Lecture 1_Field soil testing
Lecture 1_Field soil testing
Texts/References:
1) Ranjan, G. and Rao, A.S.R., 2005. Basic and Applied Soil Mechanics, 2nd Edition,
New Age International (P) Ltd.
2) Das, B. M., 2007. Principles of Foundation Engineering, 6th Edition (Low price
edition), Cengage Learning.
3) Sivakugan, N., and Das, B.M., 2011. Geotechnical Engineering: A Practical
Problem Solving Approach, Cengage Learning.
4) Verghese, P. C., 2005. Foundation Engineering, PHI Learning Pvt. Ltd.
CE 314: Course content
CE 314: 4 credits
◼ Non-representative Samples:
◼ Water content altered and soil layers mixed up
◼ Of no use.
◼ Undisturbed Samples: Soil structure and the other
mineral properties are preserved to an extent. ◼ Some
disturbance is always there, e.g. due to stress release.
However it should be minimized in order to have suitable
sample for our analysis.
Standard Split Spoon Samplers
Shelby Tube
(Thin-wall) Sampler
◼ Permeability
tests.
In bore
IS: 2131-1981
Standard Penetration Test
Standard Penetration Test IS: 2131-1981
◼ Components
◼ Drilling Equipment
◼ Inner diameter of hole → 100 to 150 mm
◼ Casing may be used in case of soft/non-cohesive soils
hole bottom.
◼ Driving mass is dropped onto the drill rod repeatedly and the
sampler is driven into soil for a distance of 450 mm. The number of
blow for each 150 mm penetration are recorded.
Standard Penetration Test
◼ Procedure (Cont….)
◼ N-value
◼First 150 mm penetration is considered as seating penetration ◼
The number of blows for the last two 150 mm penetration are
added together and reported as N-value for the depth of bore
hole.
◼ The split spoon sampler is recovered, and sample is
collected from split barrel so as to preserve moisture
content and sent to the laboratory for further analysis.
◼ SPT is repeated at every 750 mm or 1500 mm interval
Cutting shoe of the sampler must be free from wear & tear ◼
The bottom of the bore hole must be cleaned to collect
undisturbed sample
◼ When SPT is done in a sandy soil below water table , the
water level in the bore hole MUST be maintained higher
than the ground water level.
Otherwise: QUICK condition!!
Very Low N value
SPT
Corrections
➢ Overburden correction
➢ Dilatancy correction
➢ Hammer energy correction
[ ]
SPT Hammer Energy Correction
◼ Energy is dissipated in some fraction during the impact, and the
output energy is usually in the range of 50% to 80% of energy
input.
E
out
60%
◼For rope pully hammer in
DCPT Procedure
❑ Cone – drill rod – driving head assembly is installed
vertically on the ground and hammer is dropped from
standard height repeatedly
❑ In the end, the drill rod is withdrawn. The cone is left in the
ground if unthreaded or recovered if threaded.
➢ No sample recovered
➢ Fast testing – less project cost / cover large area in due time
➢ Use of bentonite slurry is optional, which is used to reduce
friction on the driving rods.
• Modified cone is used in this case: diameter = 62.5 mm
DCPT – SPT Correlations for 50 mm dia. cone
Ncd = 1.5 N For depth < 3 m
)
Depth Below Excavated Surface (m Interbedded
3 Fine Sand and Clay (CL) Sand (SP)
4
5 Silty Sand
6 (SP-SM)
7 Fine Silty Sand
8
(SM)
9
10 Gray Silty
Mean-SD Mean+SD
Mean
From CPT From SPT
◼ CPT: Disadvantages
◼ Does not give a sample
◼ Will not work with soil with gravel
CPT Results
& Soil
Classification
Seismic
Cone
Penetration pore pressure
Test with measurement
s
(SCPTU)
Electric cone
is
required
34
Cone Tip
Piezocone
Depth (m)
0
1
2
3
4
5
6
7
8
9
10 11 12 13 14 15
Interpreted Soil Profile
EQ Drain Test Area 1 Sand
Silty sand/sand
Silt and Sandy
Silt
Sand to
Silty Sand
Resistance, qc (MPa)
0 2 4 6 8 1012
Fricton Ratio, Fr (%)
0123456
Pore Pressure, u (kPa)
-100 0 100 200
Density, Dr
0 0.2 0.4 0.6 0.8 1
bore hole
◼ For clays, and mainly for soft
clays. ◼ Measure torque required to
quickly shear the vane pushed ∴ undrained
vaneh≈2d
soft clay
torque ➔ undrained shear strength cu ◼ Typical d = 20-100 mm.
