EREC G83
EREC G83
www.energynetworks.org
PUBLISHING AND COPYRIGHT INFORMATION
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system
or transmitted in any form or by any means, electronic, mechanical, photocopying, recording
or otherwise, without the prior written consent of Energy Networks Association. Specific
enquiries concerning this document should be addressed to:
Operations Directorate
Energy Networks Association
4 More London Riverside
London
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
SE1 2AU
This document has been prepared for use by members of the Energy Networks Association
to take account of the conditions which apply to them. Advice should be taken from an
appropriately qualified engineer on the suitability of this document for any other purpose.
Contents
1 Foreword.......................................................................................................................... 5
2 Scope............................................................................................................................... 6
3 Normative References ..................................................................................................... 7
4 Terms and Definitions ...................................................................................................... 9
5 Connection, Protection & Testing Requirements ............................................................ 13
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
1 Foreword
This Engineering Recommendation (EREC) is published by the Energy Networks Association
(ENA) and comes into effect from 1 December 20121.
It has been prepared and approved under the authority of the Great Britain Distribution Code
Review Panel. The approved abbreviated title of this engineering document is “EREC G83”,
which replaces the previously used abbreviation “ER G83”.
The purpose of this Engineering Recommendation is to simplify and standardise the technical
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
requirements for connection of Small Scale Embedded Generators (SSEGs) for operation
in parallel with a public low-voltage Distribution System, by addressing all technical aspects
of the connection process from standards of functionality to site commissioning.
The procedures described are designed to facilitate the connection of Type Tested SSEGs
whilst maintaining the integrity of the public low-voltage Distribution System, both in terms of
safety and supply quality.
a) SSEG Manufacturers to design and market a product that is suitable for connection to
the public low-voltage Distribution System;
b) Users, Manufacturers and Installers of SSEGs to be aware of the requirements that will
be made by the Distribution Network Operator (DNO) before the SSEG installation will be
accepted for connection to the DNO’s Distribution System.
Legal Aspects
In accordance with ESQCR Regulation 22(2)(c) the Installer is to ensure that the DNO is
made aware of the SSEG installation at or before the time of commissioning. The DNO may
not refuse to accept the connection providing the installation complies with the requirements
of ESQCR Regulation 22. However under the terms of ESQCR Regulation 26 the DNO may
require a SSEG to be disconnected if it is a source of danger or interferes with the quality of
supply to other consumers.
In August 2008 an exemption to ESQCR Regulation 22(2) (c) was granted by the Health &
Safety Executive to the person or persons installing the source of energy from the requirements
imposed by ESQCR Regulation 22(2)(c) as long as that person or persons installing the source
of energy informed the DNO of the intention to use that source of energy in parallel with the
network no later than 28 days (inclusive of the day of commissioning) after commissioning the
source (see Appendix 6)
In addition to the requirements specified in this document which allows connection to the GB
electricity Distribution System, the SSEG and all of its components shall comply with all
relevant legal requirements including European Directives and CE marking.
—————————
1 Distribution Code Guidance Note 2/4 - December 2012. - http://www.energynetworks.info/the-distribution-code/
For all Small Scale Embedded Generators (SSEG) of up to 16A per phase, until 1 March 2014 it is permissible to connect to
the general requirements of previous versions of G83 provided this is through an Inverter or Controller with a protection/control
system that has either been fully type tested in accordance with G83/1-1, G83/2, G83/2-1 or in accordance with G59/2.
After 1 March 2014 it will only be allowable to connect SSEG of up to 16A per phase that complies with G83/2 or any
subsequently amended version of G83. .
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 6
2 Scope
This Engineering Recommendation provides guidance on the technical requirements for the
connection of Type Tested Small-Scale Embedded Generators (SSEGs) in parallel with
public low-voltage distribution networks. For the purposes of this Engineering
Recommendation a SSEG is a source of electrical energy rated up to and including 16 Ampere
per phase, single or multi- phase, 230/400 V AC.
This corresponds to 3.68 kilowatts (kW) on a single-phase supply and 11.04 kW on a three-
phase supply. The kW rating shall be based on the nominal voltage (ie 230V) as defined in BS
EN 50160 and the Electricity Supply Quality and Continuity Regulations (ESQCR).
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
SSEGs commissioned on after 27 April 2019 must comply with EREC G98. EREC G83 is not
applicable to generation commissioned on or after that date.
Where the SSEG includes an Inverter its rating is deemed to be the Inverter’s continuous
steady state rating.
The first connection procedure covers the connection of o n e o r more SSEG systems, either
single or multi-phase within a single Customer’s Installation.
Multiple SSEG systems shall be accepted within a single Customers Installation provided that
the aggregate rated capacity of the systems is not greater than 16A per phase 2.
The second connection procedure covers the connection of multiple SSEGs (other than within
a single Customer’s Installation) in a Close Geographic Region, under a planned
programme of work.
The generic requirements for all types of SSEG systems are defined in the main text of
this Engineering Recommendation, whilst the generic and technology specific type testing
requirements are defined in the annexes. The generic requirements relate to the connection,
installation and network design requirements for connection of a SSEG to a public low-
voltage Distribution System. SSEGs that are not Type Tested to conform to the requirements
of this document can only be connected via the guidelines laid down in Engineering
Recommendation G59.
Annexes A and B describe a methodology for testing the particular types of electrical interface
between the SSEG and the Distribution System whilst Annex C describes a methodology for
testing technology specific SSEG requirements. The purpose of the type tests is to demonstrate
compliance with the generic requirements of this Engineering Recommendation. By satisfying
the test conditions in the relevant annex the SSEG can be considered an approved SSEG for
connection to a public low-voltage Distribution System.
In the event that a new type testing annex is required then this should be formally initiated by
—————————
2 The manufacturer may restrict the rating of the SSEG by applying software settings provided these settings are not
accessible to the customer
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 7
The Appendices contain pro forma that relate to the connection, commissioning, type testing,
and decommissioning of SSEGs.
This document does not remove any statutory rights of an individual or organisation; equally it
does not remove any statutory obligation on an individual or organisation.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Connection agreements (ie the legal documentation supporting the connection of a SSEG),
energy trading and metering are considered to be out of scope. These issues are mentioned in
this document only in the context of raising the reader’s awareness to the fact that these
matters might need to be addressed
3 Normative References
The following referenced documents, in whole or part, are indispensable for the application of
this document. For dated references, only the edition cited applies. For undated references, the
latest edition of the referenced document (including any amendments) applies.
Standards publications
BS EN 50160
Voltage characteristics of electricity supplied by public electricity networks.
BS EN 50438
Requirements for the connection of micro-generators in parallel with public low-voltage
distribution networks.
BS EN 60034-4
Methods for determining synchronous machine quantities from tests.
BS EN 60255 series*
Measuring relays and protection equipment.
BS EN 60664-1
Insulation coordination for equipment within low-voltage systems – Part 1: Principles,
requirements and tests (IEC 60664-1:2007).
BS EN 60947 series*
Low Voltage Switchgear and Controlgear.
BS EN 61000-3-2
Limits for harmonic current emissions (equipment input current up to and including 16 A per
phase).
BS EN 61000-3-3
Limits – Limitation of voltage changes, voltage fluctuations and flicker in public low-voltage
supply systems, for equipment with rated current < 16A per phase and not subject to conditional
connection.
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 8
BS EN 61000 series*
Electromagnetic Compatibility (EMC).
BS EN 61508 series*
Functional safety of electrical/ electronic/ programmable electronic safety-related systems.
BS EN 61810 series*
Electromechanical Elementary Relays.
BS EN 62116
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
IEC 60255-5
Electrical relays. Insulation coordination for measuring relays and protection equipment.
Requirements and tests.
IEC 60725
Considerations or reference impedances for use in determining the disturbance characteristics
of household appliances and similar electrical equipment.
