MES Notes
MES Notes
Contract administration refers to the process of managing a construction contract from its start (award) to its end
(close-out). It involves ensuring that the project is executed as per the terms and conditions of the contract. This
includes managing communications, documentation, timelines, costs, quality, and resolving disputes.
In the public sector of Pakistan, such as MES or C&W departments, contract administration follows rules issued
by the Pakistan Engineering Council (PEC), Public Procurement Regulatory Authority (PPRA), and department-
specific manuals.
• Employer / Client: The owner of the project (e.g., Military Engineering Services). They finance the project
and provide the overall direction.
• Consultant / Engineer: Often a design firm or the government’s engineering wing responsible for
technical supervision, drawing preparation, and certifying bills.
• Contractor: The party who executes the work. They are bound to complete the project according to
drawings, specifications, and within the timeline.
• Engineer’s Representative: Supervises the daily works and acts as a bridge between the contractor and
client.
1. Kick-off Meeting: Held at the start of the project. Contract clauses, drawings, work methodology, and
schedule are discussed.
2. Issuance of Work Order: After acceptance of the bid, a formal work order is issued.
4. Monitoring Work Progress: The consultant supervises the work and ensures that the contractor adheres
to specifications and time schedules.
5. Managing Variations: Changes to design or scope due to unforeseen conditions must be documented as
variation orders with revised cost or time.
6. Dispute Resolution: Disagreements can be settled through negotiations, arbitration (under Pakistan
Arbitration Act), or court.
• Agreement Form
• Specifications
• Drawings
• Schedule of Work
2. Tender Documents, Bills of Quantities, Specifications, and Conditions
Tendering is the formal process of inviting bids from contractors for executing a project. In Pakistan, tenders must
follow the PPRA Rules and relevant departmental SOPs.
1. Notice Inviting Tender (NIT): Published in newspapers and on PPRA websites. It includes basic project
details like location, estimated cost, bid submission date, etc.
3. Form of Bid: A declaration by the contractor agreeing to perform the work at the quoted rate.
4. BOQ (Bill of Quantities): A detailed list of work items with estimated quantities. The contractor quotes
unit rates against each item.
5. Technical Specifications: These are standards for construction materials, workmanship, tests, and
tolerances. They ensure uniformity and quality. MES and PEC have their own specification books.
6. Conditions of Contract:
o General Conditions: Payment mode, site conditions, delay penalties, dispute resolution.
o Special Conditions: Unique requirements related to site, security clearance, military sensitivity,
etc.
• Item Rate Contract: Payment based on the quantities of work done, measured and paid at agreed rates
(widely used in MES).
• Lump Sum Contract: A fixed total price for entire work regardless of quantities.
• Cost Plus Contract: Actual cost + a fee. Not commonly used in public departments.
This is the process of ensuring that the work is being done on time and as planned. In public projects, delays lead
to cost overruns and administrative complications, so close monitoring is essential.
Monitoring Tools:
1. Bar Charts / Gantt Charts: Simple timelines showing start and finish dates of activities. MES projects
often use bar charts for internal planning.
2. Critical Path Method (CPM): Advanced planning technique showing which activities are critical to the
project timeline.
3. Work Schedules: The contractor must submit a detailed work schedule before starting.
4. Progress Reports:
• Excusable Delays: Natural calamities, non-availability of site, law & order issues. These may lead to
Extension of Time (EOT).
• Non-Excusable Delays: Delay in procurement, labor shortages, etc. Contractor may face penalties.
Importance:
Supervision ensures that the quality of work matches design specifications. In MES and other public
departments, this is vital because the government pays public money.
Supervision Includes:
• Concrete:
• Soil:
• Steel:
• Bitumen:
Documentation:
• Site Instructions
Types of Payments:
• Mobilization Advance: Paid at the start (usually 10%). Recoverable from interim bills.
• Retention Money: 6–10% deducted from every bill and held until the defect liability period ends (usually 6
to 12 months).
In large civil works, especially those involving installations (like HVAC, water supply, pumps, generators, etc.), it's
essential to inspect the equipment before it’s put into operation. Equipment failures post-installation can result
in project delays and financial losses.
Key Phases:
a) Pre-Delivery Inspection:
Before equipment is delivered to the site, engineers may visit the supplier or manufacturer to inspect:
For example: If MES is procuring a diesel generator for a mess building, it will inspect the load capacity and fuel
consumption beforehand.
c) Installation Inspection:
• Ensure the alignment, fitting, and anchoring are as per technical drawings.
• Utilities like electric supply, drainage, and ventilation are connected correctly.
d) Testing and Commissioning:
This stage ensures the system runs under actual load conditions.
• Functionality Test: Checks all performance aspects (speed, output, safety alarms).
e) Handing Over:
After successful commissioning, the contractor hands over the system along with:
• Operation manuals
• Maintenance schedule
• Warranty card
7. Post-Construction Services
After physical completion, the project enters into a maintenance and post-handover phase. MES and other
departments often require the contractor to stay responsible for certain services.
a) As-Built Drawings:
• These are revised versions of drawings submitted by the contractor showing the exact dimensions,
locations, and conditions of the completed project.
b) Operation Manuals:
• For mechanical or electrical systems, the supplier provides manuals explaining operation,
troubleshooting, and maintenance schedules.
• If any structural or mechanical defects appear, the contractor must repair them at no extra cost.
• Includes financial summary, lessons learned, technical challenges faced, and suggestions for future
projects.
8. Operation and Maintenance (O&M)
This is the backbone of long-term infrastructure sustainability. MES often operates facilities like residential
quarters, military hospitals, office buildings, and water supply systems, so O&M is crucial.
Operation:
• Ensures that buildings, water supply, electrical systems, HVAC, and other utilities function smoothly.
Maintenance Types:
a) Routine Maintenance:
b) Preventive Maintenance:
c) Corrective Maintenance:
d) Emergency Maintenance:
• Every system or equipment has a logbook showing history of service, repairs, inspections.
Purpose:
To ensure the structural integrity, functionality, and safety of buildings, especially in sensitive military areas
managed by MES.
Types of Inspections:
Frequency:
Reports:
These rules regulate how public sector organizations in Pakistan procure goods, services, and works. MES must
follow these rules for transparency, competition, and value for money.
Key Concepts:
a) Procurement Methods:
• Direct Contracting
b) Thresholds:
d) Blacklisting of Firms:
e) Grievance Redressal:
• Bidders can file a complaint if they feel unfairly treated.
f) Record Keeping:
• All documents must be kept for at least 5 years for audit purposes.