RMP - 2016 - Presentation
RMP - 2016 - Presentation
Je suis comme le destin, je ne joue pas avec les morts et je ne crois pas
aux coïncidences
We hit a cable, water pipe, drainage line or Telephone cable Major AOG‐ Storms , earthquakes or Hurricanes
The consultant rejected the Steel for the 5th time Inflation rates that affect the fund providing for the project
Concrete cubes are failed in the stress test for the 3rd time Change of Management approaches toward reserve
AHU Connection dose not match the delivered pipes The contractor fail to provide the Desired Quality
Elevator doors Opening are not matching the door size The contractor fail to provide the Desired Safety requirement
The suspended ceiling level is not compatible with the Duct size Compotator achieve a good marketing for the same product before the project end
Unexpected price rises for labor and materials The project exceeds the risk rating during the execution processes
20% of the working Engineers are resigned & on the notice period The consultant failed to guarantee the required Quality on site
We may use the Excavated materials somewhere in the construction processes The contactor performance will lead to a Exceed achieving A milestone
The Soil founded after excavation is sand while it was predicted to be rock The Design consultant Finalize Design Drawing early
I’m Mr.
We developed a method to set 3 shuttering for slabs in the same time New Economical Requirements for the project
Client,
The Delivery of a main material finished before scheduled Contractor New Funds for the Project
or Engineer
One of the project staff has an experience in a complicated assigned task New Strategic visions changes the priorities of project
The MDB is available in the local market & no need to purchase it from Inflation rates that affect the fund providing for the project
outside the country
Change of Management approaches toward reserve
A scheduled Hurricane wont take place
New Technology is released that decrease time
We have an expert in the county for the time being
New Technology is released that decrease time The consultant Manage to guarantee the required Quality on site
Customer change some requirements into others already in A claim from the contractor for loss and expense caused by the
our stores late production of design details by the design team
Agreed or ..? 2‐ Business models based on realizing benefits after investing in executing
projects are More risky
Agreed or ..?
3‐ Risk Management is a powerful decision making tool in all industries
Agreed or ..? 4‐ For To many organizations, risk is a four letter word and they try
to insulate themselves from risk, They position themselves to unload
unexpected costs onto others. Increased costs are passed on to
consumers by raising prices
Agreed or ..? 5‐ This approach may well have worked in the past, but it can be a
recipe for disaster. As international competition becomes stronger,
saddling consumers with increased costs becomes more difficult.
Shifting financial risk onto sub‐contractors, the least able to resist
does not encourage high levels of trust and commitment
Risks Definitions
Possible – Uncertain – Event that may positively or negatively
impact the project
Pure Risk Insurable Risks – Only Risk of loss – Ex. Fires
Type of Risks
Business Risk Risk of gain or loss – Ex. Product that can be lose money
or gain money
Analytical technique
Used to understand and define the overall risk management context .
‘The ostrich approach ‘ where you burry your head in the sand
2 and amuse everything will be alright, that somehow you will
muddle through
3 ‘the intuitive approach’ that say don’t trust all the fancy analysis,
trust your intuition and gut feel
‘The brute force approach’ that focuses on the uncontrollable risk
4 and says we can force things to be controlled, which of course
they cannot
The project from the Investment Decision Stage Up to occupancy
(Client/Developer Point of View)
Monitor and
control risk
Plan Risk
response
p
Quantitative
risk analysis
y
Qualitative
risk analysis
y
Identify Risks
Plan Risk
management
g
To have the ability & Culture to Do Risk management
Now We Know what is Risk…
To Do What……?
General Procedures & Response
To Do What……?
Major Application in
Construction Industry
5 Assumptions
7 Network Diagram
Culture Issues & suggested Protocol, language barriers & social customs (religions)
5 Assumptions
Things are accepted to be true, but they may not be true & the validity of such assumptions will be tested in the
project life cycle
7 Network Diagram
Summary Level – Rolling Up for Activities Duration & Logic
10 Organization Processes assets (when sealing & company it really worth to have)
Risk Management policies, Procedures & templates
Printing the
Labeling the To
Boarding Immigration
Baggage (S)
Pass
Map your Mind
Risk
Uncertain
Risk Zone
Risk
Duration
Cost Risk
Risk
Duration
Risk
Cost
Risk
Duration
Deterministic Zone Cost
Risk
Duration
Cost
Risk
Project Risk Management
Planning
Inputs
1. Plan Risk Management
Outputs
Tools & Techniques
Project Charter Analytical techniques
Reserves
Risk Response, Contingency, and
Fall‐back Plans
Roles &
Categories
Responsibility
Methodology
RM Stakeholders’
Tolerance
Plan
If
Yes
Monitor & control Risks, Through Risk meetings Evaluate Responses Document the New Risks & create lessons learned
Starting From the risk Planning process
Advanced Risk Management Practicing
Planning
Inputs
1. Plan Risk Management
Outputs
Tools & Techniques
Project Charter Analytical techniques
Planning
Inputs
4. Perform Quantitative Risk Analysis
Outputs
Tools & Techniques
Risk Management Plan
Data Gathering & Representing Tec.