IEC 60909-1
Short circuit calculation in three-phase AC systems.
IEC 62282-3-2
Fuel cell technologies - Part 3-2: Stationary fuel cell power systems - Performance test methods.
*Where standards have more than one part, the requirements of all such parts shall be
satisfied, so far as they are applicable.
Other publications
Planning limits for voltage fluctuations caused by industrial, commercial and domestic equipment
in the United Kingdom.
NOTE: Defined terms are capitalised and in bold script where they are used in the main text of this report.
Alternating Current or AC
An electric current that reverses direction in a circuit at regular intervals.
Act
The Electricity Act 1989 (as amended by the Utilities Act 2000 and the Energy Act 2004).
Apparatus
All Equipment, in which electrical conductors are used, supported or of which they may form a
part.
Authority
The Gas and Electricity Markets Authority established under Section 1 of the Utilities Act 2000.
Circuit Breaker
An automatically operated electrical switch designed to protect an electrical circuit from damage
caused by overload or short circuit.
1) The postcodes of any of the premises where a SSEG installation is planned by the same
organisation are the same when the last two letters are ignored…i.e. AB1 2xx, where xx could
be any pair of letters or where x could be any letter.
2) The premises where a SSEG installation is planned by the same organisation are within
500m of each other.
Connection Point
An Entry Point or an Exit Point of the Distribution System as the case may be.
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 10
Controller
A device for controlling the functional operation of an SSEG.
Converter
The generic name for electronic architecture that, for the purpose of this recommendation,
converts either an alternating (AC) or direct (DC) current input into alternating current (AC)
output suitable for direct connection to the DNO’s Distribution System.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Customer
Any person supplied or entitled to be supplied with electricity at any premises within Great
Britain but shall not include any Authorised Electricity Operator in its capacity as such.
NOTE: Other documentation may use the term Consumer when making reference to the functions and/or
features that this document has attributed to the Customer.
Customer's Installation
The electrical installation on the Customer's side of the Exit Point together with any equipment
permanently connected or intended to be permanently connected thereto.
Direct Current or DC
The movement of electrical current flows in one constant direction, as opposed to Alternating
Current or AC, in which the current constantly reverses direction.
Distribution Code
A code required to be prepared by a DNO pursuant to condition 9 (Distribution Code) of a
Distribution Licence and approved by the Authority as revised from time to time with the
approval of, or by the direction of, the Authority.
Distribution Licence
A distribution licence granted under Section 6(1)(c) of the Act.
Distribution System
The electrical network operated by an Other Authorised Distributor.
Equipment
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 11
Embedded Generator
A Generator including a Customer With Own Generation whose Generating Units are
directly connected to the DNO’s Distribution System or to an Other Authorised Distributor
connected to the DNO’s Distribution System.
Entry Point
The point at which an Embedded Generator or other Users connect to the DNO’s Distribution
System where power flows into the DNO’s Distribution System under normal circumstances.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Exit Point
Means the ends of the electric lines at which the supply is delivered to a Customer’s Installation.
Generator
A person who generates electricity under licence or exemption under the Act.
Generation Set
Any Apparatus which produces electricity.
Generating Unit
Any Apparatus which produces electricity.
Great Britain or GB
The landmass of England & Wales and Scotland, including internal waters.
Installer
The person who is responsible for the installation of the SSEG.
Interface Protection
The electrical protection required to ensure that the SSEG is disconnected for any event that
could impair the integrity or degrade the safety of the Distribution System. This protection
will normally include the elements detailed in Table 1 of this Engineering Recommendation.
Inverter
A device for conversion from Direct Current to nominal frequency Alternating Current.
Islanding
Any situation where a section of electricity system, containing generation, becomes physically
disconnected from the DNO’s Distribution System or User’s Distribution System; and one
or more Generating Units maintains a supply of electrical energy to that isolated system.
Low Voltage or LV
In relation to Alternating Current, a voltage exceeding 50 volts but not exceeding 1000 volts.
Manufacturer
A person or organisation that manufactures SSEG and also ‘packages’ components
manufactured by others to make a SSEG which can be Type Tested to meet the requirements
of this Engineering Recommendation.
Meter Operator
A person, registered with the registration Authority, appointed by either a Supplier or Customer
to provide electricity meter operation services. (This Distribution Code does not place any direct
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 12
obligation on Meter Operators other than through the appointment by either a Supplier or a
Customer.)
Plant
Fixed and movable items used in the generation and/or supply and/or transmission of electricity
other than Apparatus.
Quality Factor, Qf
A measure of the strength of resonance of the Islanding test load.
Where Qf is quality factor, R is effective load resistance, C is reactive load capacitance (including
shunt capacitors), and L is reactive load inductance.
On a power system with active power, P, and reactive powers, QL, for inductive load, and QC for
capacitive load, Qf can be determined by:
Where P is active power, in W, QL is inductive load, in VAr, and QC is capacitive load, in VAr.
Supplier
(a) A person supplying electricity under an Electricity Supply Licence; or
(b) A person supplying electricity under exemption under the Act; in each case acting in its
capacity as a Supplier of electricity to Customers.
System
An electrical network running at various voltages .
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 13
Type Tested
An SSEG design which has been tested by the Manufacturer, component manufacturer or
supplier, or a third party, to ensure that the design meets the requirements of this Engineering
Recommendation, and for which the Manufacturer has declared that all products supplied will
be constructed to the same standards, and with the same protection settings as the tested
product.
User
A term used in various sections of the Distribution Code to refer to the persons using the DNO’s
Distribution System.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
This procedure will not apply where an Installer plans (within the next 28 days) or has already
installed (in the previous 28 days) other SSEGs in a Close Geographic Region; in this case
the procedure in 5.1.2 shall be followed. Failure to comply with this requirement may lead to the
disconnection of the Customer’s Installation under ESQCR (26) or failure of the SSEG to
operate as intended.
phases and neutral. The isolation switch shall be capable of being secured in the ‘off’ (isolated)
position.
The purpose of the Interface Protection is to ensure that the connection of a SSEG system will
not impair the integrity or degrade the safety of the DNO’s Distribution System. The interface
protection may be located in a separate unit or integrated into the SSEG (the Inverter in the
case of technologies which connect via an Inverter).
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
The DNO is responsible under the Distribution Code for ensuring, by design, that the voltage
and frequency at the Connection Point remains within statutory limits. The G83 Interface
Protection settings have been chosen to allow for voltage rise or drop within the Customer’s
Installation and to allow the SSEG to continue to operate outside of the statutory frequency
range as required in the Distribution Code.
The total disconnection time for voltage and frequency protection including the operating time
of the disconnection device shall be the trip delay setting with a tolerance of, -0 s + 0.5s.
For the avoidance of doubt voltage and frequency excursions lasting less than the trip delay
setting shall not result in disconnection.
—————————
3 For grid surge voltages greater than 230V +19% which are present for periods of <0.5s the SSEG is permitted to
reduce/cease exporting in order to protect the equipment.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 15
All settings shall be applied as shown in the above table, so that they can be inspected if required
by the DNO to confirm that the settings are correct. Only devices that have protection settings
set and locked during manufacture can be considered as Type Tested.
The Manufacturer needs to establish a secure way of displaying the settings in one of the
following ways.
correct device by means of a serial number permanently fixed to the device and visible
on the PC screen at the same time as the settings;
c) Display of all settings including nominal voltage and current outputs, alongside the
serial number of the device, permanently fixed to the device.
The provision of loose documents, documents attached by cable ties etc, a statement that the
device conforms to a standard, or provision of data on adhesive paper based products which
are not likely to survive due to fading, or failure of the adhesive, for at least 20 years is not
acceptable.
The Manufacturer must ensure that the Interface Protection is capable of measuring voltage
to an accuracy of ± 1.5% of the nominal value (± 3.45V) and of measuring frequency to ± 0.2%
of the nominal value (± 0.1Hz) across its operating range of voltage, frequency and temperature .
