BB MM Final
BB MM Final
, Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Business Blueprint
For
Materials Management
Prepared by
Sumantra Chattopadhyay
1
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
DOCUMENT CONTROL
MCL - Project
Mr. Pranjal Madamwar
Manager
SBT – Project
Mr. Sachin Shinde
Manager
CONTENTS
2
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
3
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
8.4 Reservation..................................................................................................................................... 55
8.5 Goods Movements.......................................................................................................................... 55
8.6 Rejection Return to Supplier........................................................................................................ 58
8.7 Line Rejected material send back to Supplier..........................................................................59
9.0 Pricing Condition................................................................................................................................ 60
9.1 Pricing Elements............................................................................................................................. 60
9.2 Terms of payment.......................................................................................................................... 61
10.0 Physical Inventory........................................................................................................................... 62
11.0 Vendor Evaluation........................................................................................................................... 65
12.0 Invoice Verification.......................................................................................................................... 67
12.1 Invoice Verification for Vendor.................................................................................................. 67
12.2 Invoice Verification for payment through LETTER OF CREDIT.............................................70
13.0 Material Valuation........................................................................................................................... 71
14.0 Scrap.................................................................................................................................................. 72
15.0 Release Strategy............................................................................................................................. 72
16.0 Excise Master:.................................................................................................................................. 73
17.0 Month End Closing........................................................................................................................... 73
18.0 Process Change Document – MM.................................................................................................. 74
19.0 Special System/Organizational Considerations..........................................................................80
19.1 Purchasing Document Types and Number Ranges................................................................80
19.2 Forms/Reports (SAP script) Document Printing......................................................................80
19.3 Availability & Use of Standard reports.....................................................................................81
19.4 System Configuration.................................................................................................................. 82
19.5 Data Migration Considerations.................................................................................................. 82
4
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
2. To optimise total Supply Chain Operations in terms of Delivery, Quality and Cost.
5. To integrate all the business functions like Business Development, Production, Quality, SD,
Finance and Controlling, Vendors etc on one common system.
5
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
1.0 Introduction
This document is the Business Blueprint for delivering the ‘AS-IS’ project at SBT. It outlines the
business requirements, ‘TO-BE’ processes and design considerations for the project.
This document is meant for MIS Managers, MIS Team leads and Key User champions who will
have to have a good understanding of ‘AS-IS’ system. This document explains all the
specifications that are broadly captured for successfully delivering the project. This is a
controlled document and its circulation is left to the discretion of MCL and SBT project
sponsors.
2.1 Objectives
The objective of this Blueprint Process is to define how to process Purchase processing in the
system.
6
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Purchase Management
Vendor Development
Accounts department
Excise department
Subcontracting operations
Invoice verification
Excise settlements
The system should meet all the requirements as per the following guidelines
7
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
2.5 Responsibility
The following ‘Role’ (or function) will be directly responsible for executing the Materials
management.
To be decided.
8
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
3.1 Company
A company is an organizational unit in accounting, which represents a business organization
according to the requirements of commercial law in a particular country. In the SAP system,
consolidation function in financial accounting is based on companies.
Company : SBT
The Company Codes that will be created in the system will be as under:
9
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
3.3.1 Plant:
A plant is an organizational unit that subdivides an enterprise according to
production, procurement, maintenance or materials planning.
It is a place where materials are produced or goods and services are provided.
A Plant is assigned to a Company.
A plant also has the following in SAP ERP:
An address
A language
A country assignment
A workday calendar
A Plant is assigned to a Company.
Purchasing organization and sales organization are assigned to plants.
10
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
11
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
1000
Company Code
2000
1000
Depot Plant
SBT Plant
(Gurgaon)
1001
1001
1002 Domestic
Domestic Purchase
Import Purchase
Purchase
Organization Organization
Organization
12
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
1000
Company Code
2000
1000
Depot Plant
SBT Plant
(Gurgaon)
FG01
SC01
ST01 Finished Goods ST01
Scrap Stores
General Stores Store General Stores
13
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
2 002 Stores
3 003 Procurement
5 005 Modeling
6 006 Assembly
7 007 Quality
8 008 Development
10 010 Maintenance
Machines
11 011 Finance
12 012 Admin
13 013 HR
14 014 Asset
14
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
The material master database (often referred to simply as the "material master", comprising
all the individual material master records stored in the system) contains descriptions of all
materials that an enterprise procures, produces, and keeps in stock. It is the central
repository of information on materials (such as inventory levels) for the enterprise.
