Guide to Nuclear Decommissioning
Guide to Nuclear Decommissioning
Contents:
• What is decommissioning?
• Stages of decommissioning
• Site restoration
• Waste management
• The UK decommissioning industry
• The international picture
What is decommissioning?
There comes a time in the life of any power station – nuclear, coal or oil-fired – when
age takes its toll and it becomes uneconomic to run any longer. Once this stage has
been reached the decision has to be taken to shut it down. Eventually the plant is
taken to pieces to remove any hazardous material, the debris disposed of and the
site left in a safe condition which is visually acceptable. This is called
decommissioning. Each project is treated on its merits; actions can range from simply
closing the facility to dismantling and restoration of the land for other use.
1. Initial decommissioning
• Reactors are defuelled and the fuel usually moved
away from the reactor. All non-fixed contaminated
components are removed.
3. Demolition
• Once all radioactive and other hazardous material
(such as asbestos or mercury) have been removed,
the building is refurbished for alternative uses or
demolished if no longer required.
• Demolition is carried out in the same way as for any
industrial building, although stringent controls are
applied to monitor for the possible presence of radioactivity.
• The land is then remediated and returned to a condition where no radioactive
hazard remains.
In some cases the stages will follow directly one after the other. However, they are
often separated by periods of care and maintenance to allow for radioactive decay.
Site restoration
Restoring the environment of a whole nuclear site involves integrating a large range
of individual projects within an overall programme. UKAEA has led the development
of site restoration plans that prioritise these projects based on safety, environmental
and cost considerations.
The end-point for decommissioning a site depends on the potential for its future use.
UKAEA has experience in managing a wide variety of waste types safely and
securely. In each case we assess all relevant options, so that the chosen strategy
represents the best balance of environmental, safety, economic and community
considerations.
The Nuclear Decommissioning Authority (NDA) is responsible for overseeing the £48
billion restoration of the UK’s 20 civil nuclear sites, including those operated by
UKAEA.
• The NDA provides national co-ordination and ensures that best practice and
value for money is being achieved. It contracts out the management of its site
clean-up programmes
• UKAEA is a contractor for management of the Dounreay, Harwell, Windscale and
Winfrith sites.
• The NDA monitors site clean-up progress against Near Term Work Plans –
showing the detailed scope of work for the first three years – and long-range
Lifecycle Baseline plans covering the entire restoration process. They are
available at www.nda.gov.uk.
Around the world, nuclear clean-up is becoming a major growth industry, with over
400 reactors being decommissioned or awaiting decommissioning.