CHAINAGE 57+399.250
CLIENT:
NATIONAL HIGHWAYS AUTHORITY OF INDIA
EPC CONTRACTOR:
G.R.INFRAPROJECTS LTD.
The test pile will be reinforced and concreted upto ground level for
visual inspection. The steel reinforcement shall be ensured that it is
available for reaction welding. The steel bars shall be welded in place
over a steel plate and the same shall be used to provide the uplift thrust
for the piles.
Settlement is recorded with the help of 4 dial gauges for single pile
of 0.01mm sensitivity each positioned at equal distance around the
test pile. Datum bars resting on immovable supports at a distance of
3D (subjected to a minimum of 1.5m) from the edge of the piles
where D is the pile stem dia hold the dial gauges.
TC-11097
The test load is applied to 2.5 times the safe load for test piles as per
the provision of design drawings.
TC-11097
The Initial lateral load test on a single pile will be carried out as per the provisions
of IS-2911 (Part-4) 1985 by taking reaction from the existing piles/earth in the pile
group around the test pile. For applying lateral load to the test pile , one side of the
pile is chiseled/smoothened against which the ram of the hydraulic Jack acts. The
other end of the jack is packed against the anchor piles with the help of a piece of
girder suitably fixed in between the anchor piles and the jack. The reaction is then
drawn from these anchor piles and a horizontal load is applied to the test pile (as
per the plan diagram). Deflection readings are then observed with the help of dial
gauges fixed on datum bars and with its needle acting against the opposite end of
the test pile as shown in diagram.
The safe lateral load on the pile shall be taken as the least of the following for
initial load test:
1. Fifty percent of the final load at which the total displacement increases to
12mm i.e. at two times the safe load the deflection should not be more than
12mm for a pile to be safe.
2. Final load at which total displacements corresponds to 5mm i.e. at the safe
load the deflection should be less than 5mm for the pile to be safe.
For Initial pile tests the test is conducted up to 2 times the safe load or else as
specifically mentioned by the designer.
TC-11097
To transfer reaction from the anchored girders to the test pile one manual
controlled hydraulic jack will be used. The jack will be operated with a single
hydraulic pump.
For this test we propose to take reaction from existing anchor piles using jacks and
girders.
TC-11097
CALIBRATION CERTIFICATES
TC-11097
TC-11097
TC-11097
TC-11097
TC-11097
TC-11097
SITE RECORD
TC-11097
TC-11097
TC-11097
TC-11097
TC-11097
TC-11097
TEST REPORTS
TC-11097
Ph 1141716543
INITIAL VERTICAL LOAD TEST FOR CHAINAGE 57+399
CYCLIC LOAD TEST
PILE REF. NO. : TEST PILE-01 A-1 (RHS)
DIA OF PILE : 1200 MM
LENGTH OF PILE : 16.70 M
CAPACITY OF PILE : 950 MT
GRADE OF CONCRETE : M-35
DATE OF CASTING OF PILE : 14/04/2023
DATE OF TESTING OF PILE : 06/06/2023
1000.00
800.00
LOAD (tonnes)
600.00
400.00
200.00
0.00
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00
SETTLEMENT (mm)
TC-11097