3388323 - Executing and Monitoring Downtime-Optimized Conversion
3388323 - Executing and Monitoring Downtime-Optimized Conversion
Symptom
You want to use the Software Update Manager 2.0 for the downtime-optimized conversion to SAP S/4HANA, that is, you want
to significantly reduce the technical downtime for the conversion of your SAP system to SAP S/4HANA (on-premise edition).
This Note contains important information about executing and monitoring the downtime-optimized conversion such as
specific preparation activities, and known errors in the conversion process and their fixes. The Note also gives the most recent
and additional information to the downtime-optimized conversion guide that is available in the SAP Help Portal
at Downtime-Optimized Conversion To SAP S/4HANA Using SUM 2.0 - SAP Help Portal.
Other Terms
SUM, Software Update Manager, S/4HANA, conversion, downtime-optimized
If the source system is already on SAP HANA SAP HANA 2.0 SPS 05 rev 52 or higher
The downtime-optimized conversion supports the following source database types. The SAP Kernel requirements for each supported database type
are listed in the following SAP Notes:
Correction to chapter "Planning" section "Downtime and Business Restrictions", paragraph "Caution":
"Additionally, starting with the Asset Accounting lock, the Software Update Manager locks the following transactions in the
source system till the end of the downtime:
SARA
KA12
KA16
AS91
AJRW
AJAB"
Interference with Other SUM Scenarios
"DMO with System Move" is not possible for a downtime-optimized conversion.
"DMO Move to SAP S/4HANA (on Hyperscaler)", aka DMOVE2S4, is supported for downtime-optimized conversion.
For more information, see sub-section "DMO Move to SAP S/4HANA (on Hyperscaler)" in the DMO guide on SAP Help
Portal.
Data transition validation (DTV) can be used for a downtime-optimized conversion run. This is a tool that allows you to
compare business data before and after a system conversion from SAP ERP to SAP S/4HANA. DTV is available as part of
the standard license. For more information about the DTV tool, see SAP Note 3117879.
Application-Specific Restrictions
Account-based CO-PA (account-based profitability analysis) must not be used in the source system.
Source systems with MFLE / DIMP-LAMA active are not supported
For more prerequisites and restrictions for MM-IM, see SAP Note 2281657- S/4HANA MM-IM migration by SUM with sMIG
feature.
For more prerequisites and restrictions, see the downtime-optimized conversion guide that is available on the SAP Help
Portal:
Downtime-Optimized Conversion To SAP S/4HANA Using SUM 2.0 - SAP Help Portal
Solution
Preparation and Execution of the Downtime-Optimized Conversion to SAP S/4HANA
For all preparation steps, follow the instructions under the Preparation section of the "Downtime-optimized DMO with SUM
2.0" SAP Note 2547309 - Downtime-optimized DMO with SUM 2.0.
Prior to starting the downtime-optimized conversion run on the source system, it is required that the SUM Toolbox is
installed on the source system, and the file ZDIMPANA.ZIP from the impact analysis is provided in the download directory.
Impact Analysis
Impact Analysis is mandatory for the execution of downtime-optimized conversion as described in SAP Notes 2481983 -
SUM Impact Analysis for downtime-optimized DMO / downtime-optimized Conversion and 2402270 - Export of Table
Statistics for SUM Impact Analysis.
Archiving
Before the conversion:
Before the conversion of the production landscape starts, do archive as much as possible of your data due to the following
reasons:
To reduce the data volume that needs to be converted
Previous booking periods might contain inconsistant data that can lead to increased effort during the SAP S/4HANA
conversion project
During the conversion:
For more information about all archiving objects, see the attached PDF document.
CAUTION: The archiving objects listed in the attached PDF document must not be used for archiving during the conversion.
Otherwise, migrated and converted data might be archived and deleted that must be replicated and converted again during
the downtime!
Delta Load and Replication Test
In order to test the Change Record & Replay mechanism and the delta processing within the technical downtime, we
recommend that you simulate productive activity in your sandbox environment. For this purpose, we recommend that you
use software testing tools or database scripts of your choice.
