Proj Doc
Proj Doc
Submitted to:
“ www.globalgiving.org ”
Submitted By
Springstars Foundation,
Lingidi Plaza Kabala West Junction, Nnamdi Azikiwe Way,
Kaduna, Kaduna State, Nigeria.
Ph: +234805328330
Email: [email protected]
Website: www.springstars.org.ng
MAY 2020
1|Page
BASIC INFORMATION
Project description
Project Beneficiaries
2|Page
1. PROJECT INTRODUCTION
Yelwa Shendam
Source: https://www.mindat.org/feature-2318166.html
The land of Shendam Local Government Area is very fertile and suitable for a
variety of agricultural crops. The main crops are Guinea corn, maize, Irish
Potatoes and vegetables . The major source of employment of the people is
Agriculture. Some people are also engaged in trade and other Government.
services.
Total population of this village is 13,236 (1996) and it is the target population
to be benefited from the proposed project.
The literacy ratio of the area is low as compared to other villages of this district i-
e (30 %), a lot of work in education sector is needed to achieve better results
as education directly influences the life standards and living standards of the
community. The basic needs of daily life are non-existent in the village due to
less intervention of government and non- government agencies.
A very small section of the project area is getting water from few open wells
(Unsafe source of Water Supply) located in mosques and churches of the village
while some portion of the community are fetching water from a spring located in
3|Page
depression in near the village. Women and girls go through a difficult path to
get water for drinking and other routine jobs. Because of the non-availability of
clean drinking water, the people of the village are suffering from wide
Spread occurrence of water and sanitation related diseases. Women are also
go to jendi rover for washing clothes and dish washing.
Source: http://www.maplandia.com/nigeria/plateau/shendam/yelwa/
4|Page
Shendam have requested FS for the provision of potable water services.
Field team of FS conducted social and technical survey of the village and found
that there is currently one tube well installed by the Plateau State Water Board
which is not working for long time. According to the community the
distribution pipes are blocked and due to long period it was not used and low
voltage the tube well is not functional. FS staff found the area suitable for the
implementation of Drinking water supply scheme (Installation of motorized
boreholes and erection of water storage tanks). They found that the most
alerting problem of the area is non- availability of clean drinking water supply
facilities.
The project is designed keeping in view urgent need of the community and their
willingness to shoulder responsibility of managing the project once the project is
implemented. After conducting socio-economic survey and technical feasibility of
area, a contractor acceptable to FS and Social Organizers suggested motorized
boreholes and water reservoir. This will address the water supply problem of
the area to a great extent.
Project Objective-1
To empower the local Community Organization to undertake the management
and maintenance their own potable water supply programme onece the
projected is implemented, which is the representative body responsible for
undertaking proposed sustainable village development scheme.
5|Page
Weekly meetings with the committees
Project Objective-2
To provide clean drinking water facilities to the people of the village and
enable them to mobilize their resources for their own betterment
6|Page
FS will also hold regular meetings with the community groups and individuals
at FS Sub Office and or main office. In these meetings they will be told about
importance and need of Social Organization (CO) for the development of village.
This will cultivate friends and support for the CO among the community.
Regular meetings with the CO will help the CO members to understand the
organizational behavior. They will understand their roles, responsibilities
and duties within the organization. Sense of ownership among the members
will be created and they will prefer common interest to individual interests. Social
Organizers of PRDS will help CO in building strong linkages and co-ordination
with other organizations. They will also help CO in identification of
productive activities and establishment of priorities.
Water Table depth of the area ranges between 90-190 ft. Therefore
installation of Motorized Pumps is feasible which can lift water from the depth
of about 150 ft.
Present population of village = P = 13000
Projected Population = P (N) = P (1+n/100) N
Design Period= N = 10 Years
Growth rate = n = 4.3
Projected Population = P (10) = 13,000 (1+ 4.3/100)^10
= 19,064
50% of total Project population = 9,531 or 10,000 approximately
One Motorized Borehole can serve more than 800-1000 people. To cover 50%
population, Installation of 10 Hand Pumps will completely fulfill the demand of
the projected population.
7|Page
under this scheme. Water User Committees will collect and deposit 10 cents
per Household per month with maintenance committee.
3. PROJECT IMPLEMENTATION
Upon receiving approval from Shendam Local Government Council; and the
Plateau State Government, FS will formally initiate the project.
4. PROJECT MANAGEMENT
FS and CO will jointly manage implementation of the project. FS will be responsible
for procurement of project supplies and provision of payment to CO for labor
8|Page
while CO will be responsible for the execution under the strict supervision of
contractor and will be responsible for arranging labor and resolving local
level issues. PRDS and CO will be responsible for the project management
as described below;
Financial Management
FS finance department and programme section will be fully responsible for
financial management. The payments will be made in to labor and on weekly
basis after verification of work by Community Organization and contractor.
The project committee will be responsible to provided record of labor payment
to FS and Field team will be responsible to check the project quality and
quantity frequently.
9|Page
them.
Women folk of the project area are deputed with the duty of fetching water
from distant areas. They regularly perform their duty. The implementation
of this project will relieve them form this difficult task and ultimately their
time will be saved for performing other important household chores. They
will be able to take part and utilize their time in other developmental and
income generation activities like Vocational Skills etc.
With the implementation of the proposed project CO will be
strengthened and empowered. CO, working under the technical assistance
and guidance of FS, will learn a lot at all levels of the project cycle and as a
result emerge as a relatively confident and experienced Community
Organization.
It is hoped that after completion of the proposed project the majority of the
people of the proposed area will become, to some extent, prosperous and will
lead a sound and healthy lives and the Socio-economic conditions of the area
will automatically improve. Having a good sound system of drinking water
supply other problems will die their natural deaths. The huge costs of
emotional pain and physical efforts involved in dealing with sick
community members signify a huge drain on the resources of the
communities. Implementation of this project can solve the problem to much
extent.
The benefits from investing in small scale water supplies and from
developing appropriate policies, programmes and regulations are
significant. The impact of diarrhoeal disease for children under the age of
15 is greater than the combined impact of HIV/AIDS, tuberculosis and
malaria. The provision of improved drinking-water and sanitation could
reduce diarrhoeal diseases by nearly 90%, and current estimates indicate
that improvements in these areas could reduce the number of children who
die each year by 2.2 million.
10 | P a g e
increased school attendance
Time savings (working days gained) resulting from more convenient
access to services
Value of deaths averted (based on future earnings)
1
Comparison of donor commitments to sanitation with donor commitments to drinking water projects, 14 donors,
2008
11 | P a g e