ITP Control and Relay Panel
ITP Control and Relay Panel
1.1 Construction Drawing 100% Prior to Construction Activities Good for Construction Drawing Technical Specifications Owner's Approval Review R R/A R/A
1.2 Work Method Statement 100% Prior to Construction Activities Approved Method Statement IFC Drawing/ Documents Owner's Approval Review R R/A R/A
1.3 Inspection and Test Plan 100% Prior to Construction Activities Approved Inspection and Test IFC Drawing/ Documents Owner's Approval Review R R/A R/A
Plan
1.4 Approved Inspection Checklist 100% Prior to Construction Activities Approved Inspection Checklist IFC Drawing/ Documents Owner's Approval Review R R/A R/A
1.6 Electrical Testing Team Qualification and 100% Prior to Construction Activities Certificate of Qualification TESDA / other 3rd party Certificate Owner's Approval Review R R/A R/A
Certification
1.7 Permit from Responsible Government 100% Prior to Construction Activities Approved Permits Approved Permits Owner's Approval Review R R/A R/A
Agencies
2.0 Material Receipt
2.1 Receiving and Checking of Materials as per 100% Complete Materials as per Packing List Visual H W/A S
packing list
Design specification , Approved
2.2 Check for damage and/or defects 100% Prior to Installation Activities Material Acceptance Report Drawings, Manufacturer's No damage and/or defects Visual H W/A S
catalogue , Method Statement
2.3 Availability of Factory Test Reports 100% FAT Test Report provided Visual H W/A S
3.0 Storage
Materials are to be stored inside and covered Storage area is clean and free from dust, water
3.1 with polythene sheet 100% spillage, vermin, etc. Panels are covered with Visual H W/A S
polyethene sheet
Prior to Installation Activities Inspection Checklist Manufacturer Catalogue
3.2 Heavy materials are not to be stacked one 100% All panels including accessories are properly stored Visual H W/A S
above the other
4.0 Pre-Installation
4.1 Site Physical Layout as per approved drawing 100% Control and Relay Panels as per approved drawing Visual and Measurement H W/A S
/ design specification
Design specification , Approved
Ensure theres no fouling/clashing with Prior to Installation Activities Inspection Checklist Drawings, Manufacturer's
4.2 civil/structural 100% catalogue , Method Statement No clashing with other civil/structural components Visual and Measurement H W/A S
4.3 Raised floor level and readiness 100% Raised floor is leveled Visual and Measurement H W/A S
5.0 Installation
5.1 Placement of Panel 100% Panels are installed properly Visual H W/A S
5.2 Proper bolting with adjacent shipping section 100% Bolts are torque-tightened and marked Visual and Measurement H W/A S
5.3 Proper alignment,leveling and tag welding / 100% Panels are properly aligned and leveled Visual and Measurement H W/A S
bolting of panel with foundation
5.5 Polarity of DC and Phase Sequence of AC 100% Polarity and Phase Sequence are correct Visual and Measurement H W/A S
Source
5.6 Sealing of unused holes 100% All unused holes are properly sealed Visual H W/A S
6.2 Interlocks 100% Interlocks are checked based on interlock diagram Visual H W/A S
6.3 Testing numerical relays as per approved 100% Electrical Testing H W/A S
scheme ≤5% of the calculated time setting
6.4 Tightness of control and power cables 100% Control and power cable terminations are torque- Visual H W/A S
tightened and marked
6.5 Functional test of indication,breaker,isolation, 100% Functionality of all indicators, breakers, protection, and Visual H W/A S
tripping, metering as per approved scheme metering are working properly
Design specification , Approved
Prior to Commissioning Activities MVSG Test Report Drawings, Manufacturer's
catalogue , Method Statement, FAT
6.6 Secondary Injection for relays , transducers , 100% Report Electrical Testing H W/A S
meters ≤5% of the calculated time setting
6.7 Logical Operations of all equipment 100% Logical operations of all equipment are working properly Visual H W/A S
6.8 Check that no CT remains open 100% All CT are in closed position Visual H W/A S
6.9 Inter panel wiring 100% All inter panel wiring are properly terminated Visual H W/A S
6.10 Relay Setting 100% Actual relay setting is based on the approved protection Electrical Testing H W/A S
coordination study
Ma Kaizhi
Prepared By: Checked By: Reviewed By: Approved By:
GENERAL NOTES
1.
The first three incidents of each inspection or testing activity listed requires 100% participation by Owners Engineer Site Inspection Personnel. After this, Owners Engineer may adjust the levels of Owners Engineer participation based upon the contractor's performance
2. Surveillance: QAQC organization to monitor work in progress without notice from construction organization
Witness:
QA/ QC organization shall be notified of the timing of inspection or test in advance. However, the inspection or test shall be performed as schedule if Owners engineer QAQC organization representative is not present.
4.01
Comments:
Name:
Date:
Sign:
NA OK PL
1/1