EDP M5
EDP M5
Network Analysis
Method of planning and controlling projects by recording their
interdependence in a diagrammatic form that enables each
fundamental problem involved to be tackled separately.
1
4/10/2020
1.
◦
◦ “
Increased orderliness and consistency
◦ Operational flexibility
◦ Resource requirements
2
4/10/2020
Steps Involved In
Network Analysis
3. Apply estimated job time to the network diagram and calculate the
total length.
3
4/10/2020
4
4/10/2020
5
4/10/2020
11
12
6
4/10/2020
1 3 B None 5
1 4 C None 4
2 5 D A 2
3 5 E B 3
4 6 F C 9
5 7 G D, E 8
3 6 H B 7
6 7 I H,F 9
13
FINISH
D G
2 5 7
2 8
A E I
START 3 9
3 B
1 3 H 6
5 7
C F
4 9
4
14
7
4/10/2020
15
Rules/Guidelines
◦ A complete network should have a START event and a FINISH
event.
◦ Every activity must have one preceding or 'tail' event and one
succeeding or ‘head' event
◦ 'Loops' i.e. a series of activities which lead back to the same event
are not allowed.
8
4/10/2020
Network Techniques
Project
Critical Evaluation
Path And
Method Review
Technique
17
◦ Developed in 1956
18
9
4/10/2020
Critical Path
20
10
4/10/2020
21
22
11
4/10/2020
EOT Formula
23
For determining LOT, we start from the end event and move
backward towards the beginning. It is called Backward Pass.
12
4/10/2020
LOT Formula
◦ LOT (i) = Min { LOT (j) – d (i, j)}
25
3. Calculation Of Slack
◦ Slack for an event is the difference between
LOT and EOT.
13
4/10/2020
Event Slack
Event LOT EOT Slack = LOT- EOT
5 28 28 0
4 26 20 6
3 18 12 6
2 13 13 0
1 0 0 0
27
14
4/10/2020
Activity Floats
1. Total float
2. Free float
3. Independent float
29
Total Float
◦ Total float of an
activity is the extra
time available to
◦ Total Float for activity (2-4) =
complete the activity LOT for event 4 – EOT for event 2
if it is started as – duration of activity (2-4)
early as possible,
without delaying the
completion of the
project.
30
15
4/10/2020
Free Float
◦ the extra time
available to complete
the activity when the
◦ Total Float for activity (2-4) =
activity is started at EOT for event 4 – EOT for event 2
the EOT of its – duration of activity (2-4)
preceding event and
completed by the
EOT of its
succeeding event.
31
Independent Float
◦ the extra time
available to complete
the activity when the
◦ Total Float for activity (2-4) =
activity is started at EOT for event 4 – LOT for event 2
the LOT of its – duration of activity (2-4)
preceding event and
completed by the
EOT of its
succeeding event.
32
16
4/10/2020
33
34
17
4/10/2020
35
36
18
4/10/2020
37
38
19