Risk Register Information Gathering Tec. (project documents ) Risk
Register Update
Cost management plan Quantitative Risk Analysis Modeling
Techniques
Schedule management plan Updated List of Potential Risks
Expert Judgment
PM Plan Update
Exploit Transfer
Avoid
Enhance
Mitigate
Share
Accept
Advanced Risk Management Practicing
Change Request
PM Plan Update
Stakeholder Engagement 18 – 20 %
If
Yes
Monitor & control Risks, Through Risk meetings Evaluate Responses Document the New Risks & create lessons learned
Starting From the risk Planning process
Agreed or ..? The Most Important Process of Risk management – if we will do RM – Is to Identify the Risks Processes of RM
Agreed or ..? Most of the Construction risks are linked to the construction schedule Construction Point
of View
Agreed or ..? Most of the Risks In Construction are with high Impact & Controlled Probability
Agreed or ..? Risk as A decision making tool & the Scenario management can be mostly Used in Construction Decide To Do RM &
Agreed or ..? Risk as A decision making tool Can not be done in the Detailed Level of Schedule
RM Planning
Identify Risks
Use a prompt list – List of Risk Categories
Analyze Risk
Review your Own Company’s historical
records and other documentation Score & Ranking for Risks Team
Plan Risk Responses
Brainstorming High Level Risk Analysis for Cost
Executives Simply How we are going
Conduct a ‘’ Pre‐mortem' Imagine the High Level Risk Analysis for Time to deal with risks
project is completed or failed
Matrices & Templates for Risk Categories Complicatedly What is the
Affinity diagrams – Grouping of Identified effect of our responses to
Detailed Level Scenarios Analysis for Time & Cost
Expert interviews the Risks probabilities &
All Time An cost Scenarios outputs Reviewed Impacts
Nominal group technique – Group thinking
Use the New Modified
Delphi technique – Individual Experts Probabilities & Impact To
Cause and effect diagram – Fish bone Re – Simulate the Project
outputs
Failure modes and effects analysis
Exploit Enhance Transfer Avoid Plan Risk Responses
Strengths, weaknesses , opportunities , and
Share Accept Mitigate Categories
threats (SWOT)
Monitor & control Risks, Through Risk meetings Evaluate Responses, Document the New Risks & create lessons learned
Starting From the risk Planning process
The Most Important Process of Risk management – if we will do RM – Is to Identify the Risks
Most of the Construction risks are linked to the construction schedule
Most of the Risks In Construction are with high Impact & Controlled Probability
Risk as A decision making tool & the Scenario management can be mostly Used in
Construction
Risk as A decision making tool Can not be done in the Detailed Level of Schedule
Identify Risks
Use a prompt list – List of Risk Categories
Review your Own Company’s historical records and other documentation
Brainstorming
Conduct a ‘’ Pre‐mortem' Imagine the project is completed or failed
Affinity diagrams – Grouping of Identified
Expert interviews
Nominal group technique – Group thinking
Delphi technique – Individual Experts
Cause and effect diagram – Fish bone
Failure modes and effects analysis
If you are not confident that you have identified all the risks, redo the previous steps,
If you are confident, determine whether questions remain and what information is still needed to understand and
analyze the identified risks
• Reach consensus
from EXPERTS.
