4 Class-contract Completed
4 Class-contract Completed
Deliberate abandonment
Waiver Novation
Giving up a right entitled to Sec. 62
Other party released from the obligation Parties to a contract agree to substitute a new contract /
It is a discharge under mutual consent to rescind / alter it
It is a kind of remission • the original contract need not be performed.
- A to perform something, other party later forbids it. Meaning
Accord and Satisfaction Wiping out of the original contract and creating of a new
One party to obtain release, agrees to do something other than valid contract in its place
what he is bound When a new contract is substituted for an existing
When he has discharged that obligation
When he is set free/released
contract
* Contract is said to discharged by accord and Satisfaction between the same parties
•
- Performance of contract is not A&S between different parties
•
- Mutual consent Nature of obligation changes
•
- Party gives something different Old obligation is extinguished
•
- Other accepts in satisfaction ‘Novation’ occurs.
•
- A builds house for consideration, after construction he is A owes B, agree that C will be debtor henceforth. Old debt of A has
offered a plot of land instead, which he accepts. ended and new debt from C is contracted.
“Sec 73. Compensation for loss or damage caused by breach of Reliance was placed on: M/s. Murlidhar Chiranjilal
Contract. - When a contract has been broken, the party who suffers by vs. M/s. Harishchandra Dwarkadas & Anr
such breach is entitled to receive, from the party who has broken the
contract, compensation for any loss or damage caused to him thereby, The two principles on which damages in such cases
which naturally arose in the usual course of things from such breach, are calculated are well-settled.
or which the parties knew, when they made the contract, to be likely to
result from the breach of it.
The first is that, as far as possible, he who has
Such compensation is not to be given for any remote and indirect
proved a breach of a bargain to supply what he
loss or damage sustained by reason of the breach. contracted to get is to be placed, as far as money can
Compensation for failure to discharge obligation resembling those do it, in as good a situation as if the contract had
created by contract. - When an obligation resembling those created by been performed;
contract has been incurred and has not been discharged, any person but this principle is qualified by a second, which
injured by the failure to discharge, it is entitled to receive the same
compensation from the party in default, as if such person had
imposes on a plaintiff the duty of taking all
contracted to discharge it and had broken his contract. reasonable steps to mitigate the loss consequent on
Explanation - In estimating the loss or damage arising from a breach the breach, and debars him from claiming any part
of contract, the means which existed of remedying the inconvenience of the damage which is due to his neglect to take
caused by non-performance of the contract must be taken into such steps
account.“ Copyright Protected - Adv. Beena Menon 100 Copyright Protected - Adv. Beena Menon 101
Copyright Protected - Adv. Beena Menon 110 Copyright Protected - Adv. Beena Menon 111
The true legal position in regard to the extension of time for It would be arbitrary for the DDA to forfeit the earnest
the performance of a contract is quite clear under s. 63 of the money on two fundamental grounds
Indian Contract Act.
First, there is no breach of contract on the part of the
Every promisee, as the section provides, may extend time appellant as has been held above.
for the performance of the contract.
There can be no doubt, we think, that both the buyer and the and Second, DDA not having been put to any loss, even if
seller must agree to extend time for the delivery of goods. DDA could insist on a contractual stipulation in its favour, it
It would not be open to the promisee by his unilateral act to would be arbitrary to allow DDA as a public authority to
extend the time for performance of his own accord for his appropriate Rs.78,00,000/without any loss being caused.
own benefit. The measure of damages in the case of breach of a stipulation
In Citi Bank N.A. v. Standard Chartered Bank – 2004 - held by way of penalty is by Section 74 reasonable compensation
Under Section 63, a promisee can act unilaterally and may not exceeding the penalty stipulated for. In assessing
(i) dispense with wholly or in part, or damages the Court has, subject to the limit of the penalty
(ii) remit wholly or in part, the performance of the promise stipulated, jurisdiction to award such compensation as it
made to him, or deems reasonable having regard to all the circumstances of
(iii) may extend the time for such performance, or the case.
(iv) may accept instead of it any satisfaction which he thinks The aggrieved party is entitled to receive compensation from
fit the party who has broken the contract, whether or not actual
118 damage or loss is proved to have been caused by the breach. 119
Copyright Protected - Adv. Beena Menon Copyright Protected - Adv. Beena Menon
It merely dispenses with proof of "actual loss or Section 73, when a contract has been broken, the party
who suffers by such breach is entitled to receive
damages"; compensation for any loss caused to him which the
It does not justify the award of compensation when parties knew when they made the contract to be likely
to result from the breach of it. This section is to be read
in consequence of the breach no legal injury at all with Section 74, which deals with penalty stipulated in
has resulted, because compensation for breach of the contract, inter alia (relevant for the present case)
contract can be awarded to make good loss or provides that when a contract has been broken, if a sum
is named in the contract as the amount to be paid in case
damage which naturally arose in the usual course of of such breach, the party complaining of breach is
things, or which the parties knew when they made entitled, whether or not actual loss is proved to have
the contract, to be likely to result from the breach. been caused, thereby to receive from the party who has
broken the contract reasonable compensation not
Referred to Maula Bux case exceeding the amount so named.