The SSEG shall be designed to withstand without adverse effect, voltage and frequency
variations within the settings shown in Table 1 plus the measurement error inherent in the
device itself.
The Interface Protection shall function correctly, ie operate within the required tolerance range
as given in the relevant annex, across the expected range of ambient operating temperatures
and other environmental factors.
Once the SSEG has been installed and commissioned the protection settings shall only be
altered following written agreement between the DNO and the Customer or his agent.
5.3.2 Loss of Mains Protection
Loss of mains protection shall be incorporated and tested as defined in the relevant annex.
Active methods which use impedance measuring techniques by drawing current pulses from
or injecting AC currents into the DNO’s system are not considered to be suitable. For
SSEGs which generate on more than one phase, the loss of mains protection should be able to
detect the loss of a single phase of the supply network. This should be tested during type testing
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 16
Under normal operation of the network the frequency changes over time due to continuous
unbalance of load and generation or can see a step change due to the loss of a network
component which does not cause a loss of supply.
In order to ensure that the phenomena do not cause un-necessary tripping of SSEG, stability
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
The Rate of Change of Frequency (RoCoF) and Vector Shift values required for this test are
marginally less than the corresponding protection settings for RoCoF protection in Table 1 and
vector shifts of up to 50º. Both stability tests shall be carried out in all cases.
The stability tests are to be carried out as per the table in Appendix 4 of this document and the
generator should remain connected during each and every test.
RoCoF - 0.95 Hz per second in the range 49.0Hz to 51.0Hz on both rising and falling
frequency
Vector shift - 50º plus from 49.5Hz and 50º minus from 50.5Hz
These standards were written on the basis that only a small number of devices would be installed
on an LV network and / or that the duration of operation would be short and therefore permits a
large diversity factor to be used.
—————————
4 Reference in accordance with BS EN 50438 (2007)
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 17
SSEGs are likely to be installed in large numbers on LV networks and they are likely to operate
for long periods with no diversity between them, and adjacent SSEGs are likely to be of the
same technology. Therefore in order to accommodate a high number of SSEGs on a network
the following procedures need to be applied when testing for harmonic current emissions and
flicker.
installed singly in an installation then this can be tested alone, for example a domestic CHP unit.
The maximum group size for the test is 3.68kW.
The results for all Inverters should be normalised to a rating of 3.68kW. The SSEG or group
shall meet the harmonic emissions of table 1 in BS EN 61000-3-2 with a scaling factor applied
as follows for each harmonic current;
Table 1 current limit × rating of SSEG being tested (kW) per phase / 3.68
The test must be carried out with a minimum of 2kW of rated SSEGs. Where an individual SSEG
is smaller than 2kW it should be tested as a group. However where a SSEG is designed to be
installed singly in an installation then this can be tested alone, for example a domestic CHP unit.
The maximum group size for the test is 3.68kW.
The SSEG or group shall meet the required dmax, dc, d(t), Pst, Plt requirements of BS EN 61000-
3-3 with a scaling factor applied as follows for each voltage change component.
dmax, dc, d(t), Pst, Plt × rating of SSEG being tested (kW) per phase / 3.68
The results for groups of Inverters should be normalised to a rating of 3.68kW and to the
standard source impedance. Single Inverters need to be normalised to the standard source
impedance, these normalised results need to comply with the limits set out in Appendix 4.
For voltage change and flicker measurements the following simplified formula is to be used to
convert the measured values to the normalised values where the power factor of the generation
output is 0.98 or above. Where it is less than 0.98 then compliance with the full requirements of
BS EN 61000-3-3 is required.
The duration of these tests need to comply with the particular requirements set out in the testing
notes for the technology under test and can be found in annex C.
Note: For wind turbines, flicker testing should be carried out during the performance tests
specified in IEC 61400-12-1. Flicker data should be recorded from wind speeds of 1m/s below
cut-in to 1.5 times 85% of the rated power. The wind speed range should be divided into
contiguous bins of 1m/s centred on multiples of 1m/s. The dataset shall be considered complete
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
when each bin includes a minimum of 10 minutes of sampled data. The highest value of each
parameter measured across the entire range of tests shall be recorded.
Note that as an alternative to Type Testing the supplier of a SSEG incorporating an Inverter
may give a guarantee that rates of change of output do not exceed the following ramp rate limits.
Output needs to ramp up at a constant rate
This exception to site testing does not apply to devices where the output changes in steps of
over 30ms rather than as a ramp function, a site test is required for these units.
Single phase units and two phase units in a three phase system, maximum ramp up rate 333
watts per second;
Two phase units in a split phase system and three phase units, maximum ramp up rate 860
watts per second.
It should be noted that units complying with this declaration are likely to be less efficient at
capturing energy during times when the energy source is changing.
For technologies other than wind turbines, testing should ensure that the controls or automatic
programs used produce the most unfavourable sequence of voltage changes.
5.5 DC Injection
The effects of, and therefore limits for, DC currents injected in the DNO’s Distribution System
is an area under current investigation by DNOs. Until these investigations are concluded the
upper limit for DC injection is 0.25% of AC current rating per phase. Where a SSEG is designed
to be installed singly in an installation, for example a domestic CHP unit, then this DC injection
limit can be a maximum value of 20mA for sub 2kW SSEG and can be tested alone,. Where
SSEGs are designed such that multiple units may be installed in an installation for example roof
mounted wind turbines and PV with micro Inverters on each panel, then they should be tested
as a group of at least 2kW and with a maximum group size of 4kW. Tests are to be carried out
a three power levels plus or minus 5%.
At 230V a 2kW single phase Inverter has a current output of 8.7A so DC limit is 21.75mA; a
10kW three phase Inverter has a current output of 14.5A per phase which is equivalent to a
total of 43.5A at 230V so DC limit is 108.75mA.
Where necessary the DC emission requirements can also be satisfied by installing an isolating
transformer between the Inverter and the connection to the DNO’s Distribution System.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 19
The Manufacturer shall establish the maximum short circuit current contribution from the
SSEG and the conditions under which this exists. This information shall be provided to the
DNO by the Installer as part of the commissioning notification as per Appendix 3.
One method for determining the short circuit current contribution is described below.
The short circuit current contribution of the SSEG shall be measured upon application of a
short circuit on the SSEG terminals (all phases / phase to neutral) with the SSEG operating
at rated output steady state conditions.
Current measurements shall be taken from application of fault until the time the fault has
been disconnected, following operation of the SSEG protection. A current decay plot shall be
produced for each phase from inception of the fault until SSEG has been disconnected – trip
time. The plot will need to show the highest value of peak short circuit current, eg for a SSEG
supplying a purely inductive load the highest value of peak short circuit current will result when
the fault is applied at a voltage zero. Where practicable the tests will need to determine values
for all of the relevant parameters listed in Table 3.
These parameters are described in IEC 60909-1, whilst this standard is primarily for three-
phase generators the methodology for determining these parameters can be applied to single-
phase generators.
However DNOs need to understand the contribution that they do make to system fault levels in
order to determine that they can continue to safely operate without exceeding design fault levels
for switchgear and other circuit components.
As the output from an Inverter reduces to zero when a short circuit is applied to its terminals, a
short circuit test does not represent the worst case scenario; in most cases the voltage will not
collapse to zero for a network fault.
A test which ensures that at least 10% of nominal voltage remains and which allows the SSEG
to feed into a load with an X to R ratio of 2.5 is specified as details in Annex A4.6 for common
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Inverter requirements.
For multiple installations of SSEGs (eg in new housing developments), balancing the SSEGs
evenly against the load on the three phases will need to be considered by the DNO.
5.9.1 General
Type Tested certification is the responsibility of the SSEG Manufacturer. The requirements are
detailed in Appendix 4.