• ANONYMOUS: no
bias
• Written questionnaire
Consultant
Contractor
Authority
Employer
Operator
Police
PMC
Procurement
Contractual
Financial
Design
Engineering
Construction
Logistics
Quality
HSE
40
We have COP directors in many various fields with
PMI‐AGC does not have a fixed office in Riyadh
high experience & well Educated
We are working in a booming era in the filed of
SWOT Analysis
PMI‐AGC does not have a fixed training Schedule
project management
The market is hungry for project management PMI‐AGC does not have a fixed training place in
Riyadh
We have a well established relations with the
The service of the PMI‐AGC especially in trainings
largest clients & Contractors in many fields
in Riyadh is week
We have well Experienced members of the COP
Providing Practical application in specified
board in the training filed
industries is not strong enough
We know that the most wanted service now ins
Surveys for the market needs (PM) tools are not
trainings
strong enough
PMI‐AGC is an official representative of PMI
Opportunities Threats
Score
Risk Factors ‐ QL Factors‐ QN Risk Potential
S co re
ID Action Notes
Owner Response
Cause Description effect P I P I Owner
As we don’t have which wil cause a
On a small scale (1 to 3)
R_001 the proper existing delay of 10 days &
Quantitative Rank
existing cable Qualitative Rank
utilities drawings penalty of 1000 SR
Score
R_002
R_003
R_00X
Probability Definitions
The Likelihood of having the event on reality, based on
Experience or Lessons learned
Impact
The effect (time or money) as number for Quantitative Analysis or as category (large,
Medium, Low effect) for Qualitative Analysis that the project will suffer if the Event
happened
Risk Score for Each Risk or Activity
Multiply the Probability times Impact to get a value (Qualitatively or Quantitatively) for
the Risks & the Activities (threats are positive Values & Opportunities are negative
values))
Risk Score for Project
The Sum of all the Scores of all the Risks or the Activities in the Project
Risk Ranking
The Arrangement of Risks due to there Scores
Risk Rating
Is A number Between 1 & 10 chosen to evaluate the Probability or Impact of a Risk
Expert interviews – The most Effective method of Identifying Risk
1‐ I wanted to ask your advice because I heard
you have a lot of experience with this issue!
“This will get them more interested in helping
you. Watch out, though‐ your compliment
must be a real one and not just fluff such as,
“I heard you are great.”
50
Project Risk Analysis (Qualitative &
Quantitative)
Copy righted for Hosam Eid Mohammed (kandeel)
Agreed or ..? The Most Important Process of Risk management – if we will do RM – Is to Identify the Risks Processes of RM
Agreed or ..? Most of the Construction risks are linked to the construction schedule Construction Point
of View
Agreed or ..? Most of the Risks In Construction are with high Impact & Controlled Probability
Agreed or ..? Risk as A decision making tool & the Scenario management can be mostly Used in Construction Decide To Do RM &
Agreed or ..? Risk as A decision making tool Can not be done in the Detailed Level of Schedule
RM Planning
Identify Risks
Use a prompt list – List of Risk Categories
Analyze Risk
Review your Own Company’s historical
records and other documentation Score & Ranking for Risks Team
Plan Risk Responses
Brainstorming High Level Risk Analysis for Cost
Executives Simply How we are going
Conduct a ‘’ Pre‐mortem' Imagine the High Level Risk Analysis for Time to deal with risks
project is completed or failed
Matrices & Templates for Risk Categories Complicatedly What is the
Affinity diagrams – Grouping of Identified effect of our responses to
Detailed Level Scenarios Analysis for Time & Cost
Expert interviews the Risks probabilities &
All Time An cost Scenarios outputs Reviewed Impacts
Nominal group technique – Group thinking
Use the New Modified
Delphi technique – Individual Experts Probabilities & Impact To
Cause and effect diagram – Fish bone Re – Simulate the Project
outputs
Failure modes and effects analysis
Exploit Enhance Transfer Avoid Plan Risk Responses
Strengths, weaknesses , opportunities , and
Share Accept Mitigate Categories
threats (SWOT)
Monitor & control Risks, Through Risk meetings Evaluate Responses, Document the New Risks & create lessons learned
Starting From the risk Planning process
To have the Ability & Culture to Implement Risk If Not Don’t waste your time & money
Analysis
If
Yes
Monitor & control Risks, Through Risk meetings Evaluate Responses Document the New Risks & create lessons learned
Starting From the risk Planning process
Important Single Formula – Risk Factors
Quantitative Amount
Qualitative Score
(Money or Time)
Identify the total Project Risk Identify the total Project Risk
Score & Go/No Go Decision Score & Go/No Go Decision
Advanced Risk Management Practicing
Planning
Inputs
3. Perform Qualitative Risk Analysis
Outputs
Tools & Techniques
Risk Register
Risk Probability & Impact assessment (project documents ) Risk
Risk Management Plan Probability & Impact Matrix Register Update
OPA and EEF Risk & Quality Assessment
Updated List of Potential Risks
Risk Categorization
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
1 2 3 4 5
Advanced Risk Management Practicing
Planning
Inputs
1. Plan Risk Management
Outputs
Tools & Techniques
Project Charter Analytical techniques
Planning
Inputs
4. Perform Quantitative Risk Analysis
Outputs
Tools & Techniques
Risk Management Plan
Data Gathering & Representing Tec.