The integration of all material data in a single materials database eliminates the problem of
data redundancy and permits the data to be used not only by Purchasing, but by other
applications (such as Inventory Management, Materials Planning and Control, Invoice
Verification, and so on).
Material Masters will be maintained at the client level but function related attributes
like sales, production planning, accounting; purchase etc will be different for different
organization levels.
Material Numbering will be External and according to SBT logic.
Material numbering will be alphanumeric.
Material Coding specifications:-
Mould
a. Length 14 char
b. 1st char – M
c. 2nd to 6th – machine
d. 7th & 8th – part description
e. 9th & 10th – Customer
f. 11th to 14th – No. of cavity
Fixture (tools)
a. Length 14 char
b. 1st char – T
c. 2nd to 6th – machine
d. 7th & 8th – part description
e. 9th & 10th – Customer
f. 11th to 14th – Size
15
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Gauge
a. Length 14 char
b. 1st char - G
c. 2nd to 6th – Part Description
d. 7th & 8th – customer description
e. 9th to 14th – size
Material Types
Materials with the same basic attributes are grouped together and assigned to a material
type. This allows you to manage different materials in a uniform manner in accordance with
SBT’s requirements. Following will be the material types in SBT:
5 DIEN SERVICES
8 CONS CONSUMABLES
9 SCRP SCRAP
Valuation Class
You group together different materials with similar properties into valuation classes so that
you do not have to manage a separate stock account for every material.
2 SPARES 3040
6 SERVICES 3200
9 CONSUMABLES 3002
10 SCRAP 7940
Unit of Measure
This is the unit of measure in which the stocks of a material are managed. The system
converts all quantities entered in other units to the base unit of measure.
Individual departments may have their own units of measure. All units of measure other than
the base unit of measure are referred to as alternative units of measure.
Following are the examples of unit of measure used in SBT: Kg. Convert to Numbers
17
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Material Group
The material group is the level in the material group hierarchy, which must be assigned
directly to a material when it is created. It is defined across the corporate group and sub-
divides the complete material assortment from a business management viewpoint.
1 01
RUBBER
2 02
METALS
3 03
MOULDS
4 04
CHEMICALES
5 05
FIXTURES
8 08
GUAGES
9 09
OTHERS
As Is:
18
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
19
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
SAP Process:
Purchase requisitions are expected to create during the MRP run for stock materials and
consumption based materials on the basis of reorder levels and safety stocks defined for each
material.
Process
Process Flow:
20
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Process
The system then calculates the net requirements. The system compares the available
stock at plant level (including safety stock) plus the firmed receipts that have already
been planned (purchase orders, production orders, firmed purchase requisitions and so
on) with the reorder point. If the sum of the stock plus receipts is less than the reorder
point, a material shortage exists.
The system then calculates the procurement quantity according to the lot-sizing
procedure defined in the material master.
For reorder point planning, the system supports the fixed lot size and Replenish up to
maximum stock level lot-sizing procedures.
The system then schedules the procurement proposal, that is, the system calculates
the dates on which the purchase order has to be sent, and the date on which the
vendor has to deliver the goods.
21
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Logistics personnel to provide and maintain planning related data such as re-order point,
Maximum Stock level, Safety Stock level, Lot Size, Planned Delivery Time, and GR
processing time for the materials to be planned in the material master records.
Improvement Areas:
22
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
The typical procurement cycle for a material consists of the following phases:
Procurement Cycle
MRP
ORDER INVOICE
? 1 Requirement Generation
8 Invoice verification
4 Order processing
23
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
SAP Process:
Several criteria are provided by the system for selecting Purchase Requisitions for
display and further processing including the status and source of requisitions.
EMBED Visio.Drawing.11
Procurement Cycle
Production Financial
Material Management
Planning Accounting
Quotation
Comparison
Outline
Agreement
Scheduling
Purchase Order Contract
Aggrement
24
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
25
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
SAP Process:
Currently at SBT quotations are invited and compared manually. Expectations include
that the quotations are recorded centrally and the comparison takes into account the
differing taxation structure into consideration for comparison the landed prices.
Mainly 03 quotations for a P.O.
Quotation Material Item wise.