5.9.2 Compliance
The SSEG shall comply with all relevant European Directives and should be labelled with a CE
marking.
6.2 Labelling
The Installer shall provide labelling at the Exit Point (Fused Cut Out), meter position, consumer
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 21
unit and at all points of isolation between the Exit Point and the SSEG within the User’s
premises to indicate the presence of a SSEG. The labelling should be sufficiently robust and if
necessary fixed in place to ensure that it remains legible and secure for the lifetime of the
installation. The following sign shall be used.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Note: The safety sign does not imply a right on the Customer, User, Installer or maintainer to
operate (remove / replace) the DNO’s cut-out fuse.
In addition to the safety labelling, this Engineering Recommendation requires the following, up
to date, information to be displayed at the point of interconnection with the DNO’s
Distribution System.
a) A circuit diagram relevant to the installation showing the circuit wiring, including all
protective devices, between the SSEG and the DNOs fused cut-out. This diagram should
also show by whom all apparatus is owned and maintained;
Figure 2 shows an outline example of the type of circuit diagram that will need to be displayed.
Figure 2 is non-prescriptive and is for illustrative purposes only.
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 22
Customers Installation
Export
Meter Meter
Operator’s
Installation
Equipment Location:
Outside Meter Box
DNO’s
Distribution
System Cut-out
Equipment Location:
Outside Meter Box
The Installer shall advise the User that it is the User’s responsibility to ensure that this safety
information is kept up to date. The installation operating instructions shall contain the
Manufacturer’s contact details eg name, telephone number and web address.
6.4 Earthing
When a SSEG is operating in parallel with a DNO’s Distribution System there shall be no
direct connection between the SSEG current carrying conductors and earth with the following
exception;
For a SSEG which is designed to operate in parallel with a DNO’s Distribution System
but which is connected via an Inverter (eg a PV array or fuel cell) it is permissible to connect
one pole of the DC side of the Inverter to the DNO’s earth terminal if the insulation between
the AC and the DC sides of the Inverter meets the requirements for at least simple separation.
The requirements for simple separation are those given in Section 5.3.3 of BS EN 60664-1 for
basic insulation. In such cases the Installer and Manufacturer shall take all reasonable
precautions to ensure that the SSEG system will not impair the integrity of the DNO’s
Distribution System and will not suffer unacceptable damage for all credible operating
conditions, including faults on the DNO’s Distribution System. In all cases the level of DC
injection should not exceed that detailed under clause 5.5.
Earthing of all exposed conductive parts shall comply with the requirements of BS 7671.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 23
7.1 General
The information required by a DNO under an Application for Connection is shown in Appendix
2. The information required by a DNO to confirm commissioning is shown in Appendix 3.
It is the responsibility of the Installer to ensure that the relevant information is forwarded to the
local DNO in accordance with the requirements of 5.1.1 and/or 5.1.2 as appropriate. The pro
forma in Appendices 2 and 3 are designed to:
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
a) simplify the connection procedure for both DNO and SSEG Installer;
b) provide the DNO with all the information required to assess the potential
impact of the SSEG connection on the operation of the network;
c) inform the DNO that the SSEG installation complies with the requirements of this
Engineering Recommendation;
d) allow the DNO to accurately record the location of all SSEGs connected to
the network.
Compliance with the requirements detailed in the relevant annex in addition to those cited in
sections 5 and 6 will ensure that the SSEG is considered to be approved for connection to the
DNO’s Distribution System. It is intended that the Manufacturers of SSEG systems will use
the requirements of this Engineering Recommendation to develop type verification certification
for each of their SSEG models.
Upon receipt of a multiple premises connection application the DNO’s response will be in
accordance with the electricity generation standards set by the Authority for applications for
connection to the network.
No parameter relating to the electrical connection and subject to type verification certification
will be modified unless previously agreed in writing between the DNO and the Customer or
his agent. User access to such parameters shall be prevented.
As part of the on-site commissioning tests the Installer shall carry out a functional check of
the loss of mains protection, for example by removing the supply to the SSEG during operation
and checking that the Interface Protection operates to disconnect the SSEG from the DNO’s
Distribution System. For three phase installations this test can be achieved by opening a three
phase Circuit Breaker or isolator and confirming that the SSEG has shut down. Testing for the
loss of a single phase is covered in the type testing of Inverters see section 5.3.2
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 24
If during the lifetime of the SSEG it is necessary to replace a major component of the SSEG, it
is only necessary to notify the DNO if the operating characteristics of the SSEG or the
Interface Protection have been altered when compared against the unit that was originally
commissioned.
In the event that a SSEG system is to be decommissioned and will no longer operate as a
source of electrical energy in parallel with the DNO’s Distribution System, the User shall notify
the DNO by providing the information as detailed under Appendix 5.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 25
NOTE: The processes shown here only refer to the interface between the Installer and the DNO. It may also be
necessary for the Installer / User to inform the relevant Meter Operator and Supplier that a SSEG has been
installed.
Single/multiple SSEGs
Planned installation of
within a single
multiple SSEGs in the
Customer’s Installation.
same Close Geographic
Region.
Installer Details
Installer
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Accreditation/Qualification:
Address
Post Code
Contact person
Telephone Number
E-mail address
Post Code
MPAN
SSEG owner if different from above
Name and
Contact Address
Post code
Contact person
Telephone number
E:mail address
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 28
Solar PV 1 Wind 2
Marine 17 Nuclear 18
SSEG Type
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Address
Tel Fax
Connection Option
kW single phase, single, split or three phase system
Maximum rated kW three phase
capacity, use separate
sheet if more than one kW two phases in three phase system
connection option.
kW two phases split phase system
Note that testing can be done by the manufacturer of an individual component, by an external
test house, or by the supplier of the complete system, or any combination of them as
appropriate.
Where parts of the testing are carried out by persons or organisations other than the supplier
then the supplier shall keep copies of all test records and results supplied to them to verify
that the testing has been carried out by people with sufficient technical competency to carry
out the tests.
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 30
Power Quality. Harmonics. The requirement is specified in section 5.4.1, test procedure in
Annex A or B 1.4.1
SSEG rating per phase (rpp) kW NV=MV x 3.68/rpp
21
0.160
0.107
22
0.084
23 0.147
0.098
24
0.077
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
25 0.135
0.090
26
0.071
27 0.124
0.083
28
0.066
29 0.117
0.078
30
0.061
31 0.109
0.073
32
0.058
33 0.102
0.068
34
0.054
35 0.096
0.064
36
0.051
37 0.091
0.061
38
0.048
39 0.087
0.058
40
0.046
Note the higher limits for odd harmonics 21 and above are only allowable under certain
conditions, if these higher limits are utilised please state the exemption used as detailed in
part 6.2.3.4 of BS EN 61000-3-2 in the box below.
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 32
Power Quality. Voltage fluctuations and Flicker. The requirement is specified in section
5.4.2, test procedure in Annex A or B 1.4.3
Starting Stopping Running
dmax dc d(t) dmax dc d(t) Pst Plt 2 hours
Measured
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Values
Normalised
to standard
impedance
and 3.68kW
for multiple
units
Limits set 4% 3.3% 3.3% 4% 3.3% 3.3% 1.0 0.65
under BS EN 500ms 500ms
61000-3-2
Test location
Power quality. DC injection. The requirement is specified in section 5.5, test procedure in
Annex A or B 1.4.4
Test power 10% 55% 100%
level
Recorded
value
as % of
rated AC
current
Limit 0.25% 0.25% 0.25%
Power Quality. Power factor. The requirement is specified in section 5.6, test procedure
in Annex A or B 1.4.2
216.2V 230V 253V Measured at three voltage levels and at
full output. Voltage to be maintained
Measured within ±1.5% of the stated level during the
value test.