38
vane
Vane Shear Test
Interpretation:
Undrained shear
strength -
c
u
=
2. 2
T
πλ...
DH
D 3.
λ 1 H
=+
For H = 2.D
0.2 T
c 73 u
3
= D
◼ Determined:
◻ Elastic Modulus
◻ Soil Type and state
60 mm dia. Flexible
membrane
40
Pressure
meter
Test
(PMT)
Determined:
Elastic Young Mod, E
Shear Mod, G
Undrained shear strength, Su
Pressure meter Test (PMT)
Measurements:
1. Fluid Pressure
Exploration Techniques
◼ Test Pits: Unlike boring, soil can be visually observed from the sides of
the test pit. Pit is made by excavating ground (typical size =1.2mx1.2m)
considering sufficient working space.
◼ Trenches: Trenches are long shallow pits. They are more suitable for
exploration on slopes than pits.
◼ Suggestions:
Auger Boring for soils which can stay open without casing or drilling
mud. It is not possible for sands below water table.
Good for Highways, railways projects where small depth of soil
exploration is needed.
Auger
◼Push and rotate the
Boring auger until annular space
Procedure of auger fills up ◼
Withdraw the auger and
clean it ◼ Repeat the – Heavy duty pipe with
process cutting edge
– Lifted and then left to fall
freely
3. Sand Bailer
1. Hand Auger
– for shallow depth (3 - 5 m)
Auger Boring4.
Hollow Stem Auger
46
Wash
Boring
◼ A casing pipe of 2-3 m
length is driven into the
soil by a heavy drop
hammer.
◼ The soil inside the
casing is removed by
means of a chopping bit
attached to a drill rod
which forces water at
high pressure.
◼ Soil mixed with water
moves up in annular
gap between drill rod
and casing.
◼ Samples are obtained at
certain depth by
removing drill rod and
pushing a sampler
instead.
47
Rotary Boring
❑ Design similar to wash boring
❑ Useful when soil is resistant to auguring
or wash boring
◼ Boring is done by rapidly
rotating drilling bits attached
to bottom of drilling rod.
◼ Soil/rock cuttings removed by
circulating drilling fluid
◼Samples are taken a certain
depths by removing drill rod
and placing
sampler.
◼ Mud Rotary Drilling: Hollow drilling
rods are used to flow mud slurry
(Bentonite) to check caving in of the
material (soil) at bottom.
◼ Core Drilling: Core barrels with
diamond bit are used.
Percussion Boring
Bearing Plate:
◼ Rough mild steel bearing plate in circular or square shape
◼ Dimension: 30 cm, 45 cm, 60 cm, or 75 cm.
Thickness > 25 mm
◼ Smaller size for stiff or dense soil. Larger size for soft or loose soil ◼
Bottom of the plate is grooved for increased roughness. ◼ Concrete
blocks may be used to replace bearing plates.
Plate Load Test – IS:1888-1982
Test Pit:
◼ Usually to the depth of foundation level.
◼ Width equal to five times the test plate
◼ Carefully leveled and cleaned bottom.
◼ Protected against disturbance or change in natural formation
Plan
Section
Plate Load Test – IS:1888-1982
Procedure:
◼ Selection of Location
◼ Based on the exploratory boring.
below the foundation level but the depth is less than width of plate
then the test is carried out at the level of water table. If the water table
is above the foundation level then the water level is reduced to
proposed foundation level by pumping out the water during the test;
however, in case of high permeability material perform the test at the
level of water table.