27
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Process Explanation
Vendors can be selected for sending RFQs. Separate documents are sent to each of the
vendors along with all the conditions. The quotations received are entered. Comparison
is made for all quotations received. Most favorable quotation can be converted into an
Purchase order record.
Process Flow:
03 Enter Offer details SAP The details of vendor terms such as price,
delivery terms, payment terms, taxes
applicable are entered against each vendor
enquiry.
04 Compare quotes SAP All the captured quotes are compared and a
for prices/ terms comparison statement is prepared on
landed cost basis.
28
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Search approved vendors for the required material in the approved vendors list.
Conduct Negotiations with the vendors listed as per the Quotation received & finalized
the rates and select the vendor (The Orders are given verbally informed to vendor
through telephones).
Check for vendor, pricing conditions, quantity, quality, transport and other condition of
vendor in the PO/Contracts agreement.
Creation is done by Accounts Department.
The Contract document is finally approved by the Commercial head.
Creation of the delivery schedules (PO) as per the contract/PO.
Send Schedule (PO) copy to the vendor.
Confirmation recd by the vendor through Email/ telephone.
Order Follow up through email / telephone.
29
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Process Flow:
30
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
31
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Improvement Areas:
Vendor wise material price maintained in Info Records & referred to automatically
while creating PO/Scheduling Agreement.
Freight & other delivery charges built through a comprehensive pricing procedure
leading to Automatic material cost calculations.
Line item wise pricing available
View of Amendments for a P.O.
Reorder levels, safety stock, minimum & maximum stock levels defined in the system
& can be monitored.
Delivery schedules can be created & monitored for PO.
Control on base line date for payment.
Document flow and integration with other modules.
Easy for monitoring and follow-up actions by the buyers.
Material price is prompted from the last ordered price on the vendor material
combination.
Several materials are required regularly and the pricing and other terms are constant for
a longer term, normally corresponding to a financial year. At the same time the
requirements of such materials are generated through MRP.
32
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Contracts are also required for group of materials. Subsequently Scheduling Agreements
can be created with reference to the contract for materials under the group covered in the
contract. In Contracts & scheduling agreements item wise rate amendments can be
maintained.
Process Flow:
33
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
02 Printing of contract SAP The printed and approved document can be sent
to vendors.
Organizational Considerations:
Improvement Area:
AS-IS:
35
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
EMBED Visio.Drawing.11
36
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Production Financial
Material Management
Planning Accounting
Logistic Invoice
Verification for vendor
Clearing Transportation
Creation Goods receipt for Booking the
charges ,Document
Liability in SAP
charges etc.
37
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
SAP-Process:
Process Flow:
Currency exchange rates must be maintained in the system regularly to ensure that
the conversion is proper.
Condition records in the PO must be maintained carefully with clear specification of
rate, currency, and vendor.
Process Flow:
Improvement Areas:
Currency conversion.
SAP Process:
40
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Purchase Order release will be taken care by the system with appropriate release
Authority.
Purchase Order Copy will be downloading & send to the vendor thru Email.
Goods will be received from the vendor with reference to the PO.
Excise Invoice will be posted to the Excise Registers.
Invoice Verification.
41
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Controlling of inventory.
As per excise rules ensure that stocks with vendors do not remain with the vendors for
more than 180 days.
Sub-contracting challans (57 F4) and reconciliation records such as Annexure IV are
maintained as per excise rules.
Subsequent adjustment for weight difference due to scrap generation at vendor end.
Scrap is either brought back to SBT or sold directly by vendor. Both scenarios to be
accounted for.
For component which is going to be converted in labour charges steps are,
For excise duty purposes, there are two ways of handling excise duty on goods that are
provided to the sub-contractors:
43
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
SBT uses only the first type of subcontracting. As per rules under excise law 4(5)(b)
Process Flow:
vendor.
Improvement Areas:
Excise system fully integrated with other sub modules for all possible transactions.
Monitoring of components provided to vendors for subcontracting .
Appropriate inventory valuations linked to all movements.
Proper accounting of material document-wise.
A complete scenario (MRP, contract, info record, PR, BOM PO, 57 F (4) challan,
reconciliation, invoice verification) is captured within the system.
Several services are procured from vendors such as AMC contracts, consultancy services
etc.
45
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Process
Service Category:
46
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
SAP Process:
The same is handled in the system using the regular process of purchasing .The
following variations need to be ensured.