Limit >0.95 >0.95 >0.95
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 33
Protection. Frequency tests The requirement is specified in section 5.3.1, test procedure in
Annex A or B 1.3.3
Function Setting Trip test “No trip tests”
Frequency Time Frequency Time Frequency Confirm no trip
delay delay /time
U/F stage 1 47.5Hz 20s 47.7Hz
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
25s
U/F stage 2 47Hz 0.5s 47.2Hz
19.98s
46.8Hz
0.48s
O/F stage 1 51.5Hz 90s 51.3Hz
95s
O/F stage 2 52Hz 0.5s 51.8Hz
89.98s
52.2Hz
0.48s
Protection. Voltage tests The requirement is specified in section 5.3.1, test procedure in
Annex A or B 1.3.2
Function Setting Trip test “No trip tests”
Voltage Time Voltage Time Voltage Confirm no trip
delay delay /time
U/V stage 1 200.1V 2.5s 204.1V
3.5s
U/V stage 2 184V 0.5s 188V
2.48s
180V
0.48s
O/V stage 1 262.2V 1.0s 258.2V
2.0s
O/V stage 2 273.7V 0.5s 269.7V
0.98s
277.7V
0.48s
Note for Voltage tests the Voltage required to trip is the setting ±3.45V. The time delay can
be measured at a larger deviation than the minimum required to operate the protection. The
No trip tests need to be carried out at the setting ±4V and for the relevant times as shown in
the table above to ensure that the protection will not trip in error.
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 34
Protection. Loss of Mains test. The requirement is specified in section 5.3.2, test
procedure in Annex A or B 1.3.4
To be carried out at three output power levels with a tolerance of plus or minus 5% in Test
Power levels.
Test Power 10% 55% 100% 10% 55% 100%
Balancing load 95% of 95% of 95% of 105% of 105% of 105% of
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Note as an alternative, inverters can be tested to BS EN 62116. The following sub set of
tests should be recorded in the following table.
Test Power and 33% 66% 100% 33% 66% 100%
imbalance -5% Q -5% Q -5% P +5% Q +5% Q +5% P
Test 22 Test 12 Test 5 Test 31 Test 21 Test 10
Trip time. Limit is
0.5s
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 35
Protection. Frequency change, Vector Shift Stability test. The requirement is specified
in section 5.3.3, test procedure in Annex A or B 1.3.6
Start Change End Confirm no trip
Frequency Frequency
Positive Vector Shift 49.5Hz +50 degrees
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Fault level contribution. The requirement is specified in section 5.7, test procedure in Annex
A or B 1.4.6
For a directly coupled SSEG For a Inverter SSEG
Additional comments
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 37
SSEG de-commissioning form and declaration, to be provided to the DNO by the installer no
later than 28 days after de-commissioning all, or some of the SSEGs in a Customer’s
Installation.
To ABC electricity distribution DNO or IDNO
99 West St, Imaginary Town, ZZ99 9AA [email protected]
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Post Code
MPAN
I confirm that the SSEG installation noted above has been modified or totally de-
commissioned and continues to comply with the requirements of G83 as required by the
distribution code of Great Britain. I enclose a copy of the system schematic which has been
left on site at the customers incoming meter location.
Name Signed Date
On behalf of Installer
Accreditation / Qualification
Installer address
Post code
Contact person
Telephone number
E:mail address
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 38
Certificate of Exemption
1. The Health and Safety Executive, in pursuance of the powers conferred on it by section
33 of the Electricity Safety Quality and Continuity Regulations 2002 (the “Regulations”)
Health & Safety At Work Etc Act 1974 ( as amended by the Legislative Reform ( Health
and Safety Executive) Order 2008) and by the Agreement dated 2 October 2006
between the Secretary of State for Trade and Industry and the Health and Safety
Commission, and being satisfied as required by regulation 33(2) hereby grants an
exemption to the person or persons installing the source of energy from the requirements
imposed by regulation 22(2)(c) of the regulations subject to the condition set out in
paragraph 2 of this certificate.
This certificate shall come into force on 4 August 2008 and will remain in force until
revoked by the Health and Safety Executive by a certificate in writing.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 39
An SSEG requiring type testing must be Type Tested in relation to its grid connection type and
its energy source technology.
Annex A relates to any SSEG that uses an Inverter (or Converter) as its means of connecting
to the grid.
Annex B relates to any SSEG that during normal running operation is connected directly to the
grid.
When type testing any SSEG you must select either Annex A or Annex B as is most appropriate
to the grid connect method relating to the SSEG under test.
The SSEG may also require additional technology specific type tests as identified in Annex C,
this annex relates to the Technology relating to the energy source.
Examples
A Wind Turbine system using an Inverter (or Inverters) for connection is required to type test
using Annex A – “Common Inverter Requirements” and Annex C5 – “Wind” Separate Specific
Technology Requirements”.
A Hydro system using an induction motor connected directly to the grid is required to be Type
Tested using Annex B – “Directly Coupled Requirements” and Annex C4– “Hydro” of Annex C
- “Separate Specific Technology Requirements”.
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 40
This Annex describes a methodology for obtaining type certification or type verification for the
interface equipment between the Inverter connected SSEG and the distribution network.
Typically, all interface functions are contained within the Inverter and in such cases it is only
necessary to have the Inverter Type Tested. Alternatively, a package of specific separate parts
of equivalent function may also be Type Tested.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Other Annexes containing Inverter connected equipment may make reference to the
requirements specified in this Annex.
This Annex applies for SSEG systems either with or without load management or energy
storage systems which connected on the generator side of the Inverter.
The type verification procedure requires that the SSEG interface be certified to the relevant
requirements of the applicable Directives before the unit can be labelled with a CE mark. Where
the protection control is to be provided as a separate device, this must also be Type Tested
and certified to the relevant requirements of the applicable Directives before it can be labelled
with a CE mark.
Currently there are no harmonised functional standards that apply to the SSEG Interface
Protection, therefore the Inverter and any separate Interface Protection unit will require
functional Type Tested as described in this Annex, and recorded in format similar to that shown
in Appendix 4.
Type Testing is the responsibility of the Manufacturer. This test will verify that the operation
of the SSEG Interface Protection shall result:
a) in the safe disconnection of the SSEG from the DNO’s Distribution System in
the event that the protection settings specified in table 1 are exceeded; and
b) in the SSEG remaining connected to the DNO’s Distribution System while
network conditions are:
a. within the envelope specified by the settings plus and minus the
tolerances specified for equipment operation in table 1; and
b. within the trip delay settings specified in table 1.
The Type Testing can be done by the Manufacturer of an individual component, by an external
test house, or by the supplier of the complete system, or any combination of them as appropriate.
Wherever possible the Type Testing of an Inverter designed for a particular type of SSEG
should be proved under normal conditions of operation for that technology (unless otherwise
noted).
This will require that the chosen SSEG Interface Protection is either already incorporated
into the Inverter or that the discrete device is connected to the Inverter for the loss of mains
protection test. Testing the voltage and frequency functions may be carried out on the discrete
protection device independently or on the Inverter complete.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 41
In either case it will be necessary to verify that a protection operation will disconnect the
SSEG from the DNO’s Distribution System.
The minimum trip delay settings, for tests in A3.2, A3.3 and A3.4, are presented in table 1.
For tests A3.2, A3.3 and A3.4, reconnection shall be checked as detailed in A3.5 below.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
To establish a trip voltage, the test voltage should be applied in steps of ± 0.5% or less, of the
nominal voltage for a duration that is longer than the trip time delay, for example 1 second in the
case of a delay setting of 0.5 second starting at least 4V below or above the setting. The test
voltage at which this trip occurred is to be recorded. Additional tests just above and below the
trip voltage should be undertaken to show that the test is repeatable and the figure at which a
repeatable trip occurs should be recorded on the type verification test report Appendix 4 of this
Engineering Recommendation.