Delta Load Verification Requires Virtualization and Isolation of Clone
The concept of Delta Load Verification (as explained in the ADM329 training) aims to simulate the downtime of the
downtime-optimized conversion approach on production-like hardware. A clone of the production system is created at the
time of the downtime dialog. This only works if the clone is created using virtualization, so that the clone is identical from
perspective of the SUM tool (for example same host names). In addition, the clone must be completely isolated from the
network of the production system.
Performance of Phase SQLRUNTASK_FDCT_TRANSFER_DIRECT on SAP HANA
The Fast Data Copy transfer, which is executed in the phase "SQLRUNTASK_FDCT_TRANSFER_DIRECT" has a high
impact on the performance of the SAP HANA database. Especially the I/O performance of a productive system needs to be
monitored during the execution of this phase.
A good starting point for a health check of your SAP HANA database is SAP Note 1999993 - How-To: Interpreting SAP HANA
Mini Check Results, which describes how to use and interpret the results of the SAP HANA mini checks.
To ensure a stable and consistent data copy, as of SUM 2.0 SP10 patch level 4, SUM by default sets the number of processes
for the execution of the SQL statements of the phase "SQLRUNTASK_FDCT_TRANSFER_DIRECT" to 2, which has been
tested and validated by SAP.
In case you have serious business requirements to minimize the runtime of the phase
"SQLRUNTASK_FDCT_TRANSFER_DIRECT" and a performance analysis of the productive system’s SAP HANA database
shows that more parallel processes can be used without impacting the performance and stability of the SAP HANA database,
the number of parallel DDL processes can be increased:
Create the file <DIR_PUT>/abap/bin/SAPup_add.par if it does not exist already and add the following line to increase the
number of DDL processes:
/SQLRUNTASK_FDCT_TRANSFER_DIRECT/HDB/parprocs/DDL = <number of parallel processes>
Remark: Please also consider the load on the productive system during this analysis. Setting the number of DDL processes to
a higher value can lead to a massive impact on the productive system and a significant database slowdown.
Start of Application Servers on IBM DB2 for LUW or IBM DB2 for z/OS
On systems running with IBM DB2 database, application servers must not be started or restarted between the
phases "MODPROF_IUUCHOOK" and "SQLRUNTASK_RRC_HOOK".
Problems During the Conversion
-----------------------< D029945 21/MAR/2024 >--------------------------
Impact analysis for source system on SAP BASIS level < 7.40
For source systems based on SAP BASIS 7.31 or lower, you must set the following parameter in file
SUM/abap/bin/SAPup_add.par
IMPACT_ANALYSIS_STBX=OFF
Only then, the impact analysis works as required, and the phase RUN_IMPACT_ANALYSIS_DODMO is executed
and ask for development support with reference to SAP Note 3388323
Chronological Summary
Date................Section...........Short description
-----------------------------------------------------------------------
21/MAR/2024...Impact analysis for source on SAP BASIS < 7.40
12/MAR/2024...Problems During the Conversion
05/JAN/2023 ... Handling of Conversion erros during Load Verification
06/SEP/2023 ... Recommendation for source on SAP HANA DB
27/JUL/2023 ... Reason and Prerequisites ... Data Transition Validation
27/JUL/2023 ... Solution ... Problems During the Conversion
17/JUN/2022 ... Solution ... SAP HANA 2.0 SPS 05 or Lower Only: SLT trigger handling on Shadow Field Tables like KONV
and VBFA
12/JUN/2023... Reason and Prerequisites ... Target product version SAP S/4HANA 2021 (or higher)
26/OCT/2021 ... Solution ... Problems During the Conversion
07/OCT/2021 ... Solution ... List of archiving objects updated
30/JUN/2021 ... Solution ... Comment on Delta Load Verification
22/JUN/2021 ... General ... Initial release of SAP Note
This document refers to
SAP Component Title
Note/KBA
3347255 BC-UPG-DTM- Executing and Monitoring Downtime-Optimized Conversion to SAP S/4HANA with SUM 2.0
TLA SP 18
3301507 BC-UPG-DTM- Executing and Monitoring Downtime-Optimized Conversion to SAP S/4HANA with SUM 2.0
TLA SP 17
Attachments
File Name File Size Mime Type