Process Flow:
04 Acceptance of Services SAP After recording the services that have been
Performed performed acceptance of satisfactory
performance can be confirmed.
47
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Improvement Areas
Purchase Order related to Account Assigned (Services) will be defined by the system
Service conditions can be maintained related to plant & vendor.
Release of PO’s with Authorized persons.
All materials received should be strictly against authorized requirements for the
specific date within defined tolerances of quantity and dates.
The system should be fully integrated with accounts for accurate material valuation
and accounts payable.
The process should ensure compliance with excise requirements.
48
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Process Flow:
03 Creation of incoming SAP The system has been set for automatic
excise invoice. creation of Part1 entry at time of posting
the GR. By capturing and posting of
invoice a part2 entry is created thereby
creating credit entry in the CENVAT
register and corresponding offsetting
accounting entry. Here again the details of
quantities, Excise duty paid, CENVAT
available are prompted by the system. If
the details are matching only the excise
invoice number and date need to be
entered.
As the Goods Receipts process is fully integrated with several functions following data
needs to be maintained:
The Goods receipt process in SAP is fully integrated with other areas in the
organization and enables automatic valuation, account assignment, creation of
inspection lots.
The excise recording system also ensures that all excise requirements are adhered to.
Customized solution to automate the no of entries at the time of making Goods
Receipt with reference to POs.
50
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
As Is
51
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Process Flow:
52
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Improvement Area:
As Is
4 Invoiced /Challan is certified for quantity & forwarded to Account dept for further
processing.
SAP Process
Goods receipt against purchase order is carried out through a standard transaction. The
quantity of materials received is input in the Goods Receipt document with the storage
location. If the quality inspection is active in quality management for material, quality
inspection stock will be generated. Further based on the quality of the material, it will be
53
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
released to unrestricted stock through usage decision. For Excisable goods, the excise
invoice can be captured and posted while posting the GR in the system or can be
captured separately using dedicated transaction in CIN.
As Is
1. The Goods received at plants are entered at security gate with following Info.
Date of receipt
Items & Description of Goods
Quantity
Name of Vendor
Invoice/Challan Ref No.
3. Invoiced /Challan is certified for quantity & forwarded to Account dept for further
processing.
4. Goods are posted in inward register.
SAP Process
The above processes of goods receipt (subcontract) are similar to the standard goods
receipt procedure .If the quality inspection is active for the material then the inspection
lot will be created in the system, as per the usage decision in the Quality Management
54
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
the material will be cleared for unrestricted use Stock.57F4 Challan can be created
through SAP CIN.
Goods Issue:
Goods issue is transacted through SAP standard movement types to production (cost
centres/ process orders)/quality inspection stock (Lab). The details of the requisition slip
can be entered on the material document (external material slip field on the material
document).
AS IS
SAP Process
We can use Stock transport Order for this scenario where material is transferred from
one plant to another with in a company code with sales cycle. Applicable Excise invoice
can be generated through CIN.
55
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Outward Entry is made by security at plant gate; it is tallied when material is returned
after processing.
SAP Process
This will be handled as parts provided to vendor in the system. A record of materials
with the subcontractor can be taken from the system in the form of report. Applicable
subcontracting Challan can be created with CIN.
8.4 Reservation
General Explanations
A reservation is a request to the warehouse to keep materials ready for a goods issue
at a later date and for a certain purpose.
A reservation for goods issue can be requested by various departments for various
account assignment objects (such as cost center, order, asset, etc.).
The purpose of a reservation is to ensure that a material will be available when it is
needed. It is also to simplify and accelerate the goods issue process and to prepare
the tasks at the point of goods issue.
Goods receipt: A goods receipt (GR) is a goods movement with which the receipt of
goods from a vendor or from production is posted. A goods receipt leads to an increase
in warehouse stock.
Goods issue: A goods issue (GI) is a goods movement with which a material withdrawal
or material issue, a material consumption, or a shipment of goods to a customer is
posted. A goods issue leads to a reduction in warehouse stock.
Transfer postings from material to material
56
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
When posting a goods movement in the SAP System, the following documents are
created.
Material document
A material document consists of a header and at least one item. The header contains
general data about the movement (for example, its date). Each item describes one
movement
Accounting document
If the movement is relevant for Financial Accounting (that is, if it leads to an update of
the G/L accounts), an accounting document is created parallel to the material document.
