Advanced Capital Budgeting
Advanced Capital Budgeting
14921 10000
4921
on 1st OM 1st
115000 120000
115000 120000
100000 IRR 1 100000 IRR
At 12 Dv 102678.5 At 15 PV 104348
IRR 14 1
151
E.g Initial Investment 500000
NPV 121713
At 22 NPV 510560.35
1056035 15234 58
21 500000
At 24 NPV 495325.77
Example
Suppose there are two Projects
1 Project Initial Investment 1000000 cash flows410yrs 200000p.a
A
2 Project B 1 1000000 labsflows 437ms 500000 p h
Assume cost
of capital 10
Project A
NPV 228913
Project B
PV cash Inflows 500000 PVIFA 10 Byns 1243426
of all
1000000
Initial investment
NPV 2 243426
At 15 Pv 10,03 754
1000000 IRR 15.10
PV 9,66 645.50
At 16
2338 616900
1 2338
1655000 s
MIRR 1 655 1.1429
1000000
1 655Viatimes
ie 18.29 t 1
12times
Eg
Initial Investment 20000
cash flows sym 9000
Cost of capital 2 10
Revenue 5000000
Cost 2000000
Dep 1000000
41
2400000
cash flows of Project
1 1 tax 60
PAT 49600 58600 119514 131331
NPV 106744
NPV 13433
I Project should be
accepted
Alternative 501
Nominal discount rate 12 Inflation 10
Dothis in Exam
Calculation
of Real cashflows
Revenue 30000 30000 30000 30000
Cost 10000 10000 10000 70000
Tax 50
PAT 5000 5000 5000 5000
Dept 10000 10000 10000 10000
3935
of
PV
of all cashInflows 57367 Differencenin Answer is due
Calculate NPV
Alternative
NPV 15364
Alternatively
Alternative 2
NPV 15380
1 Statistical Analysis
Cash flows
for yead 2
Scenarios Cash Flow Probabilities Expected cashflows
30 18000
Best 60000
Cash flows
for yead B
Scenarios Cash Flow Probabilities Expected cashflows
Calculation of Risk
years
R CIF Prob a I a IT
50000 25 9000 81000000 Independiente x.rs
40000 60 1000 1000000 u x 60
0 0
40000 40
20000 30 20000 400000000 30
x̅ 40000 fu 240000000
5 49500 Me 114750000
Co efficient
of variation for year 3 b
c
10712 2164
49500
Discountrate 10
Othym 1st 2ⁿᵈ 3rd
39000000 240000000 114750000
32231405 39000000
111012
240000000
110
163923229 0000
47
111107
poun Dis 10
64773383 on istyn
1
1
Here NPV of Project is 27484
9 D of Project is 16153
i Co efficient
of variation 5D
IP
on on
SEE Exp return
at othym
16153 5877
27484
2 Conventional Techniques
A Risk Free Rate
if cash flows are risk free we should use Risk free Discount
rate to calculate Pv of future cash Flows
all
Eg Investment Amount in Risk free securities 100
Riskfree rate 5
Regd Cash flows if one you maturity 100 1.05
105
Rf 5 Risk Premium 7
i RADR 5 7 12
P.v 1786
20,92
E9
Initial Investment 100000
Rf 6 fish Premium 8
NPV 20420
NPV 17041
1 Dt is understood that
a In case of Risky CIF use RADR
b cent g CIF use Risk free rate
3 Other techniques
A Sensitivity Analysis
it is a risk analysis technique that examines how changes in
single variable E.g Sales cost discount rate affects a project outcome
like NPV on IRR while keeping all other variables constant
it helps identify the most critical variable influencing a project's
success or failure
Eg
Initial Investment 1000,000 Tax is ignored
SalesPrice of 60 costPrice at 40 Project life 3yrs Dis Mate 10
Salesvolume 1ˢᵗyn 20000uts 2ndyr 30000 uts 2ⁿᵈmn 30000 uts
501
1styrs cash flow 20000ms x 60 40 400000
3ʳᵈyrs 11 30000
up x 60 40 600000
1310293 1000000
310293
i Initial Investment sensitivity
investment can be increased so that NPV
It means How much of initial
becomes Zero
Here initial Investment can be increased from 1000000 to 1310293 where
NPV will be zero Lie I I can be increased
by 3102937
1 Initial investment sensitivity 310293 x 100 31.03 As
1000000 RANKG
100
Ciil Sales Price at sensitivity
Let the bP fat of 290 NPN we 1 Alternative
60
AQ
20009 30099 9
x 40 30000 1
300
20000 30000 x 401 40 1000000
1110 1.10 1 107
3930879
40 9.9
1000000 Annual Rev sensitivity
29
19 NPV