Risk Register Information Gathering Tec. (project documents ) Risk
Register Update
Cost management plan Quantitative Risk Analysis Modeling
Techniques
Schedule management plan Updated List of Potential Risks
Expert Judgment
Excavation line
No existing utilities
map
Point
Low accuracy existing
A utilities map
20
20
5
5
130
Risk analysis framework- The Probability breakdown structure
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
1 2 3 4 5
Risk analysis framework- The Probability
Planning
Inputs
4. Perform Quantitative Risk Analysis
Outputs
Tools & Techniques
Risk Management Plan
Data Gathering & Representing Tec.
Risk Register Information Gathering Tec. (project documents ) Risk
Register Update
Cost management plan Quantitative Risk Analysis Modeling
Techniques
Schedule management plan Updated List of Potential Risks
Expert Judgment
Uncertainties
Finishing of R. Concrete work for
Chemical Chimney for Power Planet
FS
Resources
Sensitivity Analysis
Critical Risks for the Model
Risk 2
Risk 3
Risk 4
Risk 5
Sub‐Network (Fragment 1)
Risk 6
Risk 10
Sub‐Network (Fragment 5)
Risk 11
Sub‐Network (Fragment 6)
Risk 12
75
Now What have we done…….? Based On fluctuation in Schedule variables,
(duration, Resources rates or Productivities) (A)
Identify Risks
Group Of
Effort Based On Some possible Scenarios (Group B)
Score & Ranking for Risks Analysis
Based & depend on the Identified risks & there
High Score Risks for further analysis Detailed Level Probability , Impact & Activity Sensitivity (Group C)
Most Probable
Optimistic
Duration 4 Duration
(deterministic )
Pessimistic
Duration
6
For Analysis across a time schedule the probable durations are set
to the Uncertain Activities & Based on the Logic a Software could
Develop iterations up to 1,000,000 (IT) to produce the Shown
Curve giving the probability of achieving various durations for the
Project, work packages & Activities Duration
Group (A) ‐ Analysis Number (2) – Resources Rates & Productivities)‐ Direct Numbers Entry
Manpower (hr) Equipments Materials
Resources
FS 10%
FS
PC ‐ Foundation
(Excavation – Duration = XX) – (Possible Soil Replacement Due to clay condition ‐ Duration = Z1 or Z2 or Z3) ‐ (PC – Foundation Duration= YY)
Probable Path (1) 20%
(Excavation – Duration = XX) – (Possible Rock Breaking ‐ Duration = N1 or N or N3) ‐ (PC – Foundation Duration= YY)
Probable Path (2) 10%
After Collecting & Applying All the Probable paths in the Time schedule a software can do Iterations up one Million
Times to adjust the Curve of possible Dates & Durations for the Whale project, work packages, Summary Levels &
Activities
Group (B) ‐ Analysis Number (1) – Based On Possible Construction Scenarios – Logic & Paths Probabilities
Case (2) –Probabilistic Branching
(Finishing of R. Concrete work for chemical Chimney for electrical station )
Deterministic Path
Uncertainties – (Outside High Advanced Isolation & smoke filtering )
filtering Duration= YY
FS
Duration only
Probabilistic
Duration = Zero Finding Internal &
External Support & replace Some Parts BR2 38%
Probability = 50% Structural Cracks
Branching Point
Relation = FS Demolishing & Restructure BR3 2%
All are FS
After Collecting & Applying All the Probable Branches in the Time schedule a software can do Iterations up one
Million Times to adjust the Curve of possible Dates & Durations for the Whale project, work packages, Summary
Levels & Activities
Group (B) ‐ Analysis Number (1) – Based On Possible Construction Scenarios – Logic & Paths Probabilities
Case (2) –Probabilistic Branching
Deterministic Path Excavation & Padding for cables – Cable Pulling & Connection for JP
Uncertainties
Duration= YY
FS
Duration only
Probabilistic
Duration = Zero Due to Absence of
Utility maps old Re‐ Direction for the Cable
Probability = 40% utilities could be trenching BR2 15%
found
Relation = FS Branching Point Use Special construction (HDD) BR3 55%
All are FS
After Collecting & Applying All the Probable Branches in the Time schedule a software can do Iterations up one
Million Times to adjust the Curve of possible Dates & Durations for the Whale project, work packages, Summary
Levels & Activities
After every single group of analysis The previewed curve took place
