Revised Programme-as per EOT-01 - Copy
Revised Programme-as per EOT-01 - Copy
9 Traffic Safety and Control 668 days Wed 10/26/22 Fri 8/23/24
10 Environmental and Social Management and Screening 668 days Wed 10/26/22 Fri 8/23/24
13 Road No.01- KURU 42- Road from Maharachchimulla to 436 days Wed 10/26/22 Thu 1/4/24
Wenaruwa(4.34km)
14 1. Possession of Site 1 day Wed 10/26/22 Wed 10/26/22
22 4.1 Road Structures and Drains 276 days Tue 4/4/23 Thu 1/4/24
27 4.2.1 Clearing and Grubbing 100 days Tue 4/4/23 Wed 7/12/23
28 4.2.2 Removing trees/ existing structures 100 days Tue 4/4/23 Wed 7/12/23
30 4.2.4 Sub grade preparation 100 days Tue 4/18/23 Wed 7/26/23
35 4.2.9Tack Coat and Asphalt 120 days Tue 5/23/23 Tue 9/19/23
36 4.2.10 Shoulder top layer construction 120 days Wed 8/23/23 Wed 12/20/23
Page 1
ID Task
Task Name DurationStart Finish
Mode
2022 2023 2024 2025 2026
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q
42 5.1 Handed over (03/01/24) 1 day Thu 1/4/24 Thu 1/4/24
43 Road No.02- KURU 65- Road from palawaththa 393 days Tue 2/28/23 Tue 3/26/24
transformer to Dambadeniya fuel Station (7.56km)
44 1. Possession of Site 0 days Tue 2/28/23 Tue 2/28/23 2/28
45 2. Surveying 28 days Tue 2/28/23 Mon 3/27/23
52 4.1 Road Structures and Drains 291 days Sat 5/20/23 Tue 3/5/24
55 4.1.3 Retaining wall construction 120 days Sat 5/20/23 Sat 9/16/23
57 4.2.1 Clearing and Grubbing 115 days Sat 6/3/23 Mon 9/25/23
58 4.2.2 Removing trees/ existing structures 115 days Tue 6/6/23 Thu 9/28/23
60 4.2.4 Sub grade preparation 115 days Fri 6/30/23 Sun 10/22/23
65 4.2.9Tack Coat and Asphalt 115 days Tue 9/5/23 Thu 12/28/23
66 4.2.10 Shoulder top layer construction 58 days Mon 1/8/24 Tue 3/5/24
73 Road No.03- KURU39- Road from Waguruwela via 319 days Tue 10/10/23 Fri 8/23/24
Yayamulla to Nedalagamuwa (3.83km)
74 1. Possession of Site 0 days Tue 10/10/23 Tue 10/10/23 10/10
75 2. Surveying 28 days Tue 10/10/23 Mon 11/6/23
76 2.1 Surveying (GPS, Control Point 14 days Tue 10/10/23 Mon 10/23/23
Establishment&Road Geometry Survey)
77 2.2 Pavement&Geometric Survey 14 days Tue 10/24/23 Mon 11/6/23
Page 2
ID Task
Task Name DurationStart Finish
Mode
2022 2023 2024 2025 2026
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q
82 4.1 Road Structures and Drains 192 days Mon 2/5/24 Wed 8/14/24
83 4.1.1 Widening/Reconstruction of Culverts 100 days Mon 2/5/24 Tue 5/14/24 1 Cube Tipper,Bob Cat,JCB,Porker Vibrator,Soil Compactor,Vibro Roller - 1 Tone,Water Bo
84 4.1.2 Construction of Drains as directed by the Eng
42 days Thu 7/4/24 Wed 8/14/24 1 Cube Tipper,Bob Cat,JCB,Porker Vibrator,Soil Compactor,Vibro Roller - 1 Ton
85 4.1.3 Retaining wall construction 100 days Mon 2/5/24 Tue 5/14/24 2 Cube Tipper,Bob Cat,JCB,Soil Compactor,Vibro Roller - 1 Tone,Water Bouser
86 4.2 Road Works 149 days Thu 3/28/24 Fri 8/23/24