PVofallRevenue 100
J a 40 418181.82 24793.39 22539.44 1000000
319,293,9 100
7.91
1 40 65514.65 1000000
N 40 1000000
6551465
verify
a 15.26 40 20000 55.26 40 30000 55.26 40
1.10 1.10
55 26
30000 55.26 40
9
2n 60 401 3 60 40 3 60 40 1000000
110
4 pop 1111077
how
1
1000000
110 p
36.36m 49.59m 45.08 a 1000000
of 131.03 U 1000000
I 7631.84
i Sales volume in 1styrs 2n 2 763184 15263.68
Sales volume in Istyn can be decreased by 20000 15263.68 473632
23 681
V1 costof capital sensitivity on Discount mate sensitivity
At 26 COC 11 995333 70
IRR 25 70 25.70
I Cost to 25.70
of Capital can be increased from
10
v1 Project lifetime
Since Initial Investment is E 1000000 therefore Project life should be
such that DV is recovered to the extent of E
of lashInflows
1000000
3636367
at Istyn Dv of C 1
40998
to be done in
i of work 3dm
11 100 31.17
1310293 1100000
2 210293
I NPV change Ans
310293 210293 100 32.239
310293 Rank
NotForExam
When NPV decreases 32.23 Initial Investment changes 10
1 12.23
31.03
82745
NPV change 310293 1 82795 x 100 126.68 Arg
310293 Rank1
NotforExam
if Mpv 126.68 S.p.lt change 10
is 11 1 t 1 11 11 1
ff
100 1 11 11 1 116.68 100 7 90
3 lostPrice ut Sensitivity
Current Cost Price no pen unit
If Cost Price Per unit adversely change by 10 Revised Cl 40 101 44
Revised NPV 20000 60 4h 30000 60 44 30000 60 441 1000000
1110 1110 1.1073
48234
179264
19.2 100
23681
286049
501
P 50000 24605
79
N 20000 50000
2 486
49 48
4 Coc
491
5 Project life
recover 50000
Tope Initial investment to
300
istyre a v of C I 4 7 27273
Balance 227 27
2ndyn P v of c I 39 7 i e 24793
No 365days 91 67
of days 335days
1128500
U z 5686963 28.43
200000
195000 units
1 Expected NPV
9195000 10 1651 10000007 3.605 5000000
885163
Here
Break even sales where Npv 0 176812 whits
Practice
iii NPV 2972750
Fixed cost sensitivity 7.8416
To calculate Annual fixed Cost
Let Annual fixed cost be a
1ˢᵗ 2ⁿᵈ 3ʳᵈ 41 5ᵗʰ
Fc a n n a n
1 Dv
ofall fixedCost 3791k a PUFA10 1544
11 3791
29.72750561 2972750
I R 2972750 100000
29.7275056
Alternatively
MPV 29727 50
I Every year fixed costcanbe increased 2972750 7841.6
by 3791
B Scenario Analysis
Example
139580
I 10000 40 40 0 39 hodigits
II 12000 14 54 40 53 Indigits
8000 28 82 54 81 28digits
I 15000 05 87 82 86 5digits
13000 08 95 87 9.4 8digits
know 02 97 95 96 2digits
16000 03 1 97 99 3digits
1
Random Numbers
91,13 161,517,541,15161 9191159191.78147184
Gothrough
Miscellaneous Points Greater P I is better
P.I PVof cashInflow
1 Profitability Index
PVof cash outflow
Protect A Project B
cashFlows utilities Drob Exp utilities CashFlows utilities Prob Exp utilities
15000 100 10 10 1a000 60 10 6
10000 60 20 12 4000 3 15 45
15000 40 40 16 15000 40 he 16
10000
30 20 6 5000 20 25 5
5000 20 10 2 10000 30 10 3
Expected utilities to Expected utilities 17.55
Since Expected utilities
of Project B is more compared to A it should be accepted
Replacement Decisions
Eg Illustration12
2
CA ofold machine today 25000
9 54ms 12500
Dep Exp p.a on old machine 2500pA
50000
cost
ofNew machine
1000
salvage value
E9
Illustration
cost
of taxi 400000 useful life 3years cost
of capital 10
0ᵗʰ Istyn
Cost 400000 180000
Resalevalue 280000
100000
90900
pooooox.ro
Pv oftotalcost 309100
Resalevalue 230000
5471001 _826
1180000 20000
163620
PV totalcost
of 547100
Resalevalue 11680007
163620 86 70000
173460
751
52570 C
cycle is 24ms
E.g Project A
Pv of total lost 300000 likeGyms
Project B
Pvof total cost 330000
life 54ns
Discount rate 10
501 Since like is different Therefore EAC method is suitable
Maint Cost
60000 60W
104100 4 10 1 735
Alternatively
Machine A
Salvagevalue 21000
55000 33000 17000
29997 909
826
14042
total Cost ofP.V.in 24ns 99039
EAC 99039 57083 P a Gleast