◼ In case the soil is expected to have significant capillary action and the
water table is within 1 m below the foundation, it becomes necessary
to perform the test at the level of water table in order to avoid the
effect of higher effective stresses due to capillary action resulting in
lower values of interpreted settlements.
◼ Reaction supports should be at least (3.5 x width of plate) away from the
test plate location, and loading arrangement should provide sufficient
working space.
◼ Test plate should be placed over a 5 mm thick sand layer and it should be
centered with the loading arrangement.
Plate Load Test – IS:1888-1982
Procedure: (Contd.)
◼ A seating pressure of 7 kPa is applied and then released after some time
before the test.
◼ Loads are applied in the increments of approximately 1/5th of the
estimated ultimate safe load. (Or, one may choose to increase the load at
an increment of 0.5 kN.)
◼ At each load settlement is recorded at time intervals of 1, 2, 4, 6, 9, 16, 25
min and thereafter at intervals of one hour.
◼ For clayey soil, the load is increased when time settlement curve shows
that the settlement has exceeded 70-80% of the probable ultimate
settlement or a duration of 24 Hrs.
◼ For the other soils, the load is increased when the settlement rate drops
below 0.02 mm/min.
◼ The minimum duration for any load should, however, be at least 60 min.
◼ Dial gauges used for testing should have at least 25 mm travel and 0.01
mm accuracy.
◼ The load settlement curve can then be platted from settlement data.
Plate Load Test – Load-Settlement Curve
Zero
Correction:
The intersection of the early straight line or nearly straight line with zero load
line shall be determined and subtracted from the settlement readings to allow
for the perfect seating of the bearing plate.
Plate Load Test – Load-Settlement Curve
()
Terzaghi and Peck (1948): 2
⎤ S =Settlement of a foundation of f
⎡ +
SBB 30 width Bf(cm)
fp
f
S =Settlement of the test plate of
=⎢⎥()
SBB
⎢⎥+
ppf
30
⎣⎦ width Bp(cm) at the same load
p intensity as on the foundation
⎡⎤
Bond (1961): Soil Index
n
Clay Loose sand Dense sand 1.40 t
Sandy clay Medium sand
S B ff
=⎢⎥⎢⎥
⎣⎦
S B pp
Plate Load Test: Bearing Capacity
◼ In case of dense cohesionless soil and highly cohesive soils ultimate bearing
capacity may be estimated from the peak load in load-settlement curve.
◼ In case of partially cohesive soils and loose to medium dense soils the ultimate
bearing capacity load may be estimated by assuming the load settlement curve
so as to be a bilinear relationship.
63
◼ Fix adjustable stem and perforated plate on the compacted soil specimen
in the mould along with 2.5kg surcharge load
◼ Place the above set up in the soaking tank for four days (ignore this step
in case of unsoaked CBR).
◼ After four days, measure the swell reading and find % swell with the help
of dial gauge reading.
Procedure :Cont.…..
◼ Remove the mould from the tank and allow water to drain. ◼ Then place
the specimen under the penetration piston and place total surcharge load
of 4kg (2.5kg during soaking + 1.5 kg during testing) ◼ The load and
deformation gauges shall then be set to zero ◼ Load shall be applied to the
plunger into the soil at the rate of 1.25 mm per minute.
◼ Reading of the load shall be taken at penetrations of 0.5, 1.0, 1.5, 2.0, 2.5,
4.0, 5.0, 7.5, 10.0 and 12.5 mm
◼ Remove the plunger and determine the water content of the soil. ◼
Note :
The maximum load and penetration shall be recorded if it occurs for
a penetration of less than 12.5 mm
Calculation
Where,
df=final dial gauge reading in mm(after 96 hrs),
ds=initial dial gauge reading in mm, and
h=initial height of the specimen in mm.
Where,
◼ PT=corrected unit ( or total ) test load corresponding to the chosen penetration
from the load penetration curve
◼ PS=unit ( or total ) standard load for the same depth of penetration as for PT
taken from the table given in Fig.