87 4.2.1 Clearing and Grubbing 85 days Thu 3/28/24 Thu 6/20/24 2 Cube Tipper,JCB,Mortor Grader
88 4.2.2 Removing trees/ existing structures 85 days Sun 3/31/24 Sun 6/23/24
89 4.2.3 Roadway Excavations 85 days Wed 4/3/24 Wed 6/26/24 1 Cube Tipper,JCB
90 4.2.4 Sub grade preparation 85 days Sun 4/7/24 Sun 6/30/24 Soil Compactor,Vibro Roller - 1 Tone,Vibro Roller - 4 Tone,Water Bouser
91 4.2.5 Embankment Construction 85 days Tue 4/9/24 Tue 7/2/24 1 Cube Tipper,Bob Cat,Crew Cab,JCB,Mortor Grader,Vibro Roller - 1 Tone,Vibro Rol
92 4.2.6Sub Base and Shoulder 1st layer Construction
85 days Fri 4/12/24 Fri 7/5/24 2 Cube Tipper,Bob Cat,Crew Cab[2],JCB,Mortor Grader,Vibro Roller - 1 Tone,Vibro
93 4.2.7Aggregate Base Constructions 85 days Fri 4/19/24 Fri 7/12/24 2 Cube Tipper,Crew Cab[2],JCB,Mortor Grader,Vibro Roller - 10 Tone,Water Bouse
94 4.2.8 Prime Coat 78 days Fri 5/3/24 Fri 7/19/24 Air Compressor,Bitumen Bouser,Crew Cab,Bob Cat With Broomer
95 4.2.9Tack Coat and Asphalt 79 days Fri 5/10/24 Sat 7/27/24 Air Compressor,Asphalt Pavor,Bitumen Bouser,Crew Cab[3],Penumetic Tyred Ro
96 4.2.10 Shoulder top layer construction 36 days Thu 7/4/24 Thu 8/8/24 Bob Cat,Crew Cab[2],JCB,Mortor Grader,Vibro Roller - 1 Tone,Vibro Roller - 4 T
97 4.3 Incidential Constructions 14 days Fri 8/9/24 Thu 8/22/24
98 4.3.1 Trafic Signs 9 days Fri 8/9/24 Sat 8/17/24 1 Cube Tipper,Crew Cab
99 4.3.2 Road marking 9 days Fri 8/9/24 Sat 8/17/24 1 Cube Tipper,Crew Cab,Water Bouser
100 4.3.3 Grass Sodding 14 days Fri 8/9/24 Thu 8/22/24 1 Cube Tipper,Crew Cab,JCB,Water Bouser
101 5. Handing over 1 day Fri 8/23/24 Fri 8/23/24
103 Road No.04- KURU 40- Road from Daraluwa to 330 days Tue 9/26/23 Tue 8/20/24
waguruwela road (3.9km)
104 1. Possession of Site 0 days Tue 9/26/23 Tue 9/26/23 9/26
105 2. Surveying 28 days Tue 9/26/23 Mon 10/23/23
112 4.1 Road Structures and Drains 191 days Sun 1/28/24 Mon 8/5/24
113 4.1.1 Widening/Reconstruction of Culverts 120 days Sun 1/28/24 Sun 5/26/24 1 Cube Tipper,Bob Cat,JCB,Porker Vibrator,Soil Compactor,Vibro Roller - 1 Tone,Water B
114 4.1.2 Construction of Drains as directed by the Eng
43 days Mon 6/24/24 Mon 8/5/24 1 Cube Tipper,Bob Cat,JCB,Porker Vibrator,Soil Compactor,Vibro Roller - 1 Tone
115 4.1.3 Retaining wall construction 120 days Fri 3/1/24 Fri 6/28/24 2 Cube Tipper,Bob Cat,JCB,Soil Compactor,Vibro Roller - 1 Tone,Water Bouser
116 4.2 Road Works 155 days Sun 1/28/24 Sun 6/30/24
117 4.2.1 Clearing and Grubbing 90 days Sun 1/28/24 Fri 4/26/24 2 Cube Tipper,JCB,Mortor Grader
118 4.2.2 Removing trees/ existing structures 90 days Sun 1/28/24 Thu 6/27/24
119 4.2.3 Roadway Excavations 90 days Tue 1/30/24 Sun 4/28/24 1 Cube Tipper,JCB
120 4.2.4 Sub grade preparation 90 days Tue 2/27/24 Sun 5/26/24 Soil Compactor,Vibro Roller - 1 Tone,Vibro Roller - 4 Tone,Water Bouser