1.735
Salvage 9000
55000 37000 38000 77000
29997 909
826
31388
751
27787
Total Cost atPu in 349 144172
827 Alternatively
One
year replacement
Initial Cost 55000
I EAC 9 57083
Salvage
50000
50008 60
3 Replaced machine 2000000 20,20000
2050000 410000p.cn
Dep
5
option I
Existing machine upgraded machineGinitialInv 10000007
CashInflow lashInblowGPAT Dep created lshp.ir
GPATFD.fi
491 500000 550000 200000 750000 250000 870
1 1 IncrementalCostofupgradation 1000000
Incremental NPV 191320
4692 540000
Ghodo 410000 1050,000 510000 756
4193 580000 410000 520000 658
690000 11,00 on
Yeah 620000 530000
thoooo 410000 11150,00 572
yeary 660000 550000
800000 410000 12110,00 1497
Pv of Incremental C'I 1747930
2020000
c 1 Incremental costofRepair
Incremental NPV 272070
One Replacement
year
Purchase Price 60000
cannotbe applied
Hillier model millionmodel
Eg
Initial Investment 270000 Discount rate 10 Projectlife 24ms
Here 2ndym C F
160000 III 40 X 25 10
ENPY
NPV 1106 a 5 Ca x̅
8920 16 Prob
660 14 Prob
7600 10
42300 10
50560 0875
58820 0625
93520 114
118300 1225
134820 0875
I 50951.95 variance 2570560380
SD 2570560380 50700.69
Since NPV's one at Present value therefore variance and SD calculated here
will also be at Present value
f v of variance 2570560380
11 SD 50700 69
Co efficient
of variation SD 50700.61 995
Npy 5095195
2 when cash flows are Independent Hillier model can be applied
A PATH BASIC
PATH NPV NPV JP ENDV
I 75000 909 70000 826 120000 5995 28 1678.5
II 475000 909 100000 826 120000 30775 112 3693
ENPV 31154 5
Npual Prob a ñ n ñ
5995 28
30775 12
24175 21
48955 09
46900 21
71680 09
Cashflows a Prob a ñ a 55
75000 40 19500 380250000 x 40
95000 30 500 250000 30
2ⁿᵈyrs shortant
Cashflows a Prob a 5 a 55 adn
70000 28 9000 81000000 28 cashraful a5 4 51
100000 12 21000 441000000 12 70000 70 9000 81000000
3 When cash flows are Perfectly dependent Hillier model canbe applied
Eg Initial Investment 14000 Discount rate 10
CashFlows
NPV al n r ca ñJ
12936.5
3429 5
x̅ 9133.7 variance
bD 4657.46
B Hillier model
istym cashflows a
prob n 5 un
8500 60 1200 1440000 X 60
5500 40 1800 3240000 40
7300 variance 2160000
1stym SD 1469.69
I 2ⁿᵈyn 3rdyn and hthyr S'D will also 1469.69
1469 09
p.ve
of 5 D 1469.69 146969
14
1110
aug 1 10
Points to Note
varianceIstyn Valiance2dam
a my I mgh
3 in case
of Perfectly Dependent off 9 ApplyMillier model or PathBasis
bD Istym S'D Udyn
ITM ITM
97
I ECF 100000 30 110000 x 50 120000 20 109000
95 to 1
V1 Co efficient
of variation of average project manger from
However Co efficient
ofvariation of NewProjectofMs x is 90
1 it is less risky
i Revised cost of capital 10 1 94
1 Revised ENPV
4109000 PVIFA19 54M 43000 PVIF49 5hpm 400000
Iii Probability
ofworst case if cashflows Perfectly dependent
30 1 1 XIX
30
60 I
no 40000 2h
50
60000 50000 I 30 60
10
VI 06
60000
1
ON
is cap of RADR
Project I RADR 10 1.87
5 191
Project I RADR 10 45 17 15
Project IT RADR 10 45X 6 13
Project II 7 ENPV 1600000 x 870 400000 X 756 500000 x 658 200000 572 1100000
167800
213800
PV ofSalvage
Play A 4400000 14867 594401
PlantBY 9400000 2394 95760
275016 pra
3904240 1315
513408p a
wages Pa 100000 p.a 140000p.a
60000000 up
No
of us Prod D
a 30000000ms
041167 028557
3093375
Savings in cost of startand stop
Incremental Cost
Average Cost Perkm 2 70 5 30 2.9 Per km
952650
BSheet
Eg.sncapital 50M Bank 200cm
loan 15f 7 150cm
1 Project IRR
901 Total Project Cost 200cm
at Present
i Project IRR is the IRR i e mate of which Piv of all 40cmfor 154ns will
be equivalent to 200cm
424
Ii Equity IRR
Equity Investment 50cm
Do it yourself
i Equity IRR 289
Project IRR on overall inv of 200 CM 18.42
Put Return paid to F 1 151
Difference 3 42
Understanding