In some cases, several accounting documents are created for a single material
document. This might be the case, for example, if you have two material document
items with different plants that belong to different company codes.
The G/L accounts involved in a goods movement are updated through an automatic
account assignment.
Changes to a Document
Once you have posted a goods movement, you can no longer change the document. You
can only enter additional information in the document, such as the reference to the
original document, or a comment on the event. If you want to reverse the movement or
change the quantity of material moved, you must enter a new document.
Document Numbers
The material document number and the accounting document number are different.
When you enter a goods movement, you start the following chain of events in the
system:
57
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
The stock values in the material master record are updated, as are the stock and
consumption accounts.
Depending on the movement type, additional updates are carried out in participating
applications. All updates are based on the information contained in the material
document and the financial accounting document. For Example, in the case of a goods
issue for a cost centre, the consumption values of the items is also updated.
58
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
59
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
60
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Separate Debit note and excise reversal if material not send back to supplier and
scraped at storage location end.
Material can be send to vendors without reference if vendor code exists.
As Is
i. Date
ii. Invoice Number
iii. Supplier
iv. ECC NO
v. Date Of Invoice
vi. Value of Input
vii. BED
viii. ADI ( for import parts)
ix. CESS
x. HS EDU
xi. Chapter ID (Customer chapter Id)
xii. Unit
xiii. QTY
xiv. Description
Excise Duty
Basic excise duty 16%.
Education Cess @ 2% on Basic Excise Duty.
Secondary & higher Secondary Education Cess @ 1% on Basic Duty.
Service Tax
CENVAT
61
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
At time of GR the excise entries will get capture but posting will be done separately
The Excise posting will be done on below pricing procedure For Import
C – CESS 2% on CVD
E – Cess 2% on Total (A to D)
For Domestic
B – ECS 2% on BED
Or
Physical inventory is carried out at the end of every month to ensure that the inventory
value and consumption figures considered for financial statements are accurate.
Further it is requirement of the audit process conducted by the statutory auditor of the
company to verify the stock and consumption figures are accurately presented to the
stockholders of the company.
Periodic inventory
Continuous inventory
Cycle counting
At SBT Physical inventory Stock (periodic inventory method) taking is carried out
monthly wise for stocks based on Qty.
The system should be able to generate a list of materials and display the differences
between physical and book stocks. No movements should be permitted during the
physical counting.
63
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
64
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
05 Entering the count SAP The count results may be entered into the
results system. The system unblocks postings for
movements.
07 Going for a Recount SAP Results once entered into the system can
not be changed. Recount may be organised
with a new physical inventory document
65
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
In the SAP System, Vendor Evaluation has been completely integrated into the MM
Purchasing component within Materials Management. This means that information such
as delivery dates, quantities can be taken from purchase orders.
Vendor Evaluation also uses data from the Quality Management component, such as the
results of incoming inspections.
The Vendor Evaluation component helps user to select sources of supply and facilitates,
the continual monitoring of existing supply relationships. It provides with accurate
information on prices, and terms of payment and delivery. By evaluating vendors, user
can improve enterprise's competitiveness.
Main criteria’s for a vendor evaluation process will be Quality & Delivery. System will
provide a scoring range from 1 to 100 points, which is used to measure the performance
of your vendors on the basis of main criteria’s.
You can determine and compare the performance of your vendors by reference to their
overall scores.
Vendor Master: Vendor master Record will contain vendor currency, Terms of
payments, Contact Person.
Material Master: The individual material master records contain data such as the order
unit, responsible purchasing group, and over / under delivery tolerances.
Purchasing Info-Record: Purchasing info records are used as a source of information for
Purchasing. It represents a specific vendor-material relationship.
Sub - criteria are the smallest units for which scores are awarded in Vendor Evaluation.
Elements are Quality, Goods Receipt, On Time Delivery, and Quantity Reliability.
Description:
66
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
User has to define the weighting keys. A weighting key is an identifier under which the
weighting factors for a number of main criteria can be grouped together and saved.
Defining the main Criteria’s under which the evaluation of a vendor takes place .User
has to specify the scores (1 - 100) which has to be awarded to each criterion (Quality,
and Delivery).
