Weekly Progress Table - Sample

The project progress report for the week of April 7 to April 13, 2025, indicates that overall progress is at 69.65%, with significant variances in various work breakdown structure (WBS) components. Mobilization, Engineering, and Procurement have notably low actual completion percentages compared to planned values, reflecting challenges in these areas. The report highlights a cumulative variance of -24.87% across all tasks, indicating a need for improved performance to meet project timelines.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views

Weekly Progress Table - Sample

The project progress report for the week of April 7 to April 13, 2025, indicates that overall progress is at 69.65%, with significant variances in various work breakdown structure (WBS) components. Mobilization, Engineering, and Procurement have notably low actual completion percentages compared to planned values, reflecting challenges in these areas. The report highlights a cumulative variance of -24.87% across all tasks, indicating a need for improved performance to meet project timelines.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT PROGRESS TABLE

Engr. Asad Rehman


[Type Project ID & Name here] Data Date: 4/13/2025
Weekly Progress Table: 07-04-25 to 13-04-25 | Week No # 10
Cumulative Previous This Period Overall Cumulative
Sr. No WBS Name Wtg%
Planned Actual Variance Planned Actual Variance Planned Actual Variance
1 Mobilization 0.15% 100.00% 89.56% -10.44% 0.00% 0.00% 0.00% 100.00% 89.56% -10.44%
2 Pre-Engineering 0.75% 99.76% 86.29% -13.47% 0.24% 0.89% 0.65% 100.00% 87.18% -12.82%
3 Engineering 4.50% 100.00% 74.82% -25.18% 0.00% 0.00% 0.00% 100.00% 74.82% -25.18%
4 Procurement 40.00% 93.52% 49.99% -43.53% 1.80% 4.02% 2.22% 95.32% 54.01% -41.31%
5 Construction 54.00% 99.14% 85.25% -13.89% 0.30% 1.06% 0.76% 99.44% 86.31% -13.13%
6 Testing & Commissioning 0.50% 57.64% 27.92% -29.72% 6.27% 1.71% -4.56% 63.91% 29.63% -34.28%
7 Project Closing 0.10% 3.89% 0.00% -3.89% 0.18% 0.00% -0.18% 4.07% 0.00% -4.07%
Overall Progress % 100.00% 65.95% 43.43% -22.52% 3.70% 1.35% -2.35% 69.65% 44.78% -24.87%

This Week Cumulative Overall Cumulative This Week Progress Planned Actual
69.65%

0.00% 1.00% 2.00% 3.00% 4.00% 5.00% 6.00% 7.00%


Mobilization 0.00%
0.00%
44.78%
Pre-Engineering 0.24%
0.89%

Engineering 0.00%
0.00%

Procurement 1.80%
4.02%

Construction 0.30%
3.70%

1.35%

1.06%
Testing & 6.27%
Commissioning 1.71%

Project Closing 0.18%


0.00%
PROJECT PROGRESS TABLE
Engr. Asad Rehman
[Type Project ID & Name here] Data Date: 4/13/2025
Weekly Progress Table: 07-04-25 to 13-04-25 | Week No # 10
Cumulative Previous This Period Overall Cumulative
Sr. No WBS Name Wtg%
Planned Actual Variance Planned Actual Variance Planned Actual Variance
1 Mobilization 0.15% 100.00% 89.56% -10.44% 0.00% 0.00% 0.00% 100.00% 89.56% -10.44%
2 Pre-Engineering 0.75% 99.76% 86.29% -13.47% 0.24% 0.89% 0.65% 100.00% 87.18% -12.82%
3 Engineering 4.50% 100.00% 74.82% -25.18% 0.00% 0.00% 0.00% 100.00% 74.82% -25.18%
4 Procurement 40.00% 93.52% 49.99% -43.53% 1.80% 4.02% 2.22% 95.32% 54.01% -41.31%
5 Construction 54.00% 99.14% 85.25% -13.89% 0.30% 1.06% 0.76% 99.44% 86.31% -13.13%
6 Testing & Commissioning 0.50% 57.64% 27.92% -29.72% 6.27% 1.71% -4.56% 63.91% 29.63% -34.28%
7 Project Closing 0.10% 3.89% 0.00% -3.89% 0.18% 0.00% -0.18% 4.07% 0.00% -4.07%
Overall Progress % 100.00% 65.95% 43.43% -22.52% 3.70% 1.35% -2.35% 69.65% 44.78% -24.87%

This Week Cumulative Overall Cumulative This Week Progress Planned Actual
69.65%

0.00% 1.00% 2.00% 3.00% 4.00% 5.00% 6.00% 7.00%


Mobilization 0.00%
0.00%
44.78%
Pre-Engineering 0.24%
0.89%

Engineering 0.00%
0.00%

Procurement 1.80%
4.02%

Construction 0.30%
3.70%

1.35%

1.06%
Testing & 6.27%
Commissioning 1.71%

Project Closing 0.18%


0.00%