Jurisdiction of the court to award compensation in Section 74 emphasizes that in case of breach of contract,
the party complaining of the breach is entitled to
case of breach of contract is unqualified except as to receive reasonable compensation whether or not actual
the maximum stipulated; and compensation has to loss is proved to have been caused by such breach.
be reasonable Therefore, the emphasis is on reasonable compensation.
120
Copyright Protected - Adv. Beena Menon Copyright Protected - Adv. Beena Menon 121
(1) Terms of the contract are required to be taken into Section 74 will apply to cases of forfeiture of earnest
consideration before arriving at the conclusion whether the party
claiming damages is entitled to the same. money under a contract.
(2) If the terms are clear and unambiguous stipulating the
liquidated damages in case of the breach of the contract unless it is Where, however, forfeiture takes place under the
held that such estimate of damages/compensation is unreasonable terms and conditions of a public auction before
or is by way of penalty, party who has committed the breach is
required to pay such compensation and that is what is provided in agreement is reached, Section 74 would have no
Section 73 of the Contract Act. application
(3) Section 74 is to be read along with Section 73 and, therefore, in
every case of breach of contract, the person aggrieved by the breach There has been no breach of contract by the appellant
is not required to prove actual loss or damage suffered by him
before he can claim a decree. The court is competent to award Refund of earnest money with 9% was directed
reasonable compensation in case of breach even if no actual damage
is proved to have been suffered in consequence of the breach of a
contract.
(4) In some contracts, it would be impossible for the court to assess
the compensation arising from breach and if the compensation
contemplated is not by way of penalty or unreasonable, the court
can award the same if it is genuine pre-estimate by the parties as
the measure of reasonable compensation."
Copyright Protected - Adv. Beena Menon 122 Copyright Protected - Adv. Beena Menon
123
M/s Construction & Design vs Delhi Development There is no dispute that the appellant failed to execute
the work of construction of sewerage pumping station
Authority 4th February 2015 ,Supreme Court within the stipulated or extended time. The said
Constructing a sewerage pumping station pumping station certainly was of public utility to
maintain and preserve clean environment, absence of
When and to what extent can the stipulated which could result in environmental degradation by
liquidated damages for breach of a contract be stagnation of water in low lying areas. Delay also
resulted in loss of interest on blocked capital.
held to be in the nature of penalty in absence of
In these circumstances, loss could be assumed, even
evidence of actual loss without proof and burden was on the appellant who
To what extent the stipulation be taken to be the committed breach to show that no loss was caused by
delay or that the amount stipulated as damages for
measure of compensation for the loss suffered breach of contract was in the nature of penalty. Even if
even in absence of specific evidence technically the time was not of essence, it could not be
presumed that delay was of no consequence.
Liability claim was to pay Rs.20,86,446/- The party complaining of breach can certainly be
allowed reasonable compensation out of the said
amount if not the entire amount
Copyright Protected - Adv. Beena Menon 124 Copyright Protected - Adv. Beena Menon 125
Applying the above principle to the present case, it Brahmaputra Tea Co Vs Scarth - 1885
could certainly be presumed that delay in This appeal raises questions under Sections 27 and 74 of the Contract Act.
executing the work resulted in loss for which the Undertook to serve the Company as assistant tea-planter for a term of three
respondent was entitled to reasonable compensation. years, to be computed from the date of the termination of his fourth year's
service under a prior agreement. - gave notice of his intention to leave - he
Evidence of precise amount of loss may not be
actually did leave the Company's service without their consent after 6
possible but in absence of any evidence by the party months.
committing breach that no loss was suffered by the As, however, the agreement has long since expired, no injunction can now
party complaining of breach, the Court has to issue
proceed on guess work as to the quantum of The contract in the 10th Clause is void, so far as it restrains the defendant
compensation to be allowed in the given from taking service, or from engaging in, or promoting directly or
indirectly, the cultivation of tea for a period of five years from the date of
circumstances. Since the respondent also could have the termination of his agreement
led evidence to show the extent of higher amount The case clearly falls within Section 74 of the Contract Act, the effect of
paid for the work got done or produce any other which was to do away with the distinction between liquidated damages
specific material but it did not do so, we are of the and a penalty, and to leave it to the Court in all cases in which a sum is
named in the contract as the amount to be paid, to award against the party
view that it will be fair to award half of the amount who has broken the contract reasonable compensation not exceeding the
claimed as reasonable compensation. sum named.
Copyright Protected - Adv. Beena Menon 126 Copyright Protected - Adv. Beena Menon 127