Then Defining the Sub – Criteria’s (Automatic) which are the smallest units for which
scores are awarded in Vendor Evaluation. The system calculates the scores for
automatic sub-criteria on the basis of data from other areas of the enterprise outside
the Vendor Evaluation system (for example, Goods Receiving or Quality Management).
The Automatic Sub-Criteria’s are :
Quality:
Goods Receipt: This sub-criterion is used to evaluate the quality of the material that
the vendor delivers. Quality inspection takes place at the time of goods receipt.
User will enter the keys for the purchasing organization and vendor. An overview of
the main criteria for this purchasing organization.
Then the weighting will be entered in the system as defined by the user.
System will calculate the Scores Automatically.
Improvement Areas:
To view graphically the progress status of each criteria and overall criteria.
To incorporate Vendor's action plan for improving performance, in case of
unacceptable rating.
Material wise Vendor Evaluation needs to be compared.
Vendor evaluation is captured within the system
67
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
The Invoice Verification component is part of the materials system. It provides the link
between the Material Management component and the Financial Accounting, Costing
and Asset Accounting components.
68
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
It completes the material procurement process- which starts with purchase requisition,
continues with purchasing, goods receipt and ends with invoice receipt.
It allows invoices that do not originate in Material Management also to be processed
(Invoices for Services, Expenses etc.)
It allows credit memos to be processed either as cancellations or discounts.
Invoice verification does not handle payment or the analysis of invoices. The
information required for these processes is passed on to other departments.
Process Flow:
69
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
70
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Improvement Area:
Business Process:
Integration with FI module for processing invoices and status of the invoices should be
available and price changes need to be addressed in material valuation.
Description of Improvement
Raw Material or all externally procured materials are based on the moving average
price (MAP). The control indicator for the same in the system is V.
Finished Goods will be based on the Standard Price. The control indicator for the same
is S.
Manual activities involved are meant for serving the following purposes:
Revaluation of a material other than for physical inventory differences can be due to:
72
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
A price change
If the material price no longer corresponds to the current price, you can adjust it by
making a price change.
If the stock value of a material is to be increased or decreased, you can make a direct
credit or debit posting for this material.
14.0 Scrap
AS IS
All disposable items, which are treated as scrap, are transferred to a Scrap Storage
location. The scrap is sold to the best buyer. Process followed by SD department.
Asst manager
MD
To set up approval procedures for purchase requisitions or other purchasing documents, if a
purchase order document fulfils certain conditions, it has to be approved (by the manager, for
instance) before it can be processed further. This process of approving a proposed item of
expenditure is replicated in the AS-IS System by the "release procedure".
Three levels of approval will be available for purchase requisition and based on the approved
PR, purchase order is generated purchase department and approved by VP, GM, MD.
73
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
A company may have materials that are maintained in many locations within the same
system. Each month the previous posting period is closed and a new posting period is
opened. The period close program requires that no changes be made to material records
– including goods movements.
During the Month End closing the Values are transferred & the period is closed for the
pervious month.
74
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Manual Numbers of the Currently the numbers are IN SAP; the material master
material master assigned manually. This numbering is manually
results into the loss of entered as for as-is
Control.
75
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
4) No amendments would
be done in the purchase
orders except for the
material code, qty, plant,
vendor & purchasing
organization in the system.
76
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
verification.
4) No amendments would
be done in the purchase
orders except for the
material code, qty, plant,
vendor & purchasing
organization in the system.
4) No amendments would
be done in the purchase
orders except for the
material code, qty, plant,
vendor & purchasing
organization in the system.
77
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Authorized persons.
7) Quotations can be
analysed by the System.
Goods receipts Goods receipts for raw 1) All the goods receipts in
material, tools & spares, the system will be done with
consumables, capital goods, respect to purchase orders
imports, subcontracting. only.
3) Verification of Physical
inventory Card & Existing
System Stock with Physical
Stock.
78
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Goods Movements & Stores issues the material to 1) Goods issue against the
Reservations the production based on the production order.
manual issue slip/Indent.
2) Goods issue against the
reservation.
79
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
80
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
Standard – NB
Purchase Order will have Document types
NB Purchase Order
UB Stock Transfer
FO Framework PO
The purchasing document number ranges will be system generated. The Number range
is based on document type and will be set at the client level.
Remarks
S.no Description
1 REQUEST FOR QUOTATION To be customised
81
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
82
Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane
Project “VISION”
Document Business Blue Print Version 1
Module Materials Management No.
83