are not reimbursed separately, but
instead, are incorporated in the daily rates tendered for Compensation Events by the
contractor in competing for the project.
Supplemental Discussions
Exercise 1
During a contract, the client requests the contractor to change the floor finishes in various
areas. Explain how the provisions of the RIAI form of contract would be applied to value
such changes.
Exercise 2
Apply the provisions of the RIAI contract to value the following architect’s instructions
19
1. Delete all internal plastering to concrete blockwork in the staircase areas and
substitute with fair faced blockwork.
References
Cartlidge, D. (2017) Quantity Surveyor’s Pocket Book 3rd ed. Routledge, Abingdon,
Oxon.
Office of Government Procurement (2017), Public Works Contract for Building Works
Designed by the Employer PW-CF1 v.2.2 09 January 2017, Department of Public
Enterprise and Reform, Dublin
Royal Institute of the Architects of Ireland (2012) Agreement and Schedule of Conditions
of Building Contract, Royal Institute of the Architects of Ireland, Dublin.
20
APPENDIX
(a) The rates in the Bill of Quantities referred to in section (i) of sub-clause 3(a) or
the Schedule of Rates mentioned in section (ii) of sub-clause 3(a) of these Conditions
whichever applies to this Contract shall determine the value of work carried out as a
variation where such work is of a character similar to that to which the aforesaid rates
apply and is carried out under similar conditions. The aforesaid rates shall also determine
the value of any work omitted provided that if in the opinion of the Architect such an
omission varies the conditions under which any remaining items of work are carried out
such remaining items shall also be deemed to be varied and shall be valued under rule (b)
hereof.
(b) The said rates where variations are not of a similar character or executed under
similar conditions as aforesaid shall be the basis of prices for the same so far as may be
reasonable; failing which a fair valuation thereof shall be made based upon rates for
similar work in the locality current at the time the variations are executed.
(c) Where in the opinion of the Architect variations cannot properly be measured and
valued in the manner set out in rule (a) or rule (b) the Contractor shall be allowed
daywork prices:
i) at the rates in any in the Bill of Quantities referred to in Section (i) of sub-clause 3(a)
or in the Schedule of Rates referred to in Section (ii) of sub-clause 3(b) as the case may
be; or
ii) where no such rates have been inserted at the rates in the Schedule of Daywork
Charges agreed between the Society of Chartered Surveyors in the Republic of Ireland
and the Construction Industry Federation and approved by the Royal Institute of the
Architects of Ireland and current at the time the work is carried out; or
iii) where the work has been executed by a member of a sub-contracting trade at the rates
agreed between the said Society and the appropriate body representing the sub-
contracting trade or, where no such rates have been agreed, at the rates set out in Section
(i) of this rule
21
Text of Clause 10.6 of the Public Works Contract Regarding the
Valuation of Variations
Adjustments to the Contract Sum for a Compensation Event shall only be for the value of
any additional, substituted, and omitted work required as a result of the Compensation
Event under this sub-clause 10.6 and any delay cost under sub-clause 10.7. Additional,
substituted, and omitted work shall be valued as follows:
10.6.2 If the Compensation Event requires additional, substituted or omitted work that is
not similar to work for which there are rates in the Pricing Document, or is not to be
executed under similar conditions, the determination shall be on the basis of the rates in
the Pricing Document when that is reasonable.
10.6.3 If the adjustment cannot be determined under the above rules, the Employer’s
Representative shall make a fair valuation based on rates for similar work in the locality,
if available.
10.6.4 Instead of sub-clauses 10.6.1, 10.6.2 and 10.6.3 applying, the Employer’s
Representative may conclusively direct that additional or substituted work required as a
result of a Compensation Event be determined (in full or in part) on the basis of the cost
of performing the additional or substituted work, compared with the Contractor’s cost
without the Compensation Event, determined as follows:
(1) the number of hours worked or to be worked by each category of work person stated
in the Schedule, part 2D, and engaged on the work to which the Compensation Event
relates, on or off the Site, multiplied in each case by the tendered hourly rate for that
category stated in the Schedule, part 2D (But if any of the tendered hourly rates are less
than 75% of the relevant rate (in the case of Craftspersons this means 75% of the
Craftsman’s rate, or in the case of General Operatives, 75% x 88% of the Craftsman’s
rate, or in the case of Apprentices, 75% x 62% of the Craftsman’s rate) in the
construction industry registered employment agreement current on the Designated Date,
they will be read instead as 75% of the relevant rate in that agreement (in the case of
Craftspersons this means 75% of the Craftsman’s rate, in the case of General Operatives,
75% x 88% of the Craftsman’s rate, in the case of Apprentices, 75% x 62% of the
Craftsman’s rate)) and
(2) the cost of materials used in that work, taking into account discounts and excluding
VAT, plus the percentage adjustment tendered by the Contractor and stated in the
Schedule, part 2D (But if the percentage adjustment tendered is negative or blank it will
be read as 0%) and
(3) the cost of plant reasonably used for that work, whether hired or owned by the
Contractor, at the rates in the document listed in the Schedule, part 1K (as that document
22
may be modified according to the Schedule, part 1K) plus or minus the percentage
adjustment tendered by the Contractor and included in the Schedule, part 2D (But if the
percentage adjustment tendered is a deduction of more than 100% it will be read as a
deduction of 100% or if the entry is blank it will be read as 0%). If the document listed in
the Schedule does not give a rate for a plant item, a market rental rate shall be used, plus
or minus the percentage adjustment.
23