Targe
t
Sensitivity Analysis Is A computerized Analysis Done with the same data entered to the Previous Analysis to
determine the most Sensitive activities to impact the Critical Path(S)
Most Critical
Lowest Critical
Group (C) ‐ Based & depend on the Identified risks & there Probability , Impact & Activity Sensitivity – Using
Risk Register & Qualitative & Quantitative Risk Analysis & Risk Responses
The main target of Risk management is to define the impact of Risks as a probabilistic curve before mitigating
risks & after to show who dealing with Uncertainties could reduce our cost & Achieve time limits for a project
Project Risk Response planning
Copy righted for Hosam Eid Mohammed (kandeel)
Advanced Risk Management Practicing
Planning
Inputs Outputs
5. Plan Risk Responses
Tools & Techniques
Risk Register
Strategies for Negative Risks – Threats
(project documents ) Risk
Risk Management Plan Strategies for Positive Risks – Opportunities
Register Update
Contingent Responses Strategies
Updated List of Potential Risks
Expert Judgment
Updated List of Potential Responses
PM Plan Update
Exploit Transfer
Avoid
Enhance
Mitigate
Share
Accept
Advanced Risk Management Practicing
Change Request
PM Plan Update
Residual Risks
Pre – Mitigated Risks Data Post – Mitigated Risks Data
Mandatory Data To be
Mandatory Data To be Defined to Defined to Software or
Software or manual analysis manual analysis
Threat or Opportunity & Essay details Threat or Opportunity & Essay details
Cause & Effect ,Title & Description for Risk Cause & Effect ,Title & Description for Risk
Probability as Qualified (Low, Medium, High & Probability as Qualified (Low, Medium, High &
percentage) percentage)
Schedule Impact (Low, Medium, High & Value) Schedule Impact (Low, Medium, High & Value)
Project
Cost Impact (Low, Medium, High (Rank & Value) Cost Impact (Low, Medium, High (Rank & Value)
Cost Impact (Low, Medium, High (Rank & Value) Cost Impact (Low, Medium, High (Rank & Value)
Performance Impact Description Performance Impact Description
Customer
Risk Team , Risk manager & RAM As out put
All Risk
Engineering Dep. Qualitative scales of Probability
information are
available & Risk Analysis & impacts
Outside Experts
As out put
Evaluated with Probability &
Estimation Dep. acceptable quality impact for Each risk
Choose for
Cost Control Dep. Identify Further Score & ranking
YES
Analysis
Procurement Dep. Risks Watch List
Create Risk
Construction Dep. Quantitative
Breakdown Simulations
out put
structure Risk Analysis
As
HR Dep. Detailed
Risk Register RBS Sub Decisions
Coordinators
Probabilistic Scenarios Management
As out put Plan Risk Contingency &
Top Management
Reserves & Management Responses Fallback Plans
1. Plan Risk
Management Our Project
2. Identify Risks Risk
Risk Factors ‐ QL Factors‐ QN Risk Potential
3. Perform Qualitative ID Action Notes
Owner Response
Risk Analysis
Cause Description ef ect P I P I Owner
S
4. Perform Quantitative
As we don’t have which wil cause a
or Low)
o )
e ((1 to 3)
5. Plan Risk R_0 1 the proper existing delay of 10 days &
Quantitative Rankk
Rankk
existing cable
ode ate o
Responses util ties drawings penalty of 1000 SR
scale
( g , Moderate
Qualitative
Score
a sca
On a ssmall
R_0 2
l
Risk Management plan
(High,
R_0 3
O
Risk Register
R_0 X
QUESTION NO: 1
Lisa is the project manager of the SQL project for her company. She
has completed the risk response planning with her project team and
is now ready to update the risk register to reflect the risk response.
Which of the following statements best describes the level of detail
Lisa should include with the risk responses she has created?
C. The level of detail must define exactly the risk response for each identified risk.
A. Team development
B. Benchmarking
D. Cost‐benefits analysis
QUESTION NO: 5
Jenny is the project manager of the NHJ Project for her company.
She has identified several positive risk events within the project and
she thinks these events can save the project time and money. You, a
new team member wants to know that how many risk responses
are available for a positive risk event. What will Jenny reply to you?
A. Four
B. Three
C. Seven