To establish the trip time, the test voltage should be applied starting from 4V below or above the
recorded trip voltage and should be changed to 4V above or below the recorded trip voltage in
a single step. The time taken from the step change to the SSEG tripping is to be recorded on on
the type verification test report Appendix 4 of this Engineering Recommendation.
To establish correct ride-through operation, the test voltage should be applied at each setting
plus or minus 4V and for the relevant times shown in the table in Appendix 4.
For example to test overvoltage setting stage 1 which is required to be set at nominally 262.2V
the circuit should be set up as shown below and the voltage adjusted to 254.2 volts. The
Inverter should then be powered up to export a measureable amount of energy so that it can
be confirmed that the Inverter has ceased to output energy. The variable voltage supply is
then increased in steps of no more than 0.5% of nominal (1.15V) maintaining the voltage for at
least 1.5 seconds ( trip time plus 0.5 seconds) at each voltage level. At each voltage level
confirmation that the Inverter has not tripped after the time delay is required to be taken. At the
voltage level at which a trip occurs then this should be recorded as the provisional trip
voltage. Additional tests just below and if necessary just above the provisional trip voltage will
allow the actual trip voltage to be established on a repeatable basis. This value should be
recorded. For the sake of this example the actual trip level is assumed to have been established
as being 261V. The variable voltage supply should be set to 257V the Inverter set to produce
a measureable output and then the voltage raised to 265V in a single step. The time from the
step change to the output of Inverter falling to zero should be recorded as the trip time.
The Inverter then needs to operate at 4 volts below the nominal overvoltage stage 1 setting
which is 258.2V for a period of at least 2 seconds without tripping and while producing a
measurable output. This can be confirmed as a no trip in the relevant part of Appendix 4. The
voltage then needs to be stepped up to the next level of 269.7V for a period of 0.98 seconds
and then back to 258.2V during which time the output of the relay should continue with no
interruption though it may change due to the change in voltage, this can be recorded as a no
trip for the second value. The step up and step down test needs to be done a second time with
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 42
a max value of 277.7V and with a time of 0.48 seconds. The Inverter is allowed to shut down
during this period to protect its self as allowed by note 2 of Table 1 of this document, but it must
resume production again when the voltage has been restored to 258.2V or it may continue to
produce an output during this period. There is no defined time for resumption of production but
it must be shown that restart timer has not operated so it must begin producing again in less
than 20 seconds.
Note that this philosophy should be applied to the under voltage, over and under frequency,
RoCoF and Vector shift stability tests which follow.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Note:
(1) The frequency required to trip is the setting plus or minus 0.1Hz
(2) Measurement of operating time should be measured at a value of 0.2Hz (suggestion
– 2 x tolerance) above/below the setting to give “positive” operation
(3) The “No trip tests” need to be carried out at the relevant values and times as shown in the
table above to ensure that the protection will not trip in error.
SSEG
Variable AC
SSEG or Inverter
Voltage Test
Simulator
Supply
The Inverter shall be tested by operating the Inverter in parallel with a low impedance, variable
frequency test supply system, see figure A3. Correct protection and ride-through operation
should be confirmed during operation of the Inverter. The set points for over and under
frequency at which the Inverter system disconnects from the supply will be established by
varying the test supply frequency.
To establish a trip frequency, the test frequency should be applied in a slow ramp rate of less
than 0.1Hz/second, or if this is not possible in steps of 0.05Hz for a duration that is longer than
the trip time delay, for example 1 second in the case of a delay setting of 0.5 second. The test
frequency at which this trip occurred is to be recorded. Additional tests just above and below
the trip frequency should be undertaken to show that the test is repeatable and the figure at
which a repeatable trip occurs should be recorded on the type verification test report Appendix
4 of this Engineering Recommendation.
To establish the trip time, the test frequency should be applied starting from 0.3Hz below or
above the recorded trip frequency and should be changed to 0.3Hz above or below the recorded
trip frequency in a single step. The time taken from the step change to the SSEG tripping is to
be recorded on the type verification test report Appendix 4 of this Engineering Recommendation.
It should be noted that with some loss of mains detection techniques this test may result in a
faster trip due to operation of the loss of mains protection. There are two ways around this.
Firstly the loss of mains protection may be able to be turned off in order to carry out this test.
Secondly by establishing an accurate frequency for the trip a much smaller step change could
be used to initiate the trip and establish a trip time. This may require the test to be repeated
several times to establish that the time delay is correct.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 43
To establish correct ride-through operation, the test frequency should be applied at each setting
plus or minus 0.2Hz and for the relevant times shown in the table in Appendix 4.
SSEG
Variable
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
The tests should be carried out in accordance with BS EN 62116 and a subset of results should
be recorded as indicated in the Protection – Loss of Mains test section of Annex 4 Type Test
Verification Report.
.
A1.3.5 Re-connection
Further tests will be carried out with the three test circuits above to check the Inverter time out
feature prior to automatic network reconnection. This test will confirm that once the AC supply
voltage and frequency have returned to be within the stage 1 settings specified in table 1
following an automatic protection trip operation there is a minimum time delay of 20 seconds
before the Inverter output is restored (ie before the Inverter automatically reconnects to the
network).
The tests will be carried out using the same circuit as specified in A1.3.3 above and following
confirmation that the SSEG has passed the under and over frequency trip tests and the under
and over frequency stability tests.
Four tests are required to be carried out with all protection functions enabled including loss of
mains. For each stability test the SSEG should not trip during the test.
For the step change test the SSEG should be operated with a measurable output at the start
frequency and then a vector shift should be applied by extending or reducing the time of a
single cycle with subsequent cycles returning to the start frequency. The start frequency
should then be maintained for a period of at least 10 seconds to complete the test. The SSEG
should not trip during this test.
For frequency drift tests the SSEG should be operated with a measurable output at the start
frequency and then the frequency changed in a ramp function at 0.95Hz per second to the end
frequency. On reaching the end frequency it should be maintained for a period of at least 10
seconds. The SSEG should not trip during this test.
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 44
A1.4.1 Harmonics
The tests should be carried out as specified in BS EN 61000-3-2 and can be undertaken with a
fixed source of energy at two power levels firstly between 45 and 55% and at 100% of maximum
export capacity.
The test set up shall be such that the Inverter supplies full load to the DNO’s Distribution
System via the power factor (pf) meter and the variac as shown below in figure A5. The Inverter
pf should be within the limits given in 5.6, for three test voltages 230 V –6%, 230V and 230 V
+10%.
SSEG
DNO’s
SSEG or Inverter
p Variac Distribution
Simulator System
f
NOTE 1 For reasons of clarity the points of isolation are not shown.
NOTE 2: It is permissible to use a voltage regulator or tapped transformer to perform this test
rather than a variac as shown.
The voltage fluctuations and flicker emissions from the SSEG shall be measured in
accordance with BS EN 61000-3-3 and technology specific annex.
A1.4.4 DC Injection
Where appropriate the protection shall comply with the requirements of BS7671.
Inverter connected SSEG’s generally have small short circuit fault contributions however DNO’s
need to understand the contribution that they do make to system fault levels in order to
determine that they can continue to safely operate without exceeding design fault levels for
switchgear and other circuit components.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 45
The following type tests shall be carried out and the results noted in Appendix 4.
Test circuit
B
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
230v A
AC C DC supply
50Hz to suit
V D Inverter
inverter
under test
Test procedure
‘A’ and ‘V’ are ammeters and voltmeters used to record the test data required. Component ‘D’
is a resistive load plus resonant circuit as required for the loss of mains test as specified in BS
EN 62116 set up to absorb 100% rated output of the Inverter. Component ‘a’ is an ammeter
used to confirm that all the output from the Inverter is being absorbed by component D.