121 4.2.5 Embankment Construction 90 days Tue 3/12/24 Sun 6/9/24 1 Cube Tipper,Bob Cat,Crew Cab,JCB,Mortor Grader,Vibro Roller - 1 Tone,Vibro Roller
122 4.2.6Sub Base and Shoulder 1st layer Construction
90 days Sun 3/17/24 Fri 6/14/24 2 Cube Tipper,Bob Cat,Crew Cab[2],JCB,Mortor Grader,Vibro Roller - 1 Tone,Vibro Ro
Page 3
ID Task
Task Name DurationStart Finish
Mode
2022 2023 2024 2025 2026
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q
123 4.2.7Aggregate Base Constructions 90 days Mon 3/25/24 Sat 6/22/24 2 Cube Tipper,Crew Cab[2],JCB,Mortor Grader,Vibro Roller - 10 Tone,Water Bouser
124 4.2.8 Prime Coat 90 days Sat 3/30/24 Thu 6/27/24 Air Compressor,Bitumen Bouser,Crew Cab,Bob Cat With Broomer
125 4.2.9Tack Coat and Asphalt 89 days Mon 4/1/24 Fri 6/28/24 Air Compressor,Asphalt Pavor,Bitumen Bouser,Crew Cab[3],Penumetic Tyred Roller
126 4.2.10 Shoulder top layer construction 30 days Sat 6/1/24 Sun 6/30/24 Bob Cat,Crew Cab[2],JCB,Mortor Grader,Vibro Roller - 1 Tone[2],Vibro Roller - 4 Ton
127 4.3 Incidential Constructions 25 days Fri 7/19/24 Mon 8/12/24
128 4.3.1 Trafic Signs 18 days Fri 7/19/24 Mon 8/5/24 1 Cube Tipper,Crew Cab
129 4.3.2 Road marking 18 days Fri 7/19/24 Mon 8/5/24 1 Cube Tipper,Crew Cab,Water Bouser
130 4.3.3 Grass Sodding 18 days Fri 7/26/24 Mon 8/12/24 1 Cube Tipper,Crew Cab,JCB,Water Bouser
131 5. Handing over 1 day Tue 8/20/24 Tue 8/20/24
132 5.1 Handing over (8/21/2024) 1 day Tue 8/20/24 Tue 8/20/24
133 Road No. 05 - KURU32- Road from Ambawa to Galpola 410 days Sat 5/13/23 Tue 6/25/24
pansal junction (7.185km)
134 1. Possession of Site 0 days Sat 5/13/23 Sat 5/13/23 5/13
135 2. Surveying 28 days Sat 5/13/23 Fri 6/9/23
139 3.1 Geometric& Pavement Designs & Approvals 30 days Tue 11/7/23 Wed 12/6/23
142 4.1 Road Structures and Drains (4/30) 184 days Mon 12/11/23 Tue 6/11/24
143 4.1.1 Widening/Reconstruction of Culverts 110 days Thu 12/21/23 Mon 4/8/24
146 4.2 Road Works 1/3/2023 174 days Thu 12/21/23 Tue 6/11/24
147 4.2.1 Clearing and Grubbing 90 days Thu 12/21/23 Tue 3/19/24
148 4.2.2 Removing trees/ existing structures 90 days Mon 12/25/23 Sat 3/23/24
150 4.2.4 Sub grade preparation 90 days Tue 1/2/24 Sun 3/31/24
155 4.2.9Tack Coat and Asphalt 90 days Sun 1/28/24 Fri 4/26/24
156 4.2.10 Shoulder top layer construction 82 days Fri 3/22/24 Tue 6/11/24 Bob Cat,Crew Cab[2],JCB,Mortor Grader,Vibro Roller - 1 Tone,Vibro Roller - 4 Tone
157 4.3 Incidential Constructions 24 days Sat 6/1/24 Mon 6/24/24
158 4.3.1 Trafic Signs 13 days Wed 6/12/24 Mon 6/24/24 1 Cube Tipper,Crew Cab
159 4.3.2 Road marking 13 days Wed 6/12/24 Mon 6/24/24 1 Cube Tipper,Crew Cab,Water Bouser
160 4.3.3 Grass Sodding 24 days Sat 6/1/24 Mon 6/24/24 1 Cube Tipper,Crew Cab,JCB,Water Bouser
161 5. Handing over 1 day Tue 6/25/24 Tue 6/25/24
