5A-Start-up-Check-List
5A-Start-up-Check-List
Leak check
Open & enclosed generator sets
DCA dosing cartridges fitted & valves open
This checklist should be used to validate the completion of
generator set start-up procedure. A check-list should be Remote mounted radiator systems
completed for each generator set of a multiple installation. Radiator, engine & pipework checked for leaks
Customer (End User).…………………………………..……... DCA dosing cartridges fitted & valves open
Heat exchanger & cooling tower systems
…………………..………………………………………………..
System, engine & pipework checked for leaks
Address……… …………………...…………………………….
Coolant heater operational
……………………………………………………………………
Secondary cooling system checked
…………………..……………………………………………….
Fans, pumps and controls checked
Customer representative…………………..…………………..
DCA dosing cartridges fitted & valves open
Tel. No ………………………..…………………………………
Legionnella dosing checked where applicable
Email……………………………………………………………. Record dosing chemical & concentration.............................
Radiator, engine & pipework checked for leaks Suppression system lock-off operational
Belts & guards checked for security / slipping Operator instructed in fire system operation
1
Lubrication system Generator set voltage & frequency correct to order
Engine oil pan filled to correct level Control system calibrations checked
Oil make up system operational Phase rotation checked
Paralleling sets phase coincidence check
Starting system Generator set switchgear manual operation correct
Battery starting Local stop / emergency stop control checked
Batteries installed, filled and connected Remote start / stop / emergency stop checked
Battery charger commissioned
Compressed air / hydraulic starting Generator set load test
Isolating valves correctly positioned Note: Load test is carried out on customer’s site load
unless agreed in writing prior to start-up. Artificial load
Compressor operational bank test will be performed using resistive load unless
HP & LP air / hydraulic pressures checked otherwise specified.
Condensate drained Load test completed using customer’s load
Record load achieved……………………………………kW
Exhaust system Load bank test (if applicable)
Check security of pipework & muffler Check load bank voltage & power capability
Check cowl and/or rain cap are operational Check cables installed correctly & tightened
Check water drain pipework and valves correct Energise auxiliary supplies and check functionality
Generator set system controls checked Comments on any item that may affect acceptance:
Customer remote indication / controls checked ……………………………………………………………………
Changeover switchgear / transfer switch ……………………………………………………………………
Auxiliary supplies energised ……………………………………………………………………
Utility supply energised ……………………………………………………………………
Voltage / phase rotation checked ……………………………………………………………………
Indications correct ……………………………………………………………………
All covers in position ……………………………………………………………………
Paralleling switchgear
Checklist completed by ……………………………………….
Auxiliary supplies energised
Date……………………………………………………………...
Indications correct
Print Name………………………………………………………
All covers in position
Company………………………………………………………..
Note: Completion of this checklist does not relieve the installer of contract obligations.
Initial start-up By signing this document you agree to the terms and conditions of our warranty.
Failure to sign and send this document to the manufacture does not relieve the
Manual start-up, idle & full speed checks complete installer of the terms and conditions of the warranty.