Major & Medium Schemes
Major & Medium Schemes
Sl No. Name of the Scheme Source of funding Projects Taken up/ Ongoing Status Objective District Benifited
(in Crores) Duration (upto Jan-2022)
* Extension Works: i.To revive the lost ayacut by restoring the
Harabhangi Extension On going irrigation system to its designed capacity.
Gobindpur barrage On going
Nuagaon Distributary of Rushikulya Irr. ii.To increase irrigation area of some selected
On going
System projects beyond designed capacity
Kharkhara Irrigtaion Project Not taken up
Dhusuma Barrage Not taken up iii.Equitable distribution of water and full
Birupa Genguti Completed utilization of designed irrigation capacity.
* Modernization Works:
Potteru Completed
Satiguda Completed
Dadaraghati ( RMC RD 00 to 985m) Completed
Sapua ( Link Channel) Completed
Bhairpur Branch canal ( Rengali Irr. Cuttack, Jajpur,
Completed
Project) Kendrapara,
369 Ha. ayacut newly created.
Nabakrushna Choudhury Hariharjore( Damaged Structure of main Bhadrak,Jagatsingpur,
State Funded Completed 2017-18 to 43781 Ha. ayacut revived.
1 secha Unnayan Yojana. 635.00 Canal) puri, Angul, Dhekanal,
Scheme 2019-20 TOTAL- 44150 Ha.
(NCSUY) Hariharjore(Sardhapalli, Champamal kalahandi, Sonepur,
On going
Distributary) Nuapada,
MCII Completed Malkhangiri,Nayagarh
Mahanadi Delta Stage-I ( Kendrapara
On going
Irr. Divn)
Mahanadi Delta Stage-II ( Prachi Divn.) Completed
HLC-III ( Jajpur Irr. Divn) On going
Upper Indravati ( Rt. Canal System) Completed
Rehabilitation of aqueducts of Baragarh
Not taken up
Main Canal
Dredging of Taldanda Extn. Canal RD
Not taken up
0.00 to 7.20km( Mahanadi Delta Stage-I)
Minor Irrigation ( 284 nos. Minor
Irrigation Projects)
Rengali Right Bank Canal
Deo Irr. Project
Mahendratanya Irr. Project, Ph- I i. Completion of last mile projects with
Manjore Irr. Project On going adequate provision of fund.
Ong Extn. Project
Lower Suktel Irr Project, Balangir ii. Taking projects to advance stage of Angul, Dhenkanal,
Water Sector (UGPL) 57480 Ha. Irrigation potential
construction to avail central government Cuttack, Jagatsinghpur,
Infrastructure State Funded Hadua Irr. Project 2019-20 to created.
2 5000.00 funding like PMKSY- by completing pre- Kendrapara,Gajapati,
Developement Programme. Scheme Cheligada Irr. Project Funding issued under 2023-24 Funding of Cheligada and
project activities - advance stage of Ganjam, Bolangir,
(WSIDP) AIBP Kusumi is issued under AIBP
construction. Sonepur, Mayurbhanj
Baghalati Irr. Project On going
Funding issued under iii. Preparation of shelf of projects for funding
Kusumi Irr. Project
Mahanadi Chitrotpala Island Irrigation AIBP by adequate progress of pre-project activities.
Project
Ghatakeswar Irr Project On going
Rajua Irr. Project
Malkhangiri, Sambalpur,
Cement concrete lining,renovation of Bargarh, Barpalli,
Canal Lining and System structures,re-sectioning and Kendrapada, Jajpur,
State Funded 2018-19 to
3 Rehabilitation Programme. 1150.00 strengthening of canal embankment from On going Jagatsinghpur,
Scheme 2022-23
(CLSRP) RD 0.00 km to 60.00 km of TMC, Nimapara,Puri,
(phase- I from RD 00 Km to 30.00 km) Ganjam,Berahampur,
Koraput.