ITP- lighting control system
ITP- lighting control system
RSG-CN-TMP-0013
Package Name 1SV10110-110C25 SIA SIAC International for Contracting Power Construction
Responsibility
Reference/ Controlling
Item No Task/Activity Frequency Record Remarks
Document
3rd Party Contractor Employer
Approved Material Submittal, Material Delivery Note & Project Specification- 260923-2 &
2.1 Inspection of material Received at Site
260926-2 All Supplied Quantities MIR N/A H H Visual inspection
Project Specification- 260923 & 260926, Approved Method Statement & Manufacturer
2.2 Product Storage and Handling
Recommendation All Supplied Quantities MIR N/A s S Visual inspection
4.0 Testing
RSG-CN-TMP-0013 1 of 2
Rev. 00, 05 May 2024
Inspection Test Plan
RSG-CN-TMP-0013
Package Name 1SV10110-110C25 SIA SIAC International for Contracting Power Construction
Testing &
Project Specifications 260926-3.1 & Material Requirements & Commisioning
Final Inspection for lighting control
5.1 Close-Out requirements & Approved Drawing, Manufacturer’s Each Activity Reports & WIRs / N/A R/H R/H
system Installation works
Data Sheet Warranty
Certificate
General Notes
1 Employer: An authorized employee who represents RSG and is empowered to take action in the activity. This role can be filled by a Quality Supervisor, Quality Manager, Technical Engineer, or Construction Engineer as defined in the Method Statement and PQP.
2 Review Point R: Employer shall review the task results before moving on.
3 Surveillance Point S: Monitoring work in progress, which does not require a written notification. A surveillance report may be issued to document the activity.
4 Witness Point W: The Employer shall be notified in advance, in writing, about the timing of inspections or tests. However, if there is no written approval or presence from the Employer, the inspection or test shall proceed as scheduled.
5 Hold Point H: The Employer shall be notified in advance, in writing, about the timing of inspections or tests. Subsequent activities should not be carried out without written approval from the Employer.
Legend
H Hold Point Project Quality Plan ICA Independent Commissioning Agent (Employer assigned entity)
RSG-CN-TMP-0013 2 of 2
Rev. 00, 05 May 2024