Components ‘B’ and ‘C’ are set up to provide a voltage of between 10% and 40% of nominal
when component ‘C’ carries the rated output of the Inverter in Amps.
Component ‘C’ should be short term rated to carry the load which would appear through it should
it be energised at 253V for at least 1s. Component ‘B’ is to have an impedance of between 10
and 20 ohms per phase. If components ‘B’ and ‘C’ are short time rated than an additional switch
in series with ‘B’ and ‘C’ can be inserted and arranged to be closed shortly before the main
change over switch shown on the drawing and opened at the end of the test period.
Components ‘B’ and ‘C’ are to have an X to R ratio of 2.5 to 1.
The test is carried out by setting up the Inverter and load ‘D’ to produce and then absorb full
rated output of the Inverter. When zero export is shown by ammeter ‘a’ then the changeover
switch shown is operated connecting the Inverter to the reduced voltage connection created by
components ‘B’ and ‘C’ and disconnecting if from the normal connection. The make contact is
an early make and the break contact a late break so that the inverter is not disconnected from
a mains connection for any significant time.
The values of voltage and current should be recorded for a period of up to 1 second when the
changeover switch should be returned to the normal position. The voltage and current at
relevant times shall be recorded in the type test report (Appendix 4) including the time taken for
the Inverter to trip. (It is expected that the Inverter will trip on either loss of mains or under
voltage in less than one second).
Some Inverters include solid state switching devices to disconnect from the DNO’s
Distribution System. In this case 5.3.1 requires the control equipment to monitor the output
stage of the Inverter to ensure that in the event of a protection initiated trip the output voltage is
either disconnected completely or reduced to a value below 50 volts AC. This shall be
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 46
All equipment shall comply with the generic EMC standards: BS EN61000-6-3: 2007
Electromagnetic Compatibility, Generic Emission Standard; and BS EN61000-6-1: 2007
Electromagnetic Compatibility, Generic Immunity Standard.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 47
This Annex describes a methodology for obtaining type certification or type verification for the
interface equipment between a directly coupled SSEG and the distribution network. Interface
functions can be provided by either as an integrated part of the controller or by incorporating a
Type Tested protection relay.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Other Annexes containing directly coupled equipment may make reference to the requirements
specified in this Annex.
This Annex applies for SSEG systems either with or without load management or energy storage
systems which connected on the generator side of the controller.
The type verification procedure requires that the SSEG interface be certified to the relevant
requirements of the applicable Directives before the unit can be labelled with a CE mark. Where
the protection control is to be provided as a separate device, this must also be Type Tested
and certified to the relevant requirements of the applicable Directives before it can be labelled
with a CE mark.
Currently there are no harmonised functional standards that apply to the SSEG Interface
Protection, therefore the Controller and any separate Interface Protection unit will require
the functionality to be Type Tested as described in this Annex, and recorded in format similar
to that shown in Appendix 4.
Type verification testing is the responsibility of the Manufacturer. This test will verify that the
operation of the SSEG Interface Protection shall result:
a) in the safe disconnection of the SSEG from the DNO’s Distribution System in
the event that the protection settings specified in table 1 are exceeded; and
b) in the SSEG remaining connected to the DNO’s Distribution System while
network conditions are:
a. within the envelope specified by the settings plus and minus the tolerances
specified for equipment operation in table 1; and
b. within the trip delay settings specified in table 1.
The testing can be done by the Manufacturer of an individual component, by an external test
house, or by the supplier of the complete system, or any combination of them as appropriate.
Wherever possible the type verification testing of the SSEG control system should be proved
under normal conditions of operation for that technology (unless otherwise noted).
This will require that the chosen SSEG Interface Protection is either already incorporated
into the Controller or that the discrete device is connected to the Controller for the loss of
mains protection test. Testing the voltage and frequency functions may be carried out on the
discrete protection device independently or as part of the Controller.
In either case it will be necessary to verify that a protection operation will disconnect the
SSEG from the DNO’s Distribution System
The Manufacturer must declare the ambient operating temperature range of the SSEG, and
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 48
verify that the Interface Protection will operate satisfactorily throughout this temperature
range.
The minimum trip delay settings, for tests in B3.2, B3.3 and B3.4, are presented in table 1.
For tests B3.2, B3.3 and B3.4, reconnection shall be checked as detailed in 5.3.4 as a
mechanical based system.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
In some systems it may be safer and more convenient to test the trip delay time and the
disconnection time separately. This will allow the trip delay time to be measured in a test
environment (in a similar way as you could test a protection relay). The disconnection time can
be measured in the SSEG’s normal operation, allowing accurate measurement with correct
inertia and prime mover characteristics. This is permitted providing the total disconnection time
does not exceed the value specified in section 5.3.1. When measuring the shutdown time, 5
shutdowns should be initiated, and the average time recorded.
The Controller shall be tested by operating the Controller in parallel with a variable AC
test supply, see figure B2. Correct protection and ride-through operation shall be confirmed.
The set points for over and under voltage at which the Controller disconnects from the supply,
will be established by varying the AC supply voltage. The disconnect sequence should be
initiated when the conditions of table 1 are met, otherwise normal operation should continue.
To establish the certified trip voltage, the test voltage should be applied in steps of ± 0.5% of
setting for a duration that is longer than the trip time delay, for example 1 second in the case of
a delay setting of 0.5 second. It will be necessary to carry out five tests for each trip setting. The
test voltage at which this trip occurred is to be recorded as the certified trip voltage.
To establish the certified trip time, the test voltage should be applied starting from ± 4V below
the certified trip voltage in a step of at least ± 0.5% of setting for a duration that is longer than
the trip time delay, for example 1 second in the case of a delay setting of 0.5 second. It will be
necessary to carry out five tests for each trip setting. The longest trip time is to be recorded as
the certified trip time.
For example to test overvoltage setting stage 1 which is required to be set at nominally 262.2V
the circuit should be set up as shown below and the voltage adjusted to 254.2 volts. The
Inverter should then be powered up to export a measurable amount of energy so that it can be
confirmed that the Inverter has ceased to output energy. The variable voltage supply is then
increased in steps of no more than 0.5% of nominal (1.15V) maintaining the voltage for at least
1.5 seconds ( trip time plus 0.5 seconds) at each voltage level. At each voltage level
confirmation that the Inverter has not tripped after the time delay is required to be taken. At the
voltage level at which a trip occurs then this should be recorded as the provisional trip
voltage. Additional tests just below and if necessary just above the provisional trip voltage will
allow the actual trip voltage to be established on a repeatable basis. This value should be
recorded. For the sake of this example the actual trip level is assumed to have been established
as being 261V. The variable voltage supply should be set to 257V the Inverter set to produce
a measurable output and then the voltage raised to 265V in a single step. The time from the
step change to the output of Inverter falling to zero should be recorded as the trip time.
To establish correct ride-through operation, the test voltage should be applied at each setting
plus or minus 4V and for the relevant times shown in the table in Appendix 4.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 49
SSEG
Variable AC
Generator Controller Voltage Test
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
Supply
The protection shall be tested by operating the SSEG in parallel with a low impedance,
variable frequency test supply system, see figure B3. Correct protection and ride-through
operation should be confirmed during operation of the SSEG. The set points for over and
under frequency at which the SSEG system disconnects from the supply will be established
by varying the test supply frequency.
To establish a trip frequency, the test frequency should be applied in a slow ramp rate of less
than 0.1Hz/second, or if this is not possible in steps of 0.05Hz for a duration that is longer
than the trip time delay, for example 1 second in the case of a delay setting of 0.5 second.
The test frequency at which this trip occurred is to be recorded. Additional tests just above
and below the trip frequency should be undertaken to show that the test is repeatable and the
figure at which a repeatable trip occurs should be recorded on the type verification test report
Appendix 4 of this Engineering Recommendation.