Page 4
ID Task
Task Name DurationStart Finish
Mode
2022 2023 2024 2025 2026
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q
163 Road No.06- KURU36- Balance section of yagamwela to- 406 days Sun 7/2/23 Sat 8/10/24
Padiwela Road (5.46km)
164 1. Possession of Site 0 days Sun 7/2/23 Sun 7/2/23 7/2
165 2. Surveying 28 days Sun 7/2/23 Sat 7/29/23
169 3.1 Geometric&Pavement Designs& Approvals 45 days Sun 7/30/23 Tue 9/12/23
172 4.1 Road Structures and Drains 124 days Tue 4/9/24 Sat 8/10/24
173 4.1.1 Widening/Reconstruction of Culverts 86 days Tue 4/9/24 Wed 7/3/24 1 Cube Tipper,Bob Cat,JCB,Porker Vibrator,Soil Compactor,Vibro Roller - 1 Tone,Wa
174 4.1.2 Construction of Drains as directed by the Eng
60 days Wed 6/12/24 Sat 8/10/24 1 Cube Tipper,Bob Cat,JCB,Porker Vibrator,Soil Compactor,Vibro Roller - 1 Ton
175 4.1.3 Retaining wall construction 86 days Tue 4/9/24 Wed 7/3/24 2 Cube Tipper,Bob Cat,JCB,Soil Compactor,Vibro Roller - 1 Tone,Water Bouser
176 4.2 Road Works 185 days Thu 12/28/23 Sat 6/29/24
177 4.2.1 Clearing and Grubbing 90 days Thu 12/28/23 Tue 3/26/24 2 Cube Tipper,JCB,Mortor Grader
178 4.2.2 Removing trees/ existing structures 90 days Thu 1/4/24 Tue 4/2/24
179 4.2.3 Roadway Excavations 90 days Thu 1/4/24 Tue 4/2/24 1 Cube Tipper,JCB
180 4.2.4 Sub grade preparation 90 days Thu 1/11/24 Sun 5/5/24 Soil Compactor,Vibro Roller - 1 Tone,Vibro Roller - 4 Tone,Water Bouser
181 4.2.5 Embankment Construction 90 days Thu 1/18/24 Sat 5/11/24 1 Cube Tipper,Bob Cat,Crew Cab,JCB,Mortor Grader,Vibro Roller - 1 Tone,Vibro Roller - 4
182 4.2.6 Sub Base and Shoulder 1st layer Construction
90 days Thu 1/25/24 Sat 5/18/24 2 Cube Tipper,Bob Cat,Crew Cab[2],JCB,Mortor Grader,Vibro Roller - 1 Tone,Water Bous
183 4.2.7 Aggregate Base Constructions 90 days Thu 2/1/24 Sat 5/25/24 Crew Cab[2],JCB,Mortor Grader,Water Bouser,2 Cube Tipper,Vibro Roller - 10 Tone
184 4.2.8 Prime Coat 95 days Thu 2/1/24 Sun 6/2/24 Air Compressor,Bitumen Bouser,Crew Cab,Bob Cat With Broomer
185 4.2.9 Tack Coat and Asphalt 95 days Mon 2/5/24 Tue 6/11/24 Air Compressor,Asphalt Pavor,Bitumen Bouser,Crew Cab[3],Penumetic Tyred Roller[3
186 4.2.10 Shoulder top layer construction 48 days Mon 5/13/24 Sat 6/29/24 Bob Cat,Crew Cab[2],JCB,Mortor Grader,Vibro Roller - 1 Tone,Vibro Roller - 4 Tone
187 4.3 Incidential Constructions 31 days Tue 6/25/24 Thu 7/25/24
188 4.3.1 Trafic Signs 15 days Thu 7/4/24 Thu 7/18/24 1 Cube Tipper,Crew Cab
189 4.3.2 Road marking 15 days Thu 7/4/24 Thu 7/18/24 1 Cube Tipper,Crew Cab,Water Bouser
190 4.3.3 Grass Sodding 31 days Tue 6/25/24 Thu 7/25/24 1 Cube Tipper,Crew Cab,JCB,Water Bouser
191 5. Handing over 1 day Sat 8/10/24 Sat 8/10/24
192 5.1 Handing over (26/07) 1 day Sat 8/10/24 Sat 8/10/24
193 3. project Handing over 0 days Fri 8/23/24 Fri 8/23/24 8/23
Page 5