Opt Res 1
Opt Res 1
x0 3 x1 2 x 2 5 x3 x1 2 x 2 x3 430
subject to
3 x1 2 x3 460
x1 4 x 2 420
c) A bicycle shop estimates the annual demand for its Hero brand of bicycles to be 384. The hold
cost per bicycle is ksh 20 per year. The ordering cost is ksh 60 per product.
d) Coastal electrical development ltd (ced) has identified the following activities / tasks in the
regions electricity projects ced has also established the precedent relationship and duration of this
activities. This information is in the following table.
Activity A B C D E F G H I J K
Immediately - - - A A B,G A,C A,C D E,F,H E,F,H
preceeded by
Duration 8 5 3 5 6 6 3 10 8 12 11
(days)
e) An organization buys 400 units of an item in a year at a purchase cost of shs 5000 per unit and
an ordering cost of shs 2000 per order placed, the carrying cost has been determined to be 20% of
the cost of average stock. The organization has received a 2% discount offer for purchases of 100
or more units required. Determine the best inventory policy for the item. (4 marks)
b) Using the simplex method find the optimal basic feasible solution and hence the optimal value
x0 x0 3 x1 5 x 2 2 x3
of for a linear programming problem to, maximize
x1 2 x 2 2 x3 10, 2 x1 4 x 2 3 x3 15 x1 0 x 2 0 x3 0
subject to and , , . (6 marks)
c) Bandari development co. ltd is using network planning for one of their building project; the
network consists of 10 activities A to J whose duration depends on the number of craftsmen
available. Those required for each activity are given in the table below.
ii) Given that 3 craftsmen only are available thought the project, schedule the activities so that the
earliest project completion date is achieved. (Splitting of activities is allowed) (4 marks)
b) Jericho ltd manufactures B2b on a special lathe for use in a continuous assembly. The
assembles that use B2b are manufactured at a lower rate, this allows time for doing odd jobs on
the special lathe when it is not being used for B2b parts. When parts are being run deliveries are
made to the assembly area, otherwise the assembly department draws parts from the inventory.
The following data is given for B2b parts:
iv) what is the TC associated with the inventory policy formulated in i), ii) and iii) above.
(2 marks)
vi) suppose it turns out that actual holding cost is kshs 16 per unit/ year and set up cost is kshs
180,000 per set up and yet the policyabove is implemented for one year. Determine the cost of
prediction error. (3 marks)
c1
c2 z 5 x1 4 x 2
c) Determine the range of optimality, for a maximization function with a
6 x1 4 x 2 24, and x1 2 x 2 6
solution at the intersecting point of . (4 marks)
iii) Constrains
c) Using the Queuing theory advice a company that as a certain type of machines breaking down
at an average rate of 5 times a month. The breakdowns are in accordance of poisson’s process.
Cost of idle machine hour comes to kshs 150 per hour. Two repairmen V and W have been
interviewed: V charges kshs 80 per hour and services broken down machines at the rate of 7 per
month whereas W charges kshs 100 per hour and services the same at a rate of 9 per month,
which repairman’s services should be hired and why. (9 marks)
a) The manager of an oil refinery must decide on the optimal mix of 2 possible blending process
of which the inputs and outputs per production run are as follows
c) A certain production produces on average 7 % defective items, and they occur randomly. Items
are packaged for sale in lots of five. The production manager wants to know what percentage of
the lots contains no defectives, using the Monte Carlo simulation advice. (Stimulate at least 10
lots of 5 item using 2 digit tables) (5 marks)
THE END