To establish the trip time, the test frequency should be applied starting from 0.3Hz below or
above the recorded trip frequency and should be changed to 0.3Hz above or below the
recorded trip frequency in a single step. The time taken from the step change to the SSEG
tripping is to be recorded on the type verification test report Appendix 4 of this Engineering
Recommendation. It should be noted that with some loss of mains detection techniques this
test may result in a faster trip due to operation of the loss of mains protection. There are two
ways around this. Firstly the loss of mains protection may be able to be turned off in order to
carry out this test. Secondly by establishing an accurate frequency for the trip a much
smaller step change could be used to initiate the trip and establish a trip time. This may
require the test to be repeated several times to establish that the time delay is correct.
To establish correct ride-through operation, the test frequency should be applied at each
setting plus or minus 0.2Hz and for the relevant times shown in the table in Appendix 4.
SSEG
Variable
Generator Controller
Frequency
Test Supply
The resonant test circuit specif ied in this test has been designed to model the interaction
of the directly coupled SSEG under test with the local load including multiple directly coupled
connected SSEGs in parallel.
The directly coupled SSEG output shall be connected to a network combining a resonant
circuit with a Q factor of >0.5 and a variable load. The value of the load is to match the
directly coupled SSEG output. To facilitate the test for LoM there shall be a switch placed
between the test load/directly coupled SSEG combination and the DNO’s Distribution System,
as shown below:
SSEG
DNO’s
Generator Controller Distribution
System
Resonant
Variable
Circuit
Resistance
Q>0.5
Load
at 50Hz
The directly coupled SSEG is to be tested at three levels of the directly coupled SSEG’s
output power: 10%, 55% and 100% and the results recorded on the test sheet of Appendix 4.
For each test the load match is to be within ± 5%. Each test is to be repeated five times.
Load match conditions are defined as being when the current from the directly coupled
SSEG meets the requirements of the test load ie there is no export or import of supply frequency
current to or from the DNO’s Distribution System.
The tests will record the directly coupled SSEG’s output voltage and frequency from at least 2
cycles before the switch is opened until the protection system operates and disconnects itself
from the DNO’s Distribution System, or for five seconds whichever is the lower duration.
The time from the switch opening until the protection disconnection occurs is to be measured
and must comply with the requirements in table 1.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 51
B1.3.5 Re-connection
Further tests will be carried out with the three test circuits above to check the directly coupled
SSEG time- out feature prior to automatic network reconnection. This test will confirm that once
the AC supply voltage and frequency have returned to within the stage 1 settings specified in
table 1 following an automatic protection trip operation there is a minimum time delay as specified
in table 1 before reconnection will be allowed.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
The tests will be carried out using the same circuit as specified in B1.3.3 above and following
confirmation that the SSEG has passed the under and over frequency trip tests and the under
and over frequency stability tests.
Four tests are required to be carried out with all protection functions enabled including loss of
mains. For each stability test the SSEG should not trip during the test.
For the step change test the SSEG should be operated with a measurable output at the start
frequency and then a vector shift should be applied by extending or reducing the time of a
single cycle with subsequent cycles returning to the start frequency. The start frequency
should then be maintained for a period of at least 10 seconds to complete the test. The SSEG
should not trip during this test.
For frequency drift tests the SSEG should be operated with a measurable output at the start
frequency and then the frequency changed in a ramp function at 0.95Hz per second to the end
frequency. On reaching the end frequency it should be maintained for a period of at least10
seconds. The SSEG should not trip during this test.
B1.4.1 Harmonics
The tests should be carried out as specified in BS EN 61000-3-2 and can be undertaken with a
fixed source of energy at two power levels firstly between 45 and 55% and at 100% of maximum
export capacity.
The test set up shall be such that the directly coupled SSEG supplies full load to the DNO’s
Distribution System via the power factor (pf) meter and the variac as shown below in figure B5.
The directly coupled SSEG pf should be within the limits given in 5.6, for three test voltages 230
V –6%, 230V and 230 V +10%.
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 52
SSEG
DNO’s
Generator Controller
p Variac Distribution
f System
NOTE 1. For reasons of clarity the points of isolation are not shown
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
NOTE 2: It is permissible to use a voltage regulator or tapped transformer to perform this test rather
than a variac as shown
The voltage fluctuations and flicker emissions from the SSEG shall be measured in accordance
with BS EN 61000-3-3 and technology specific annex.
B1.4.4 DC Injection
The level of DC injection from the directly coupled SSEG to the DNO’s Distribution System
shall not exceed the levels specified in 5.5. In a directly coupled SSEG, any harmonics present
will be as a result of any electronic components, with in the Controller and can be measured at
0% load.
Where appropriate the protection shall comply with the requirements of BS7671.
DNOs need to understand the contribution an SSEG makes to system fault levels in order to
determine that they can continue to safely operate without exceeding design fault levels for
switchgear and other circuit components.
For rotating machines and linear piston machines the test should produce a 0 – 2 second plot
of the short circuit current as seen at the SSEG terminals.
*Values for parameters marked in Annex 4 should be provided where the short circuit duration
is sufficiently long to enable interpolation of the plot.
All equipment shall comply with the generic EMC standards: BS EN61000-6-3: 2007
Electromagnetic Compatibility, Generic Emission Standard; and BS EN61000-6-1: 2007
Electromagnetic Compatibility, Generic Immunity Standard.
ENA Engineering Recommendation G83
Issue 2 Amendment 2 2019
Page 53
For Domestic CHP SSEGs connected to the DNO’s Distribution System via an Inverter, the
type verification testing and Interface Protection requirements will be as per the requirements
defined in Annex A.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
For Domestic CHP SSEGs directly coupled to the DNO’s Distribution System, the type
verification testing and Interface Protection requirements will be as per the requirements
defined in Annex B.
C1.2 Photovoltaic
As all current Photovoltaic SSEGs will connect to the DNO’s Distribution System via an
Inverter, the type verification testing and Interface Protection requirements will be as per the
requirements defined in Annex A.
C1.4 Hydro
Hydro can be connected to the DNO’s Distribution System directly using induction or
synchronous generators or it can be connected by an Inverter.
The common requirements for the generator technologies will apply to micro hydro in addition
the following needs to be taken into consideration.
SSEGs with manually fixed output or where the output is fixed by controlling the water flow
through the turbine to a steady rate, need to comply with the maximum voltage change
requirements of BS EN 61000-3-2 but do not need to be tested for Pst or Plt.
SSEGs where the output is controlled by varying the load on the generator using the Inverter
and which therefore produces variable output need to comply with the maximum voltage change
requirements of BS EN 61000-3-2 and also need to be tested for Pst and Plt over a period where
the range of flows varies over the design range of the turbine with a period of at least 2 hours at
each step with there being 10 steps from min flow to maximum flow. Pst and Plt values to
recorded and normalised as per the method laid down in
Appendix 4.
C1.5 Wind
Wind turbines can be connected to the DNO’s Distribution System directly, typically using
asynchronous induction generators, or using Inverters.
For those connected via Inverters, the type verification testing and interface protection
requirements shall be as specified in Annex A.
For those connected directly to the DNO’s Distribution System, the type verification testing
and interface protection requirements shall be as specified in Annex B.
ENA Engineering Recommendation G83
Issue 2 Amendment 3 2019
Page 54
In addition, in either case, the note regarding wind turbine voltage flicker testing specified in 5.4
shall apply.
Energy Storage Devices can be connected to the DNO’s Distribution System directly or using
Inverters.
Supplied by ENA to: Paul Meeke (BV). Delivered to: [email protected] on 07/04/2025 at 15:27. © ENA 2025 Unauthorised sharing or distribution is prohibited.
For those connected via Inverters, the type verification testing and interface protection
requirements shall be as specified in Annex A.
For those connected directly to the DNO’s Distribution System, the type verification testing
and interface protection requirements shall be as specified in Annex B.